The New NY Bridge February Newsletter!

February 2016
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives
CLICK HERE FOR COMPLETE ISSUE!

Tappan Zee Constructors, LLC (TZC) recently installed the 650th concrete road deck panel for the westbound span. TZC began placing the panels in early October and is on track to install an additional 6,000 panels by year’s end. The work is occurring on top of recently-installed steel-blue girders, which continue to advance across the Hudson River.

PROJECT UPDATE – WESTCHESTER GIRDER INSTALLATION

update

For immediate release: Nov. 19, 2015

WESTCHESTER GIRDER INSTALLATION OVER METRO-NORTH RAILROAD TRACKS CONTINUES THIS FRIDAY EVENING
Overnight Closures of the I-87/I-287 Exit 10 On-Ramp Scheduled for Nov. 19 and Nov. 20

Next week, Tappan Zee Constructors, LLC (TZC) will continue installing structural steel girder assemblies from the new bridge’s Westchester landing in Tarrytown. The assemblies will connect the future westbound span’s on-land abutment to the first offshore support pier in the Hudson River. TZC is installing the girders by literally pushing them west over the Metro-North Railroad Hudson Line’s tracks toward the first pier in the river, as seen in this animation. As the operation progresses, additional girders are being connected to the assembly and pushed farther westward. TZC is closely coordinating the effort with Metro-North Railroad, ensuring that the operation maximizes safety for both workers and the public and minimizes impacts to rail service.

With the entire operation anticipated to conclude by the end of the year, the remaining work over the Metro-North tracks will occur during two Friday overnights, with the next scheduled for this Friday evening, Nov. 20. Metro-North has adjusted its schedule slightly to allow the work to be completed. TZC will suspend construction activities when commuter trains pass through the area, resuming when given the “all clear” instruction by Metro-North.

Across the river, TZC has completed steel girder installation near the Rockland shoreline, connecting the new bridge’s abutment to already-installed support structures in the Hudson River.

The I Lift NY super crane will continue placing larger girders across the river, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

All-Electronic Toll Collection Gantry Work
Construction of the project’s temporary all-electronic toll collection (AETC) system in Rockland will continue near the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to southbound New York State Thruway (I-87/I-287). The work will necessitate closing the on-ramp during the overnights of Thursday, Nov. 19 and Friday, Nov. 20. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the graphic below. No lane closures are planned for this work next week.

Ramp Closures Near the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Thu., 11/19 9 p.m. – Ramp Closure 5 a.m., Fri., 11/20 Southbound I-87/I-287
exit 10 on-ramp
Fri., 11/20 9 p.m. – Ramp Closure 5 a.m., Sat., 11/21 Southbound
exit 10 on-ramp

Tower Construction
Construction will continue on the new bridge’s iconic towers, which will eventually rise 419 feet above the river. Innovative self-climbing jump forms enable TZC workers to build the towers in segments that progressively “jump” up from the foundations to their full height. Within the jump forms, workers assemble steel reinforcement cages that are then encased in concrete, one segment atop the previous one and so on. Eight towers will be constructed on the project’s football-field-long main span pile caps over the coming year, as seen in this animation.

Deck Panel Installation
TZC is continuing to install nearly 6,000 high-strength concrete deck segments for the new crossing’s approach spans. Project cranes are lifting the prefabricated deck panels into place atop previously-installed structural steel girders. The deck segments are prefabricated at an off-site location and barged down river from the project’s Port of Coeymans facility in Albany County. TZC will continue installing the approach span deck sections over the coming year.

Installation of Noise Barriers in South Nyack
Next week will see continued removal of the noise walls located along the northbound Thruway and the construction of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road in South Nyack. The work involves drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
Westchester and Rockland Marine Units are continuing extensive patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

###

Project Update: Electronic Tolling System Requires Overnight Closures

For immediate release: Nov. 12, 2015

THRUWAY UNVEILS UPDATED PROJECT WEBSITE
All-Electronic Tolling System Work Requires Overnight Closure of Exit 10 On-Ramp on Friday, Nov. 20

The New York State Thruway Authority launched an updated NewNYBridge.com this week, featuring an easier-to-navigate interface, a comprehensive archive of project photos, videos and renderings, and a wealth of background information covering how the new crossing was studied and designed and is being built. Visit the new site and check back frequently for the latest updates on the fast-moving construction progress.

Steel Girder Installation
Tappan Zee Constructors, LLC (TZC) will continue installing steel girders near the Rockland shoreline, connecting the new bridge’s abutment to already-installed support structures in the Hudson River. Safely accomplishing the work will require reducing River Road/Piermont Avenue to one lane during weekdays between 6 a.m. to 5 p.m. Flag persons will keep traffic moving by alternating the directional flow between north and south. TZC also will hold traffic on River Road once daily between 9 a.m. and 3 p.m. for up to 20 minutes through Wednesday, Nov. 18 to enable the safe movement of girders and other materials.

Across the river, TZC will continue installing structural steel girder assemblies from the new bridge’s Westchester landing in Tarrytown. The assemblies will connect the future westbound span’s on-land abutment to the first offshore support pier in the Hudson River. TZC is installing the girders by literally pushing them west over the Metro-North Railroad Hudson Line’s tracks toward the first pier in the river, as seen in this animation. As the operation progresses, additional girders are being connected to the assembly and pushed farther westward. TZC is closely coordinating the effort with Metro-North, ensuring that the operation maximizes safety for both workers and the public and minimizes impacts to rail service.

