PRE-CONSTRUCTION ACTIVITIES CONTINUE

 

Second shift operations will continue on the river from 3:30 p.m. to 12 midnight on weekdays in preparation for permanent construction activities.

This work is primarily to support activities for the daytime pile driving operations and is limited by the project’s noise level restrictions. Pile driving will be limited to the hours of 7 a.m. to 7 p.m. on weekdays and, occasionally, from 12 noon to 7 p.m. on Saturdays.

Construction of the Rockland County trestle will continue. This work will include daytime pile driving to install the temporary foundation piles needed to support the platform. The trestle is a work platform that will support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required.

From Tuesday, October 15 to Friday, October 18, one southbound right hand lane and shoulder on I-87/I-287 between exit 9 and exit 11 will be closed from 9 a.m. to 3 p.m. for shoulder work.

Additionally, utility work will continue on River Road in South Nyack. This work will be performed from 6:30 a.m. to approximately 6 p.m. for the next three weeks and has been coordinated with and approved by the Village of South Nyack. The work will reduce the roadway to one lane during daytime hours and flaggers will be onsite to safely direct motorists on River Road. During non-work hours, the road will have temporary coverings in place that may create uneven surfaces. Motorists and bicyclists should slow down and use extreme caution in the area.

Mariners should be aware that TZC will be installing piles in the vicinity of the side channels. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area.

If necessary, the Coast Guard in the future may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website, NewNYBridge.com, under the boating safety icon.

E-ZPass tags are now available for purchase at the New NY Bridge Community Outreach Centers in Tarrytown and Nyack.

The pre-packaged E-ZPass tags can be purchased for $25 and are ready for immediate use. E-ZPass users avoid delays when traveling through toll plazas, receive a discount on every Thruway toll they pay, and enjoy the convenience of using E-ZPass in fifteen states: Delaware, Illinois, Indiana, Maine, Maryland, Massachusetts, New Hampshire, New Jersey, New York, North Carolina, Ohio, Pennsylvania, Rhode Island, Virginia, and West Virginia.

E-ZPass tags have a $25 value and are active upon purchase. The first $15 is immediately available for toll usage, and the remaining $10 becomes available once the tag is registered online or by phone. E-ZPass provides a five percent savings on Thruway tolls and offers toll discounts on many other roadways.

The Community Outreach Centers for the new bridge project were established last year as a gathering place and source of information for the community regarding the New NY Bridge. They are located at:

• 303 South Broadway in Tarrytown, and
• 142 Main Street in Nyack.

The centers are open Monday through Friday, 11 a.m. to 7 p.m.; Saturday and Sunday, 11 a.m. to 4 p.m.

Ongoing operations:

• Dredging operations will continue 24/7

• Test pile program

• Rockland Dock Extension under existing bridge

• Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.

• Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.

• Survey inspections on existing bridge

• Support for river-based work from the Rockland shoreline