The New NY Bridge Newsletter for January 2017

January 2017
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives

Governor Andrew M. Cuomo announced the New NY Bridge has reached a major milestone with the topping off of the eight main span towers. The New NY Bridge is on track to open in 2018 and on budget at $3.98 billion.
The project team is looking forward to another year of progress on the twin-span replacement of the original Tappan Zee Bridge, including the completion of the westbound span.
Motorists on the Tappan Zee Bridge may be familiar with the rhythmic bumps in the existing bridge’s roadway. These interruptions are the result of nearly 200 expansion joints, which are designed to absorb the slight expansion and contraction of the bridge’s steel and concrete. Drivers can expect a much smoother ride in the future thanks to the dramatic reduction of expansion joints on the new bridge.
The New NY Bridge project team is supporting local charities to make the holidays a little more joyous for those in need in our communities.
Frequently Asked Questions
Q:
How will the project reduce traffic congestion? 
A:
The existing bridge has only seven lanes, some of which are narrower than the current standard lane width of 12 feet. The new bridge will have eight, 12-foot-wide lanes and wider shoulders. The shoulders of the new crossing will greatly reduce the traffic impact of disabled vehicles and accidents, which can cause massive tie-ups on the existing bridge. The incline approaching the main span will not be as steep, allowing large trucks to maintain consistent speed and reduce engine and braking noise. The ability of trucks to maintain highway speed will also reduce speed differential with passenger vehicles which lessens lane changes and potential for accidents. There will also be gently banked curves to further smooth traffic flow and reduce accidents. In addition, the new bridge is being built with space to accommodate dedicated bus lanes. In April 2016, cashless tolling went into effect on the existing bridge, and this will be a feature of the new bridge, eliminating the need for eastbound drivers to slow down or stop and idle at a toll plaza.

Get Your E-ZPass ® 

“On-the-Go”at the

 New NY Bridge Community Outreach Centers

View the latest issues of the
Visit NewNYBridge.com to subscribe for periodic email updates
HOW TO GET INVOLVED
Follow Us on Twitter
and Instagram 

Call the Project Hotline
1-855-TZBRIDGE
(1-855-892-7434)

Westchester: 2 N. Broadway, Tarrytown, NY
Rockland: 142 Main Street, Nyack, NY
Mon-Fri: 11am-7pm | Sat-Sun: 11am-4pm


Visit the Project Website

Email Us
Scenic Hudson RiverWalk Park, Tarrytown, NY
Memorial Park, Nyack, NY
©2017 New York State Thruway Authority

The New NY Bridge November Newsletter

November 2016
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives

Following the successful completion of its phase one girder operations, the project’s largest crane has returned to familiar territory to help crews with road deck installation.
Tappan Zee Constructors recently completed the first two 419-foot towers of the iconic main span. Our new time-lapse video captures the evolution of the westbound (Rockland-bound) towers aided by the project’s blue self-climbing jump forms.
The New NY Bridge project reached a major milestone with the installation of the final steel-blue girder assembly for the new westbound approach span.
The New NY Bridge project has become a symbol for what the state can accomplish. Watch the new twin-span crossing take shape during the past three years in this new time-lapse video. From steel girders to concrete towers, from piles to road deck, from shoreline to shoreline, the transformation has been amazing.
Frequently Asked Questions
Q:
How will the project reduce traffic congestion?        
A:
The existing bridge has only seven lanes, some of which are narrower than the current standard width of 12 feet. The new bridge will have eight 12-foot-wide lanes. The wide shoulders of the new crossing will greatly reduce the traffic impact of disabled vehicles and accidents, which can cause massive tie-ups on the existing bridge. The incline over the main span will not be as steep, allowing large trucks to maintain consistent speed and reduce engine and braking noise. There will also be gently banked curves to help smooth traffic flow and reduce accidents as well as a cashless tolling system to eliminate the need for drivers to slow down or stop at a toll plaza. In addition, the new bridge is being built with the structural capacity to handle commuter rail, light rail, or bus rapid transit.
Get Your E-ZPass ® 

“On-the-Go”at the

 New NY Bridge Community Outreach Centers

View the latest issues of the
Visit NewNYBridge.com to subscribe for periodic email updates

New NY Bridge October Newsletter

October 2016
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives

Tappan Zee Constructors, LLC (TZC) is one step closer to completing the twin-span crossing as the new bridge’s westbound towers reach their ultimate height, 419 feet above the Hudson River. Crews are putting the finishing touches on the upper sections of the towers and removing the blue jump forms when the operations are complete. TZC is scheduled to complete all four westbound towers within the coming weeks.