With the entire operation anticipated to conclude by the end of the year, the remaining work over the Metro-North tracks will occur during two Friday overnights, one in November and one in December. The work will be announced in advance to enable Metro-North riders to plan ahead. Metro-North has adjusted its schedule slightly to allow the work to be completed. TZC will suspend construction activities when trains pass through the area, resuming when given the “all clear” instruction by Metro-North.

Additionally, the I Lift NY super crane will continue placing larger girders across the Hudson River, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

All-Electronic Toll Collection Gantry Work
Construction of the project’s temporary all-electronic toll collection (AETC) system in Rockland will continue near the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to southbound New York State Thruway (I-87/I-287). The work will necessitate closing the on-ramp during the overnight of Friday, Nov. 20. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the graphic below. The work also requires double-lane closures during weekday overnights from Monday, Nov. 16 through Thursday, Nov. 19. This and other work require the specific lane and ramp closures detailed in the chart below.

Lane and Ramp Closures Near the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Thu., 11/12 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Fri., 11/13 Southbound I-87/I-287
from exit 12 to exit 10
Fri., 11/13 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Sat., 11/14 Southbound
from exit 12 to exit 10
Mon., 11/16 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Tue., 11/17 Southbound
5 a.m., Tue., 11/17
Tue. 11/17 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Wed., 11/18 Southbound
from exit 12 to exit 10
Wed., 11/18 8 p.m. – One left lane
9 p.m. – Two left lanes
5 a.m., Thu., 11/19 Southbound
from exit 12 to exit 10
Thu., 11/19 8 p.m. – One left lane
9 p.m. – Two left lanes
5 a.m., Fri., 11/20 Southbound
from exit 12 to exit 10
Fri., 11/20 9 p.m. – Ramp closure 5 a.m., Sat., 11/21 Southbound
exit 10 on-ramp

Tower Construction
Construction will continue on the new bridge’s iconic towers, which will eventually rise 419 feet above the river. Innovative self-climbing jump forms enable TZC workers to build the towers in segments that progressively “jump” up from the foundations to their full height. Within the jump forms, workers assemble steel reinforcement cages that are then encased in concrete, one segment atop the previous one and so on. Eight towers will be constructed on the project’s football-field-long main span pile caps over the coming year, as seen in this animation.

Deck Panel Installation
TZC is continuing to install nearly 6,000 high-strength concrete deck segments for the new crossing’s approach spans. Project cranes are lifting the prefabricated deck panels into place atop previously-installed structural steel girders. The deck segments are prefabricated at an off-site location and barged down river from the project’s Port of Coeymans facility in Albany County. TZC will continue installing the approach span deck sections over the coming year.

Installation of Noise Barriers in South Nyack
Next week will see continued construction of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road in South Nyack. The work involves drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
Westchester and Rockland Marine Units are continuing extensive patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

###

The New NY Bridge July Newsletter

July 2015
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

Heavy Metal:

Bridge Starts Taking Shape with Installation of First Section of Structural Steel


Following months of careful planning and with the use of the project’s king of cranes, the New NY Bridge team installed the span’s first section of structural steel on June 17: a 410-foot segment of welded girders that will support the road deck.

READ MORE

With the 2015 recreational boating season hitting full stride this weekend as boaters celebrate Independence Day on the water, the New NY Bridge project team and local law enforcement officials remain committed to helping all boaters navigate safely near the work area. Boaters are reminded to be extra vigilant around commercial vessels and the construction zone, especially the no-wake low-speed zone at the Tappan Zee Bridge.

 

READ MORE

Oyster reefs were once a predominant feature of the Hudson River, supporting vast and diverse communities of aquatic life. But past decades of pollution and overharvesting led to a decline in oyster populations in the area to near-extinction. In recent years, however, there have been promising signs of recovery.

 

 READ MORE

The addition of a third floating concrete batch plant this week enables the New NY Bridge project to shift into an even higher gear. Capable of delivering 180 cubic yards of concrete per hour – more than twice as much as the initial two batch plants combined – the new mixing platform will supply concrete for the new bridge’s remaining foundations and piers as well as its 419-foot towers, which will begin later this summer.

 

READ MORE

After a stunningly beautiful trip down the Hudson River, the first 12′ tall, 400′ long section of structural steel arrived at the New NY Bridge construction site on Thursday June 10, 2015. The girder sections, weighing up to 1,100 tons are assembled at the Port of Coeymans in Albany County and then barged to the project site. The trip can take from 12 to 20 hours depending on weather, tides and other conditions. The individual steel girders, totaling 31 miles in length before assembly, are all made in the USA and will support the road deck of the new twin span bridge. The girders will be set in place by the I Lift NY crane in the coming days.

 

 READ MORE

Frequently Asked Questions
Q:
How can my company apply for subcontracting work on the project?
A:
Businesses interested in obtaining contracts for the New NY Bridge project should reach out to Tappan Zee Constructors, LLC through the TZC website, TappanZeeConstructors.com.
Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates
HOW TO GET INVOLVED
Follow Us on Twitter

@NewNYBridge

Call the Project Hotline

1-855-TZBRIDGE

(1-855-892-7434)

Community Outreach Centers

Westchester: 2 N. Broadway, Tarrytown, NY

Rockland: 142 Main Street, Nyack, NY

Mon-Fri: 11am-7pm | Sat-Sun: 11am-4pm

Visit the Project Website
Email Us
Construction Viewing Platform

Scenic Hudson RiverWalk Park, Tarrytown, NY

Next to the Tarrytown Senior Center at
240 West Main St.