While the large and powerful I Lift NY super crane continues to raise enormous, 410-foot sections of steel above the Hudson River, a far smaller and swifter machine, called a derrick crane, is hard at work on an equally important task – installing hundreds of road deck panels to form the base driving surface of the bridge.

As the New NY Bridge project continues to makeremarkable progress above the Hudson River, crews are installing several safety features on the crossing.
These features are the result of the project’s close collaboration with local and regional first responders during the bridge’s design development phase.

Prior to the start of New NY Bridge construction in 2013, Rockland and Westchester residents living near the project site voted overwhelmingly in favor of new permanent barriers to reduce highway traffic noise. Today, progress on the barriers is readily apparent in South Nyack.

The first full closure of the main navigational channel occurred this September. Approximately 70 closures are anticipated through the end of 2017 as project crews install new sections of structural steel and road deck panels between the towers of the new crossing.
Frequently Asked Questions
Q:
How many lanes will the new bridge have?       
A:
The new twin-span bridge will have eight general traffic lanes – four in each direction. Space will also be provided for disabled vehicles, emergency responders and express buses and/or bus rapid transit. There will also be a shared-use path for bicycles and pedestrians.

Video Captures the New NY Bridge Progress!

Three Years in Two Minutes

New Video Captures Construction Progress

The New NY Bridge project has become a symbol for what the state can accomplish.

Watch the new twin-span crossing take shape during the past three years in this new time-lapse video. From steel girders to concrete towers, from piles to road deck, from shoreline to shoreline, the transformation has been amazing.

Initiated by Gov. Andrew M. Cuomo, the 3.1-mile New NY Bridge project is one of the largest active projects of its kind in the nation.

The time-lapse video debuted today as part of Governor’s Day at the Great New York State Fair in Syracuse, a 12-day celebration that shares the best that New York State has to offer. For those visiting the State Fair, you can check out the video at the Governor’s booth.

The video is also available on the New NY Bridge project’s YouTube page.

Those interested in a closer look are also invited to view the daily project progress via the project’s webcams and photo gallery as well as by visiting the New NY Bridge construction viewing platforms at Scenic Hudson RiverWalk in Tarrytown and Memorial Park in Nyack.

http://www.newnybridge.com/three-years-in-two-minutes-new-video-captures-construction-progress/ 

New NY Bridge Project August 2016 Newsletter

August 2016
New NY Bridge Project Monthly Newsletter
  |    Home   |    Archives

The outline of the new twin-span crossing is emerging this summer as the project continues to make remarkable progress on the Hudson River. The Rockland and Westchester approaches continue to grow with rows of steel girders and hundreds of precast road deck panels. At the main span towers, crews are also installing sections of steel and roadway, and preparing the area for the new stay cable system.

The New York State Thruway Authority announced that Tappan Zee Constructors, LLC has completed installation of the first stay cables on the New NY Bridge project. The stay cables, along with the 419-foot towers, will be the most prominent features of the new 3.1-mile structure. The first two stay cables were installed by TZC on the new northbound bridge’s main span on Thursday, July 21, 2016.

In just half a year, Tappan Zee Constructors, LLC has transformed the New NY Bridge project site by connecting piers, installing road deck panels and doubling the height of the new main span towers. The iconic structures now rise above the existing Tappan Zee Bridge, with TZC preparing to install the first of nearly 200 stay cables.

With summer in full swing, the New NY Bridge project is making its most visible advancements to date. Those keen on observing the progress firsthand have a “front row seat” to the action, through the project’s viewing platforms and outreach centers in Tarrytown and Nyack.
Frequently Asked Questions
Q:
Why does the current Tappan Zee Bridge need to be replaced?     
A:
The Governor Malcolm Wilson Tappan Zee Bridge opened to traffic in 1955 and is a vital artery for residents, commuters, travelers, and commercial traffic. The bridge, which was designed to carry up to 100,000 vehicles per day, currently handles an average of 140,000 daily, and traffic congestion and delays are regular occurrences. Heavy traffic, narrow lanes and the lack of emergency shoulders contribute to congestion and frustration for motorists and can create unsafe driving conditions. As a result, the bridge has twice the average accident rate per mile as the rest of the 574-mile Thruway system. In recent years, hundreds of millions of dollars have been spent to maintain and repair the bridge. If the current bridge were not being replaced, the state would need to spend an additional $3 to $4 billion over the next 20 years to ensure its structural integrity.
Get Your E-ZPass ® 

“On-the-Go”at the

 New NY Bridge Community Outreach Centers

View the latest issues of the
Visit NewNYBridge.com to subscribe for periodic email updates

TZ Bridge Tour _ Rand Commercial Day of Learning 7.18.2016

A view from the Hudson River is the best way to view the progress of the New NY Bridge . Rand Commercial agents spent the day navigating the waters and learning about the bridge building process. We lunched and saw the amazing progress that has been made and the daunting task that lies ahead.  A very special “thank you” to Dan Marcy of the New NY Bridge Project who guided us thru the site tour.

13654269_10210069582166827_1129219761141861526_n 13701136_1118892414844972_1520934281411212663_o 13767343_10209287171631571_2366547569189200652_o

13701136_1118892414844972_1520934281411212663_o 13692858_1118892408178306_4150119926181696754_o 13654269_10210069582166827_1129219761141861526_n

New NY Bridge Monthly Newsletter July 2016

July 2016
New NY Bridge Project Monthly Newsletter
  |    Home   |    Archives

Tappan Zee Constructors (TZC) has begun building the roadway for the new bridge’s main span.
In June, TZC installed four large pre-assembled sections of steel, weighing nearly 340,000 pounds each, atop the main span crossbeams. These steel segments will allow the team to build out from the towers one section at a time, attaching stay cables to the structure along the way. Precast concrete deck panels will be placed in the erected steel sections to provide a base driving surface.
The New NY Bridge project has made extraordinary progress over the past year, with more than a mile of steel girders in place and new towers rising above the existing Tappan Zee Bridge. You can see the transformation for yourself in this narrated video.

Governor Andrew M. Cuomo announced that “Alternative F” was selected as the design for the New NY Bridge project’s shared-use path connections in Westchester and Rockland. The decision followed a thorough review of the alternative’s impacts and benefits to the local communities.

This Independence Day weekend, the U.S. Coast Guard, the New York State Thruway Authority, Tappan Zee Constructors, LLC (TZC) and local law enforcement are reminding boaters of the safety measures near the extremely active work site.
Frequently Asked Questions
Q:
How much will the new bridge cost?    
A:
The project cost is $3.98 billion. This includes bridge design-builder Tappan Zee Constructors, LLC’s (TZC) contract cost of $3.142 billion and $600 to $800 million in owner’s (New York State Thruway Authority) costs, which cover project management, oversight, a contingency fund and some financing costs.

Continues Cashless Tolling System Now In Effect

The new NY bridge

Tarrytown Toll Plaza Demolition ContinuesCashless Tolling System Now In Effect

http://www.newnybridge.com/tarrytown-toll-plaza-demolition-continues-cashless-tolling-system-now-in-effect/Demolition of the deactivated toll plaza in Tarrytown continues as Tappan Zee Constructors, LLC (TZC) removes the toll plaza structures on the four right-most lanes of the southbound New York State Thruway (I-87/I-287) in preparation for the next shift in traffic, which is scheduled to occur in late May.

Survey work in the area will necessitate a midday lane closure, detailed in the chart below.

LANE CLOSURES NEAR THE TAPPAN ZEE BRIDGE

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Tue., 5/10 10 a.m. – One right lane 3 p.m. Southbound Thruway
near the former toll plaza

Noise Barrier Construction
TZC will continue constructing noise barriers along the Thruway in South Nyack next week. The work includes constructing noise barrier foundations and excavating soil along the southbound Thruway between the South Broadway bridge and River Road. After the foundations are established, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

TZC also will continue constructing foundation walls for the future highway and shared-use path along the northbound Thruway in South Nyack. The operation is scheduled to continue in the coming months.