©2015 New York State Thruway Authority

June 2015 New NY Bridge Newsletter

June 2015
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

The Votes Are In, Tappan Zee Falcon Chicks Are ‘Hudson, Bridge-ette and Zee’:

A Day After Being Named, Falcon Chicks Make Inaugural Flights


Following a week-long campaign in which more than 3,000 ballots were cast, the New NY Bridge project is pleased to announce the winners of its 2015 falcon naming poll: Hudson, Bridge-ette and Zee received the greatest number of votes among 10 candidate names provided by local elementary schools.

READ MORE

When it came to designing the lighting of the New NY Bridge, the project team’s strategy was twofold: accentuate the architectural features of the iconic crossing while at the same time respecting the context in which it is built: the historic Hudson Valley. To achieve this balance-while also maintaining high standards of efficiency and safety-the team engaged Domingo Gonzalez Associates, (DGA) a leading architectural lighting design firm based in New York City.

 

 READ MORE

The New NY Bridge project held its annual public meetings in Westchester and Rockland on May 12 and 14, respectively, to give residents an in-depth briefing about construction progress to date and what lies ahead for the largest bridge and highway project in the nation.

 

READ MORE

The New NY Bridge project crossed another milestone this week with the installation of the first precast pier cap. These large concrete fixtures sit atop completed pier columns and eventually will support the new bridge’s road deck.

 

READ MORE

With the 2015 recreational boating season now underway, the New NY Bridge project team’s partnership with local officials is further enhancing safety on the waters of the Hudson River. As construction intensifies this summer, helping all boaters navigate safely near the work area is a top priority for the project team.

 

 READ MORE

Frequently Asked Questions
Q:
How many lanes will the new bridge have?
A:
The new twin-span bridge will have eight general traffic lanes – four in each direction. Space will also be provided for disabled vehicles, emergency responders and express buses and/or bus rapid transit.
Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates
HOW TO GET INVOLVED
Follow Us on Twitter

@NewNYBridge

Call the Project Hotline

1-855-TZBRIDGE

(1-855-892-7434)

Community Outreach Centers

Westchester: 2 N. Broadway, Tarrytown, NY

Rockland: 142 Main Street, Nyack, NY

Mon-Fri: 11am-7pm | Sat-Sun: 11am-4pm

Visit the Project Website
Email Us
Construction Viewing Platform

Scenic Hudson RiverWalk Park, Tarrytown, NY

Next to the Tarrytown Senior Center at
240 West Main St.

©2015 New York State Thruway Authority

Traffic Update thru Jan 4th to Ease Holiday Travels

For immediate release: December 26, 2014

ALL LANES OF NEW YORK STATE THRUWAY (I-87/I-287) WILL REMAIN OPEN FROM FRIDAY DEC. 26, 2014 THROUGH SUNDAY, JAN. 4, 2015 TO EASE HOLIDAY TRAVEL

All lanes of the New York State Thruway (I-87/I-287) will remain open from Friday, Dec. 26, 2014 through Sunday, Jan. 4, 2015 to help New Yorkers reach their winter holiday destinations. The 10-day lane-closure-free period follows Governor Andrew M. Cuomo’s “Drivers First” initiative, which gives priority to motorists by ensuring that disruptions associated with highway and bridge projects are kept as minimal as possible.

While Tappan Zee Constructors, LLC (TZC) will continue working in several areas of the project during the week of Dec. 29, none of the planned activities will result in the closure of any traffic lanes. No construction work is scheduled for New Year’s Day, Thursday, Jan. 1, 2015, though safety and security teams will remain on site.

Limited concrete placement will continue as TZC progresses the investigation of the recent incident on one of its floating concrete batch plants. The concrete for foundations near the S. Nyack shoreline will be acquired from local concrete suppliers that will be delivered to the site via trucks to the Rockland Trestle off of the New York State Thruway southbound access ramp. The trucks will exit the trestle to the Thruway via the northbound access ramp. This work could begin as soon as this week.

Activities on the Westchester and Rockland landings will continue as originally scheduled as this work has always been planned to receive the needed concrete from trucks to the site.

Continued Demolition of Westchester Landing of Existing Tappan Zee Bridge
Following the removal of sections of deck of the existing Tappan Zee Bridge to make way for the new bridge, the associated supporting piers are being demolished. The majority of this work, which will clear the path for the northbound bridge’s landing and first foundation pier, will be completed during daytime hours.

Pile Driving and Other Construction Activity
Construction will continue in the Hudson River as crews place the foundations of the new bridge. Work will include pile driving from 7 a.m. to 7 p.m., Monday through Wednesday and noon to 7 p.m., Saturday. No pile driving will occur on New Year’s Day, Thursday, Jan. 1, 2015. Operations will resume on Friday, Jan. 2, 2015 at 7 a.m.

A second shift of workers also will continue pile welding, pile cleanout and concrete placement operations associated with foundations.

Work is continuing on the new bridge’s landings on both sides of the river.

Additional work includes:

  • Pile cap foundation construction
  • Main span foundation construction
  • River Road utility work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on existing bridge

Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions

New NY Bridge Project Monthly Newsletter_ November 2014

November 2014
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

Enter the Super Crane:

I Lift NY Arrives at the New NY Bridge Project 


 Following a 6,000 mile journey that included transit through the Panama Canal, the New NY Bridge project’s I Lift NY super crane arrived at the Hudson River construction site on October 6.