Additional work includes:

  • Main span tower construction
  • Support for river-based work from the Rockland trestle
  • Rockland landing retaining walls
  • Survey inspections on the existing bridge
  • Westchester landings utility work
  • Girder assembly placement
  • Bridge road deck installation
  • Drainage structure installations

Boater Safety
Marine units are continuing patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. TZC will also be working in the area left and right of the main navigation channel under the main span of the bridge. TZC will begin working in the main navigation channel, which will result in partial or total closure of same. Additional temporary navigational lights have been installed on the existing bridge to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard permit requirements, as are all moorings, barges and other equipment. All Mariners should consult the latest USCG Local Notice to Mariners before transiting this area.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, construction site maps, can be found here at NewNYBridge.com. The page includes an interactive GPS map showing vessel locations on the Hudson River, detailing which vessels are stopped and which are in motion to a new location for recreational and commercial boaters to get current information on the very active construction zone. The vessel tracking map is for informational purposes and not intended for navigation.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visithttp://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

Tarrytown Toll Plaza Demolition Continues Cashless Tolling System Now In Effect

TARRYTOWN TOLL PLAZA DEMOLITION CONTINUES

update

For immediate release: May 5, 2016

TARRYTOWN TOLL PLAZA DEMOLITION CONTINUES
Cashless Tolling System Now In Effect

Demolition of the deactivated toll plaza in Tarrytown continues as Tappan Zee Constructors, LLC (TZC) removes the toll plaza structures on the four right-most lanes of the southbound New York State Thruway (I-87/I-287) in preparation for the next shift in traffic, which is scheduled to occur in late May.

Survey work in the area will necessitate a midday lane closure, detailed in the chart below.

Lane Closures Near the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Tue., 5/10 10 a.m. – One right lane 3 p.m. Southbound Thruway
near the former toll plaza

Noise Barrier Construction
TZC will continue constructing noise barriers along the Thruway in South Nyack next week. The work includes constructing noise barrier foundations and excavating soil along the southbound Thruway between the South Broadway bridge and River Road. After the foundations are established, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

TZC also will continue constructing foundation walls for the future highway and shared-use path along the northbound Thruway in South Nyack. The operation is scheduled to continue in the coming months.

Additional work includes:

  • Main span tower construction
  • Support for river-based work from the Rockland trestle
  • Rockland landing retaining walls
  • Survey inspections on the existing bridge
  • Westchester landings utility work
  • Girder assembly placement
  • Bridge road deck installation
  • Drainage structure installations

Boater Safety
Marine units are continuing patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. TZC will also be working in the area left and right of the main navigation channel under the main span of the bridge. TZC will begin working in the main navigation channel, which will result in partial or total closure of same. Additional temporary navigational lights have been installed on the existing bridge to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard permit requirements, as are all moorings, barges and other equipment. All Mariners should consult the latest USCG Local Notice to Mariners before transiting this area.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, construction site maps, can be found here at NewNYBridge.com. The page includes an interactive GPS map showing vessel locations on the Hudson River, detailing which vessels are stopped and which are in motion to a new location for recreational and commercial boaters to get current information on the very active construction zone. The vessel tracking map is for informational purposes and not intended for navigation.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

 

May 2016 New NY Bridge Project Monthly Newsletter

May 2016
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives

The pair of peregrine falcons that live in a man-made nest box on the existing Tappan Zee Bridge became proud parents once again with the hatching of a nestling on April 10.
The New NY Bridge project team is inviting members of the public to help name the new falcon chick.
A week-long naming contest is now underway on the project’s Falcon Cam webpage. Rockland and Westchester students came up with the names.

On Sunday April 24, travelers on the Tappan Zee Bridge said goodbye to the lines at the Tarrytown toll plaza thanks to cashless tolling. The state-of-the-art technology created a new traffic pattern in the area, eliminating the need for toll booths and speeding commutes across the river.

Rows of towering piers stand in procession across the Hudson River as the New NY Bridge project steadily moves ahead.

Years of hard work and careful planning on the New NY Bridge project are paying off as Tappan Zee Constructors recorded several construction milestones.

Workers on the New NY Bridge project are making swift progress installing steel girders thanks, in part, to recent good weather.
Frequently Asked Questions
Q:
What is Cashless Tolling?    
A:
The new cashless tolling system allows motorists to pay their toll while maintaining highway speeds on the Tappan Zee Bridge. The system collects tolls via E-ZPass and Tolls by Mail, detecting classes of vehicles and applying the correct charge.
If you have E-ZPass, your toll is collected using the same process that you are already familiar with. If you don’t have E-ZPass, cameras photograph your vehicle’s license plate as it passes under the overhead equipment. A bill is then automatically sent to the registered owner by U.S. Mail.
Get Your E-ZPass ® 

“On-the-Go”at the

 New NY Bridge Community Outreach Centers

View the latest issues of the
New NY Bridge Magazine
Visit NewNYBridge.com to subscribe for periodic email upd

NEW NY BRIDGE APRIL 2016 MONTHLY NEWSLETTER

April 2016
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives

The new bridge moved another giant step forward this month as Tappan Zee Constructors, LLC (TZC) installed the fourth and final concrete crossbeam on the main span. In addition to supporting the future road deck, the massive precast beams will reinforce the outward-angled towers as they grow to their ultimate 419-foot height.

Rockland and Westchester residents voiced their opinions at a pair of public meetings this March as the New NY Bridge team presented detailed information regarding the proposed alternatives for the Shared-Use Path (SUP) parking facilities and connections in the villages of South Nyack and Tarrytown.

Living up to its safety motto, “Take Zero Chances,” Tappan Zee Constructors, LLC (TZC) recently held safety meetings with every member of its New NY Bridge project crew.

Since the start of construction of the New NY Bridge in 2013, the project’s outreach team has partnered with local schools to engage nearly 40,000 students. The team’s presentations highlight the importance of science, technology, engineering and mathematics-collectively known as the STEM fields-to the design and construction of the twin-span bridge.
Frequently Asked Questions
Q:
What is Cashless Tolling, and when will it take effect on the Tappan Zee Bridge?    
A:
Beginning on April 23, 2016, the new cashless tolling system will allow motorists to pay their toll while maintaining highway speeds on the Tappan Zee Bridge. The system will collect tolls via E-ZPass or Tolls by Mail, detecting classes of vehicles and applying the correct charge.
If you have E-ZPass, your toll is collected using the same process that you are already familiar with. If you don’t have E-ZPass, cameras photograph your vehicle’s license plate as it passes under the overheard equipment. A bill is then automatically sent to the registered owner by U.S. Mail.
Get Your E-ZPass ® 

“On-the-Go”at the

 New NY Bridge Community Outreach Centers

View the latest issues of the
New NY Bridge Magazine
Visit NewNYBridge.com to subscribe for periodic email updates
HOW TO GET INVOLVED
Follow Us on Twitter
and Instagram 

Call the Project Hotline
1-855-TZBRIDGE
(1-855-892-7434)

Westchester: 2 N. Broadway, Tarrytown, NY
Rockland: 142 Main Street, Nyack, NY
Mon-Fri: 11am-7pm | Sat-Sun: 11am-4pm

Visit the Project Website

Email Us
Scenic Hudson RiverWalk Park, Tarrytown, NY
Memorial Park, Nyack, NY
©2016 New York State Thruway Authority

The New NY Bridge Project Monthly Newsletter_March

VIEW AS WEBPAGE

March 2016
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives

Residents and other interested stakeholders are invited to attend Public Hearings to comment on the Environmental Assessment (EA) for the proposed Shared-Use Path Parking Facilities and Bicycle/Pedestrian Connections in the Villages of South Nyack and Tarrytown.

The New NY Bridge project has begun clearing the way for the construction of a state-of-the-art building that will be used for maintenance of the new three-mile crossing, which will carry billions of vehicles over the Hudson River during the next century.

This winter, volunteers from Tappan Zee Constructors, LLC (TZC) are lending their time and talent to Habitat for Humanity of Westchester’s latest endeavor: top-to-bottom renovations of homes for Iraq War veterans and their families.