READ MORE

October 16, 2014 marked the first anniversary of permanent construction operations on the New NY Bridge project, and the past year has seen exceptional progress on the foundations of the new crossing. Looking ahead, the project is poised to make even greater and more visible strides in the coming year.

 

 READ MORE 

I Lift NY Completes Journey
I Lift NY Completes Journey
 

The I Lift NY super crane arrived at the New NY Bridge site on October 6. Here is a video of the powerful lifter completing the last leg of its 6,000-mile journey.

 

 READ MORE 

Led by the recently-arrived I Lift NY super crane, an armada of more than 30 floating cranes – each capable of raising immense structural elements with great precision – is hard at work lifting and placing many millions of pounds of components and materials to help build the New NY Bridge. These workhorse machines are critical to keeping the project on schedule for completion in 2018.

 

 READ MORE

Now in its second year, the New NY Bridge Educational Outreach Program continues to engage students of all ages in Westchester, Rockland and beyond. The program reflects Governor Andrew Cuomo’s goal of using the state’s largest infrastructure project to educate tomorrow’s professionals. This year, the team is focusing on the ‘how-it-works’ engineering behind the new bridge’s foundations.

 

 READ MORE 

Those keen on observing firsthand the progress of the New NY Bridge project are invited to the recently-opened Westchester viewing platform in Tarrytown’s Scenic Hudson RiverWalk Park. Located near the Tarrytown Senior Center at 240 West Main Street, the easy-to-access platform provides an unobstructed view of the project site.

 

READ MORE

Frequently Asked Questions
Q: What will happen to the current bridge?
A: The current Tappan Zee Bridge will be carefully dismantled and the structural steel will be recycled. The concrete deck panels, which have been replaced in recent years, will be reused where possible on other Thruway and state Department of Transportation projects.

 

http://campaign.r20.constantcontact.com/render?ca=d87df910-023c-4eb5-b9f6-bcac7d294151&c=4897cfb0-a650-11e3-bc68-d4ae5292c426&ch=49f6ea80-a650-11e3-bcd8-d4ae5292c426

Going Vertical First Columns Rise out of the Hudson

 

Following extensive pile installation and other foundation work in the Hudson River over the past year, the first permanent, vertical elements of the New NY Bridge are beginning to take shape: Two 40-foot steel cage towers now stand near the Westchester shore. Soon—with the addition of high-strength concrete—the first pier for the westbound span will be created.

“Everything we’ve been doing to date has been below the surface. This new work is giving people the first opportunity to see the bridge rising above the water,” noted Thruway Authority Construction Compliance Engineer Tom McGuinness.

The columns—over 130 in total—eventually will support the steel girders and deck of the new bridge. The girders and decking will be lifted in place by the soon-to-arrive I Lift NY super crane.

The steel cage frameworks for the piers are pre-assembled at a site several miles upriver. The rebar cages are transported to the project site by barge and lifted into place by floating cranes.

After the steel cages are carefully inspected, they are filled with concrete produced by the project’sfloating batch plants. Enclosing forms are erected around the frameworks to enable the concrete to set in the shape of the piers that will hold up the new twin-span structure.

The floating concrete batch plants maneuver around the river, mixing the precise amount of concrete required and using an extending arm to apply the material directly into the frameworks. The concrete flows around the steel cages and eventually hardens to form steel-reinforced concrete. The composite material is remarkably strong and capable of supporting the new bridge for the next century or more.

The New NY Bridge project remains on schedule and on budget as it approaches the one-year anniversary of new bridge construction that began with permanent pile installation in October 2013. Local residents can expect to see more and more vertical pier structures rise out of the river in the coming months as construction progress continues.

September 26, 2014 |

T.Z. viewing areas in Nyack, Tarrytown to open this fall

The public will be able to see construction up close and learn all about the mega-project.

The two designated spots from which people can watch the new Tappan Zee Bridge get built are likely to open in October.

The sites will be at parks in Nyack and Tarrytown and feature view finders, seats and detail-rich panels about constructing the world’s widest bridge.

Even though the river villages share a common goal, they are working separately to build their respective viewing areas.

Local officials anticipate the spots will prove to be tourist draws, and entice people to spend money at village shops and restaurants.

Nyack

Rockland’s viewing area is piggybacking on a long-planned conversion of the fishing pier at the southern end of Memorial Park.

The village is planning to hold a groundbreaking during the first week of August, Mayor Jen Laird-White said. It had already secured a $150,000 grant from New York’s state department when Tappan Zee project officials approached it about using the 90-foot long pier as an official vantage point.

Laird-White called it “frosting on the cake” since the village would receive $50,000 to make the pier even more of an attraction.

Village trustees last Thursday awarded a contract for installation of the piles for the pier.

Pile driving is expected to begin in late August followed by decking, Village Administrator Jim Politi said.

“Once you set the pilings, which I’m sure will take a couple of weeks, then building the actual structure is another couple of weeks,” he said.

From that point, Politi said it was just a matter to adding the decorative lighting, fancy wood railings and the bridge-related materials.

The viewing area should be ready in October, he said.