After months of steady progress on the main span towers, Tappan Zee Constructors, LLC (TZC) has begun installing enormous concrete crossbeams between the iconic towers.
Frequently Asked Questions
Q:
Will the bridge look exactly like the artist’s rendering that have been made public?   
A:
Yes, overall the general design of the bridge will look similar to the artist rendering but it is subject to refinement as part of the design-build process. A Visual Quality Panel has been established to gather and consider public input and make recommendations on such characteristics as surface finishes, colors, lighting design, landscaping, and the shared-use bike and pedestrian path.
Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the
New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates
HOW TO GET INVOLVED
Follow Us on Twitter

Call the Project Hotline
1-855-TZBRIDGE
(1-855-892-7434)

Westchester: 2 N. Broadway, Tarrytown, NY
Rockland: 142 Main Street, Nyack, NY
Mon-Fri: 11am-7pm | Sat-Sun: 11am-4pm

Visit the Project Website

Email Us
Scenic Hudson RiverWalk Park, Tarrytown, NY
Memorial Park, Nyack, NY
©2016 New York State Thruway Authority

The New NY Bridge February Newsletter!

February 2016
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives
CLICK HERE FOR COMPLETE ISSUE!

Tappan Zee Constructors, LLC (TZC) recently installed the 650th concrete road deck panel for the westbound span. TZC began placing the panels in early October and is on track to install an additional 6,000 panels by year’s end. The work is occurring on top of recently-installed steel-blue girders, which continue to advance across the Hudson River.

MAIN SPAN TOWERS REACH NEW MILESTONE

update

PROJECT UPDATE

For immediate release: Feb. 4, 2016

MAIN SPAN TOWERS REACH NEW MILESTONE
Overnight Lane and Ramp Closures on Southbound Thruway (I-87/I-287)

Next week, Tappan Zee Constructors, LLC (TZC) will begin the installation of four precast concrete crossbeams that will connect the new bridge’s main span towers and support its future road deck. The crossbeams were fabricated by Coastal Precast Systems in Chesapeake, Virginia, and barged to the project site last week. The precast materials will be set in place with the I Lift NY super crane, one of the few marine cranes in the world capable of the massive job.

Demolition of Thruway Maintenance Facility
TZC will begin demolition of the New York State Thruway Authority’s former maintenance offices in Tarrytown. Bridge maintenance teams currently operate from a temporary facility near exit 12 in West Nyack. The demolition will make way for a new maintenance facility and office building, which will begin construction this spring.

All-Electronic Toll Collection Gantry Work
Field testing of the project’s temporary all-electronic toll collection (AETC) system in Rockland will continue throughout the coming week near the exit 10 (Nyack – South Nyack – US Route 9W) and exit 11 (Nyack – South Nyack – US Route 9W) on-ramps to the southbound New York State Thruway (I-87/I-287).

The testing will necessitate closing the on-ramps during the overnights of Thursday, Feb. 4, through Friday, Feb. 12. Drivers will be directed to use the exit 12 (West Nyack – NY Route 303 – Palisades Center Drive) on-ramp from Route 303 in West Nyack, as shown in the graphic below. Signs will be posted to advise motorists of the detour route.

In addition, the work will require overnight closures of up to three lanes of the southbound Thruway throughout the remainder of this week and during the coming week. Specific lane and ramp closure times are detailed in the chart below.

The AETC system is expected to be activated this spring.

 

 

UPDATE: ALL-ELECTRONIC TOLLING FACILITY WORK

For immediate release: Feb. 1, 2016

UPDATE: ALL-ELECTRONIC TOLLING FACILITY WORK
Multiple Overnight Lane and Ramp Closures on Southbound Thruway (I-87/I-287)

Field testing of the project’s temporary all-electronic toll collection (AETC) system in Rockland is underway near the exit 10 (Nyack – South Nyack – US Route 9W) and exit 11 (Nyack – South Nyack – US Route 9W) on-ramps to the southbound New York State Thruway (I-87/I-287).

The testing will necessitate closing the on-ramps during the overnights of Monday, Feb. 1, and Wednesday, Feb. 3, through Sunday, Feb. 7. Drivers will be directed to use the exit 12 (West Nyack – NY Route 303 – Palisades Center Drive) on-ramp from Route 303 in West Nyack, as shown in the graphic below. Signs will be posted to advise motorists of the detour route.

In addition, the work will require overnight closures of up to three lanes of the southbound Thruway throughout the remainder of this week. Specific lane and ramp closure times are detailed in the chart below.

The AETC system is expected to be activated this spring.