Tarrytown

Village trustees last week authorized a $50,000 contract with the state Thruway Authority to move forward on the viewing area at RiverWalk Park at the end of West Main Street, Village Administrator Mike Blau said. Both Tarrytown and Nyack are receiving funding through a special $20 million community fund set up for the project. The Thruway Authority and bridge builder Tappan Zee Constructors are jointly contributing to it.

Once the village receives the technical specifications from the Thruway’s design consultant, it will put the project out to bid, likely in mid-August.

After the bids are received and one selected, Blau expects work will begin in mid- to late September.

“It shouldn’t take that long to actually do the construction end of this project,” he said, anticipating an early October opening date.

According to project renderings, a tiered timber bench will be added to the existing round deck that’s largely enclosed by a stone wall. A pergola will provide shade for visitors.

Three colorful interpretive panels will offer a bevy of information: from an overview of the construction site to design and features of the $3.9 billion bridge to a project schedule. A “spotter’s guide” for the different types of equipment being used on the river may prove most popular of all.

Besides describing what each vessel does, the guide also offers a factoid about each one. For example, the super crane registered as the Left Coast Lifter is longer than a football field while one floating concrete batch plant can produce enough concrete to fill 100 cement trucks in a single day.

There is no mention of tolls.

Twitter: @ksaeed1

Obama, at Tappan Zee Bridge, pushes transportation funding

The president will seek to rally support for more federal dollars for highway and bridge improvements.

TARRYTOWN – With the new Tappan Zee Bridge taking shape behind him, President Barack Obama on Wednesday urged Congress to inject billions of dollars in the nation’s transportation infrastructure to keep Americans working and encourage businesses to stay.

During his first visit to Westchester as president, Obama praised the progress on the new $3.9 billion crossing, which is replacing the 58-year-old crumbling structure.

“It carries a lot more traffic than when it was built back in 1955,” Obama said under sunny skies at Sunset Cove, a restaurant at the Washington Irving Boat Club. “At times, you can see the river through the cracks in the pavement. Now, I’m not an engineer, but I figure that’s not good.”

Highlights from President Obama’s speech on the country’s infrastructure at near the Tappan Zee Bridge in Tarrytown. (Video by Peter Carr/The Journal News)

He noted the new Tappan Zee will be the first new bridge in New York in 50 years and announced the federal government plans to apply the same “fast track” process to 11 other infrastructure projects, including Boston’s South Station and light rail around Seattle.

“Normally it would have taken three to five years to permit this bridge,” Obama said during his 10-minute speech. “We did it in a year and a half.”

With the Tappan Zee Bridge as a backdrop, President Barack Obama speaks from the Washington Irving Boat Club in Tarrytown May 14, 2014. The President spoke about the need for Congress to fund road and bridge improvements across the nation.

With the Tappan Zee Bridge as a backdrop, President Barack Obama speaks from the Washington Irving Boat Club in Tarrytown May 14, 2014. The President spoke about the need for Congress to fund road and bridge improvements across the nation.  (Photo: Seth Harrison/The Journal News)

He also called out congressional Republicans for blocking funding that would pay for modern highways, bridges and seaports.”We’ve got more than 100,000 bridges that are old enough to qualify for Medicare,” Obama said.Officials have warned that funding in the federal Highway Trust Fund is set to run out by the fall, which would put 112,000 active road and bridge projects and 5,600 transit projects at risk, along with nearly 700,000 jobs.”That’s like the population of Tampa and St. Louis combined,” the president said, citing the jobs figure.

“So far at least Republicans who run this Congress seem to have a different priority,” Obama said. “Rebuilding America — that shouldn’t be a partisan issue.”

Obama emphasized that “there is work to be done.”

“So the bottom line, Tarrytown, is America doesn’t stand still. … So I’m going to keep on fighting alongside all of you to make sure that we’re doing everything we can to rebuild America – not just rebuild one bridge, but I want us to rebuild every bridge. I don’t want us to just rebuild one school, I want us to rebuild every school that needs help.”

 His administration in late 2011 named replacing the Tappan Zee Bridge, which carries 138,000 vehicles a day, a top infrastructure priority. The process moved quickly from there, with environmental reviews fast-tracked and in 2013, the New York State Thruway Authority received a record $1.6 billion federal loan.

Under New York Gov. Andrew Cuomo, the state approved a process that allows infrastructure project to be designed while construction begins.

Cuomo, who introduced the president, has been praised for reviving the project, which had been stagnating for nearly a decade. It’s now in its second year of construction with completion projected for 2018.

With preparations in place for President Obama’s visit to the TZ Bridge construction site, minority construction workers protest about being shut out of major construction projects. (Video by Joe Larese/ The Journal News)

“We are the state of the bold. We are the state of the daring,” Cuomo said. “We are the state of performance. We are the state of skyscrapers, intricate transit systems. We are the state of public works that challenge the imagination.”

Also in attendance, seated to the back, was Westchester County Executive Rob Astorino, the Republican who is planning to challenge Cuomo this fall. He criticized the governor before the speech for not discussing the cost of future tolls.

“The public has a right to know before the election,” Astorino said. “They know what it’s going to be. They promised last year we would have answers.”

Astorino accused the governor’s staff of refusing to allow him to sit in the front. Cuomo’s office, however, denied it meddled with the seating chart. An official who attended the speech said Astorino spent more than an hour talking with reporters and that by the time he tried to claim a seat, the choice ones were taken.

But all eyes were on the president who wore a crisp dark suit and dark blue tie against a background of construction equipment and steel piles. Obama joked and shook hands with many of the 250 people who were invited to attend, including elected officials, construction workers and residents.

Chris Junge of Tarrytown brought his two children, Tucker, 8, and Cassie, 6. The family walked from home to the event.

“It was exciting to be that close. It was personal,” Junge said. “It was a long day for them but I think they will remember it.”

Arriving at John F. Kennedy International, Obama flew aboard Marine One to Tarrytown. He traveled by motorcade the short distance to the marina. Less than 30 minutes after he arrived, Obama was back off to New York City to attend two Democratic party fundraisers in the evening.

Reporter Brian Tumulty contributed to this story.

Twitter: @ksaeed1

http://www.lohud.com/story/news/local/tappan-zee-bridge/2014/05/14/obamas-tappan-zee-bridge-speech-set-mid-afternoon/9080115/

New NY Bridge Update January 03, 2014: NEW NY BRIDGE PROJECT SUSPENDS OPERATIONS TODAY, TOMORROW DUE TO WINTER STORM

For immediate release: January 03, 2014

NEW NY BRIDGE PROJECT SUSPENDS OPERATIONS TODAY, TOMORROW DUE TO WINTER STORM

Due to severe weather conditions, Tappan Zee Constructors, LLC (TZC), suspended scheduled project operations for today and tomorrow, but a small crew remains on site to continuously monitor conditions and respond immediately to any weather-related issues.

Normal operations are scheduled to resume Monday, as crews continue construction of the foundation of the New NY Bridge with the ongoing installation of permanent piles.

Subsurface utility investigations will take place in Tarrytown the week of Jan. 6. To facilitate this operation, the northbound right-hand lane of the New York State Thruway (I-87/I-287) near the approach to the Tappan Zee Bridge in Tarrytown will be closed on Monday, Jan. 6 and Tuesday, Jan. 7, from 10 a.m. to 3 p.m.

>From Tuesday, Jan. 7, through Thursday, Jan. 9, the northbound right-hand lane and shoulder of the Thruway (I-87/I-287) near exit 10 in Nyack will be closed from 10 a.m. to 3 p.m. The same section of roadway will be closed on Friday, Jan. 10, from 10 a.m. to 1 p.m., to allow for work on the northbound maintenance ramp.

Mariners should be aware that Tappan Zee Constructors, LLC (TZC) will be installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) – 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website at NewNYbridge.com under the “Boater Safety” icon.

Ongoing Operations:
• Rockland access ramp modifications
• Armoring of dredge channel
• River Road utility work
• Test pile program
• Permanent pile installation
• Temporary Rockland trestle construction, including pile driving on weekdays 7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline
• Reinforcement steel pre-assembly at bridge yard

Giant crane Left Coast Lifter on way to build new Tappan Zee Bridge

 Ocean voyage expected to take 6 to 8 weeks

LoHud December 31, 2013 Theresa Juva Brown

http://www.lohud.com/videonetwork/2968321291001/Left-Coast-Lifter-heads-for-Tappan-Zee-Bridge-project

The gargantuan crane that will help build the new Tappan Zee Bridge is on its way.

New video released by bridge builder Tappan Zee Constructors shows the Left Coast Lifter passing under the Golden Gate Bridge in San Francisco this week as it begins its 6,000-mile voyage to the Hudson River. The journey is expected to take six to eight weeks. The 400-foot-long floating crane — one of the world’s largest — will travel down the West Coast, through the Panama Canal, across the Gulf of Mexico, up the East Coast and through New York Harbor.

The Left Coast Lifter, previously used on the San Francisco-Oakland Bay Bridge project, can lift 1,750 metric tons, or 12 times the weight of the Statue of Liberty. It will help install the huge deck panels on the new Tappan Zee and demolish the existing Tappan Zee in 2017.

The crane is owned by Fluor Corp. and American Bridge Co., two of the companies that make up Tappan Zee Constructors.

bilde

 

Read complete article here: http://www.lohud.com/article/20131231/NEWS02/312310014/Giant-crane-Left-Coast-Lifter-on-way-to-build-new-Tappan-Zee-Bridge-(video)?nclick_check=1

Pile Driving Set To Begin This Week

The New Tappan Zee Bridge

For immediate release: July 26, 2013

TEST PILE PROGRAM IMPACT PILE DRIVING SET TO BEGIN,
ROCKLAND THRUWAY DOCK CONSTRUCTION GETTING UNDERWAY

Tappan Zee Constructors, LLC (TZC) is scheduled to begin impact pile driving as part of the ongoing test pile operation this week. The test pile installation will continue over the next two to three months at the proposed locations of the foundations for the New NY Bridge. The test pile program will verify subsurface conditions in the river and the structural capacity of the pilings.

Under the Final Environmental Impact Statement, the hours of impact pile driving are restricted to 7 a.m. to 7 p.m., Monday through Friday and 12:00 noon to 7 p.m. on Saturday. There is no impact pile driving allowed at night or on Sundays. Noise monitors are in place along the Rockland and Westchester shorelines and the data is available at www.NewNYBridge.com.

Construction of the New York State Thruway’s temporary dock at the Rockland Maintenance facility on River Road in South Nyack will begin the week of July 29. TZC will reconstruct a maintenance dock that was damaged during Superstorm Sandy. This new dock will allow the Thruway to continue its normal maintenance work on the existing Tappan Zee as the construction activities for the New NY Bridge get underway.