Lane and Ramp Closures Near the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Mon., 2/1 8 p.m. – Two right lanes
11 p.m. – Three right lanes
5 a.m., Tue., 2/2 Southbound
from exit 12 to exit 10
Mon., 2/1 9 p.m. – Ramp closures 5 a.m., Tue., 2/2 Southbound
exit 10 and 11 on-ramps
Wed., 2/3 8 p.m. – Two right lanes
11 p.m. – Three right lanes
5 a.m., Thu., 2/4 Southbound
from exit 12 to exit 10
Wed., 2/3 9 p.m. – Ramp closures 5 a.m., Thu., 2/4 Southbound
exit 10 and 11 on-ramps
Thu., 2/4 8 p.m. – Two right lanes
11 p.m. – Three right lanes
5 a.m., Fri., 2/5 Southbound
from exit 12 to exit 10
Thu., 2/4 9 p.m. – Ramp closures 5 a.m., Fri., 2/5 Southbound
exit 10 and 11 on-ramps
Fri., 2/5 8 p.m. – Two right lanes
12 a.m. – Three right lanes
6 a.m., Sat., 2/6 Southbound
from exit 12 to exit 10
Fri., 2/5 9 p.m. – Ramp closures 6 a.m., Sat., 2/6 Southbound
exit 10 and 11 on-ramps
Sat., 2/6 9 p.m. – Two right lanes
12 a.m. – Three right lanes
8 a.m., Sun., 2/7 Southbound
from exit 12 to exit 10
Sat., 2/6 9 p.m. – Ramp closures 6 a.m., Sun., 2/7 Southbound
exit 10 and 11 on-ramps
Sun., 2/7 10 p.m. – Two right lanes
1 a.m. – Three right lanes
5 a.m., Mon., 2/8 Southbound
from exit 12 to exit 10
Sun., 2/7 10 p.m. – Ramp closures 5 a.m., Mon 2/8 Southbound
exit 10 and 11 on-ramps

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

 

THE NEW NY BRIDGE MAGAZINE!

 

THE NEW NY BRIDGE MAGAZINE

Here at the New NY Bridge project, one of our priorities is keeping members of the community, like you, informed throughout the construction process. To that end, we would like to share our Winter 2016 Magazine,which chronicles the project’s latest developments.

In this issue:

  • Project Update: Substructure Nears Completion
  • Construction Update: Forging Strength
  • Educational Outreach: Inspiring Young Minds

 

Please enjoy the New NY Bridge Magazine.

 

READ COMPLETE MAGAZINE ONLINE HERE

PROJECT UPDATE – WESTCHESTER GIRDER INSTALLATION

update

For immediate release: Nov. 19, 2015

WESTCHESTER GIRDER INSTALLATION OVER METRO-NORTH RAILROAD TRACKS CONTINUES THIS FRIDAY EVENING
Overnight Closures of the I-87/I-287 Exit 10 On-Ramp Scheduled for Nov. 19 and Nov. 20

Next week, Tappan Zee Constructors, LLC (TZC) will continue installing structural steel girder assemblies from the new bridge’s Westchester landing in Tarrytown. The assemblies will connect the future westbound span’s on-land abutment to the first offshore support pier in the Hudson River. TZC is installing the girders by literally pushing them west over the Metro-North Railroad Hudson Line’s tracks toward the first pier in the river, as seen in this animation. As the operation progresses, additional girders are being connected to the assembly and pushed farther westward. TZC is closely coordinating the effort with Metro-North Railroad, ensuring that the operation maximizes safety for both workers and the public and minimizes impacts to rail service.

With the entire operation anticipated to conclude by the end of the year, the remaining work over the Metro-North tracks will occur during two Friday overnights, with the next scheduled for this Friday evening, Nov. 20. Metro-North has adjusted its schedule slightly to allow the work to be completed. TZC will suspend construction activities when commuter trains pass through the area, resuming when given the “all clear” instruction by Metro-North.

Across the river, TZC has completed steel girder installation near the Rockland shoreline, connecting the new bridge’s abutment to already-installed support structures in the Hudson River.

The I Lift NY super crane will continue placing larger girders across the river, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

All-Electronic Toll Collection Gantry Work
Construction of the project’s temporary all-electronic toll collection (AETC) system in Rockland will continue near the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to southbound New York State Thruway (I-87/I-287). The work will necessitate closing the on-ramp during the overnights of Thursday, Nov. 19 and Friday, Nov. 20. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the graphic below. No lane closures are planned for this work next week.