Orange and Rockland Utilities will install new utility poles near River Road in South Nyack to support utility relocations which are needed for the New NY Bridge project. These operations may require temporary lane closures and will be performed by the utility.

Ongoing operations:
· Test pile program
· Rockland bulkhead construction
· Temporary Westchester trestle construction including pile driving on weekdays from
7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Rockland and Westchester environmental monitor installations
· Geotechnical land borings
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline

Westchester:
Survey crews will be conducting surveys in the toll plaza area in Tarrytown on Wednesday, July 31 requiring temporary closures of toll lanes conducted one at a time.

Rockland:
Geotechnical boring operations to investigate subsurface soil conditions will be conducted in the northbound lanes of I-87/I-287 and will require a temporary lane closure between the existing bridge to Interchange 10 in South Nyack from 10 a.m. to 3 p.m. on Monday, July 29 through Wednesday, July 31. Southbound lane closures will be required from Interchange 10 to the existing bridge between 10 a.m. and 3 p.m. on Thursday, August 1 and from 10 a.m. to 2 p.m. Friday, August 2.

Holiday Construction Schedule for TZ Bridge

The new NY bridge

For immediate release: June 28, 2013

NO WORK SCHEDULED JULY 4–NEW NY BRIDGE CELEBRATES INDEPENDENCE DAY

Tappan Zee Constructors, LLC (TZC) will not work on July 4 in observance of Independence Day.

Preconstruction activities will continue throughout the week; however, TZC will have no lane closures in order to keep traffic moving on the Thruway.

Ongoing operations:

– Cleaning and preparation for future construction of the Thruway’s Rockland Bulkhead
– Construction of the temporary Westchester work trestle which includes pile driving operations that will occur weekdays from 7 a.m. to 7 p.m. (except for July 4)
– Survey inspections on existing bridge
– Rockland environmental monitor installations continue
– Geotechnical land borings
– Mobilization at the Exit 10 staging area
– Support for river-based work from the Rockland shoreline

Westchester:

Limited geotechnical analysis boring operations continue this week on Thruway property and will not require lane closures as work will be performed behind barriers. Work may be scheduled between the hours of 7 a.m. and 3:30 p.m.

Rockland:

Limited geotechnical analysis boring operations continue this week on Thruway property and will not require lane closures as work will be performed behind barriers. Work may be scheduled between the hours of 7 a.m. and 3:30 p.m.

HUDSON RIVER TEST BORINGS FOR THE NEW NY BRIDGE COMPLETED

update

For Immediate Release: June 7, 2013

HUDSON RIVER TEST BORINGS FOR THE NEW NY BRIDGE COMPLETED

The New York State Thruway Authority and Tappan Zee Constructors, LLC (TZC) have announced that test boring operations in the Hudson River have been completed. The borings in the river are part of the pre-construction geotechnical work that began in late March. Crews will, however, continue test borings on land in both Rockland and Westchester and continue installing bridge monitoring devices in the Hudson River as part of the pre-construction engineering.

Work continues on the temporary Westchester trestle. The trestle is a work platform that will support a crane for the construction of the new bridge. The 1,000-foot long platform reduces the amount of dredging required and allows crews to work from the water and not from the Westchester shoreline. Work on the Westchester trestle will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to the hours between 7 a.m. and 7 p.m. Monday through Friday.

Environmental monitors continue to be installed in Rockland County as the Thruway Authority and Tappan Zee Constructors, LLC (TZC) finalize specific installation locations. The monitors continually record noise, vibration and air quality for the duration of the project. All readings can be viewed at www.NewNYbridge.com.

Westchester:
Surveying, utility exploration and test boring work continues for the New NY Bridge Project during the week of June 10 in Tarrytown. The work being performed in the shoulder area will require a temporary right lane closure on southbound I-87/I-287 between the existing Tappan Zee Bridge and the Route 9 Bridge on Monday and Tuesday from 10 a.m. to 3 p.m.

Rockland:
Mobilization work continues at Exit 10 where TZC will store materials for construction, trailers for work operations and equipment as well as use the staging area for employee parking. Support for river-based work from the Rockland shoreline will continue the week of June 10.

Surveying, utility exploration and test boring work continues for the New NY Bridge Project during the week of June 10 in South Nyack. The work being performed in the shoulder area will require a temporary right lane closure on southbound I-87/I-287 between Interchange 11 and S. Broadway Bridge on Wednesday and Thursday from 10 a.m. to 3 p.m.

New Tappan Zee work site bustles with activity

LoHud June 5, 2013 Written by Theresa Juva-Brown

From a giant crane hoisting steel beams to workers tightening bolts on an emerging platform in the river, the site of the new Tappan Zee Bridge was bustling with activity on Tuesday.

To promote the $3.9 billion bridge replacement, project officials took about a dozen members of the media on the river to see construction preparations. Leaders from Tappan Zee Constructors — the team designing and building the new bridge — and the Thruway Authority led the tour on a tugboat suitably named Tappan Zee II.

“This project is progressing and you’re going to see it ramp up over the next several months to the next year,” said Brian Conybeare, a special adviser to Gov. Andrew Cuomo. “More and more equipment arrives almost daily for this pre-construction work.”

The twin span is set to be completed by April 2018. Crews have just wrapped up test borings of the river’s soil and plan to start test pile-driving next month. Pile-driving tests are necessary to ensure that when permanent supports are installed, they are strong enough to hold the new span.

By the middle of next year, close to 100 work barges will fill the river, with about 30 of them being used to hold giant cranes, officials said.

There are about a dozen barges in the river now, with each dedicated to specific tasks. For example, one team is currently setting up vibration monitoring equipment on the existing bridge, while another is focused on building a 1,000-foot platform off the Tarrytown shore. When completed, the temporary trestle, which won’t be attached to the shore, will house a crane for construction.

“The new northern span will be right over our heads,” Conybeare shouted as the tugboat chugged parallel to the existing bridge on its way to the trestle location.

At the site, a 300-ton crane on a barge slowly lifted a hydraulic power unit that operates a vibratory hammer.

The hammer vibrates piles into the river bed, a technique that is less noisy than pounding them in, officials said.

In addition to the Westchester trestle, crews plan to build a similar one off the Rockland shore, though that one will stretch about 1,300 feet, Conybeare said.

37861007001_2434745098001_vs-51ae778ee4b0c77bd45a17cf-1464912386001

Click here to watch the progress on The New NY Bridge:

http://www.lohud.com/apps/pbcs.dll/article?AID=2013306040075

 

 

www.NewNYBridge.com

For immediate release: May 3, 2013

The new NY bridge

WESTCHESTER TEMPORARY TRESTLE CONSTRUCTION SCHEDULED TO BEGIN

Work is expected to begin during the week of May 6 on the Westchester trestle, which is the first of the temporary work trestles to be constructed as part of the New NY Bridge project.

The work will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to a maximum of 7:00am to 7:00pm Monday through Friday and is expected begin on Friday May 10. The trestle is a work platform that will support a crane for the construction of the easternmost 1000 feet of the new bridge. The 1000-foot long platform helps reduce the amount of dredging required and allows the crews to work from the water and not from the Westchester shoreline.

In addition, two mooring buoys will be installed in the Hudson River on the Rockland side of the channel. These will be utilized to secure work barges and will be on site for the duration of the project.

Surveying work and soil sampling for the New NY Bridge Project will continue during the week of May 6 as engineering crews conduct more design surveys at various locations in Rockland and Westchester in the vicinity of the project, including the Westchester haul road location on New York State Thruway property in Tarrytown.

Preconstruction geotechnical investigations will continue as small barge-based drilling equipment will work at various locations throughout the project footprint in the Hudson River. The crews are conducting preconstruction geotechnical surveys to determine soil conditions where future piles will be installed for the new span. Noise levels from the equipment will be at a minimum. The river-based operations will run continuously 24 hours a day Monday through Friday and possibly Saturday.

Westchester:
Limited test-boring operations will continue on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 am and 5 pm Monday through Friday.

Rockland:
At times traffic on River Road near the South Nyack-Grand View border will be restricted to one lane during weekday daytime hours for utility investigations. Signs and flag persons will be in place to help keep traffic flowing safely.

Limited test-boring operations may start on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 am and 5 pm Monday through Friday.

 

 

https://tappanzeebridge.randcommercial.com/922/

Environmental sensors to be installed near Tappan Zee construction

Lohud.com; By Khurram Saeed and Theresa Juva-Brown

April 30, 2013  TARRYTOWN — As the Tappan Zee Bridge project continues to ramp up, crews this week will begin installing environmental monitors that will allow residents to track noise, dust and vibration levels during the five years of construction.

The sophisticated shoebox-sizes devices with special sensors will be placed on top of poles at eight locations — four in Tarrytown and four in South Nyack. Losee Park in Tarrytown is set to get the first one by Wednesday.

Devices also will be installed at the Quay, an 89-unit condo complex in Tarrytown, south of the bridge in the neighborhood of Irving, and on New York State Thruway Authority property near South Broadway, state officials said.

Tappan Zee Constructors, the team engineering and constructing the $3.9 billion bridge, the Thruway Authority and community leaders are working to pin down specific locations for the devices in Rockland County, said Brian Conybeare, a special adviser on the project.

“The installation process is just getting under way, but once construction starts the public will be able to view the data from the monitoring stations 24 hours a day on our website, www.newnybridge.com,” he said.

Sensors devoted just to measuring construction vibrations have already been installed on the piers of the existing Tappan Zee Bridge, officials said.

Among the likely Rockland locations to receive a monitor is the 120-unit Salisbury Point Cooperative in South Nyack. TZC also wants to add a device at South Nyack Village Hall, but a village representative said officials had not been consulted about it.

Jerry Ilowite, head of South Nyack’s Tappan Zee Bridge task force, said TZC was supposed to present a monitoring and mitigation plan that would let the village weigh in on the best locations for the devices.

“I have no idea what they’re going to monitor or where or why they’re choosing the locations that they are,” Ilowite told The Journal News on Monday. “We have had no opportunity to contribute at all.”

After The Journal News inquired about the situation, a TZC representative called Ilowite on Monday afternoon to schedule a meeting.

The project team also plans to start taking photos and reports of property conditions before construction starts. This is done in case property owners later claim vibrations from the work damaged their homes.

Tori Weisel, president of the Irving Neighborhood Preservation Association, said about a dozen Irving residents plan to meet with TZC officials Wednesday to discuss which homes will be eligible for preconstruction surveys.

Meanwhile, the state has started to install new fencing along Van Wart Avenue to shield homes from traffic on the Thruway maintenance road. Weisel said more steps are needed.

“There is progress … but the true issue is not that fencing — it’s sound barriers and making sure our foundations are not rocked and cracked,” she said