Ramp Closures Near the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Thu., 11/19 9 p.m. – Ramp Closure 5 a.m., Fri., 11/20 Southbound I-87/I-287
exit 10 on-ramp
Fri., 11/20 9 p.m. – Ramp Closure 5 a.m., Sat., 11/21 Southbound
exit 10 on-ramp

Tower Construction
Construction will continue on the new bridge’s iconic towers, which will eventually rise 419 feet above the river. Innovative self-climbing jump forms enable TZC workers to build the towers in segments that progressively “jump” up from the foundations to their full height. Within the jump forms, workers assemble steel reinforcement cages that are then encased in concrete, one segment atop the previous one and so on. Eight towers will be constructed on the project’s football-field-long main span pile caps over the coming year, as seen in this animation.

Deck Panel Installation
TZC is continuing to install nearly 6,000 high-strength concrete deck segments for the new crossing’s approach spans. Project cranes are lifting the prefabricated deck panels into place atop previously-installed structural steel girders. The deck segments are prefabricated at an off-site location and barged down river from the project’s Port of Coeymans facility in Albany County. TZC will continue installing the approach span deck sections over the coming year.

Installation of Noise Barriers in South Nyack
Next week will see continued removal of the noise walls located along the northbound Thruway and the construction of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road in South Nyack. The work involves drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
Westchester and Rockland Marine Units are continuing extensive patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

###

Project Update: Electronic Tolling System Requires Overnight Closures

For immediate release: Nov. 12, 2015

THRUWAY UNVEILS UPDATED PROJECT WEBSITE
All-Electronic Tolling System Work Requires Overnight Closure of Exit 10 On-Ramp on Friday, Nov. 20

The New York State Thruway Authority launched an updated NewNYBridge.com this week, featuring an easier-to-navigate interface, a comprehensive archive of project photos, videos and renderings, and a wealth of background information covering how the new crossing was studied and designed and is being built. Visit the new site and check back frequently for the latest updates on the fast-moving construction progress.

Steel Girder Installation
Tappan Zee Constructors, LLC (TZC) will continue installing steel girders near the Rockland shoreline, connecting the new bridge’s abutment to already-installed support structures in the Hudson River. Safely accomplishing the work will require reducing River Road/Piermont Avenue to one lane during weekdays between 6 a.m. to 5 p.m. Flag persons will keep traffic moving by alternating the directional flow between north and south. TZC also will hold traffic on River Road once daily between 9 a.m. and 3 p.m. for up to 20 minutes through Wednesday, Nov. 18 to enable the safe movement of girders and other materials.

Across the river, TZC will continue installing structural steel girder assemblies from the new bridge’s Westchester landing in Tarrytown. The assemblies will connect the future westbound span’s on-land abutment to the first offshore support pier in the Hudson River. TZC is installing the girders by literally pushing them west over the Metro-North Railroad Hudson Line’s tracks toward the first pier in the river, as seen in this animation. As the operation progresses, additional girders are being connected to the assembly and pushed farther westward. TZC is closely coordinating the effort with Metro-North, ensuring that the operation maximizes safety for both workers and the public and minimizes impacts to rail service.

With the entire operation anticipated to conclude by the end of the year, the remaining work over the Metro-North tracks will occur during two Friday overnights, one in November and one in December. The work will be announced in advance to enable Metro-North riders to plan ahead. Metro-North has adjusted its schedule slightly to allow the work to be completed. TZC will suspend construction activities when trains pass through the area, resuming when given the “all clear” instruction by Metro-North.

Additionally, the I Lift NY super crane will continue placing larger girders across the Hudson River, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

All-Electronic Toll Collection Gantry Work
Construction of the project’s temporary all-electronic toll collection (AETC) system in Rockland will continue near the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to southbound New York State Thruway (I-87/I-287). The work will necessitate closing the on-ramp during the overnight of Friday, Nov. 20. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the graphic below. The work also requires double-lane closures during weekday overnights from Monday, Nov. 16 through Thursday, Nov. 19. This and other work require the specific lane and ramp closures detailed in the chart below.

Lane and Ramp Closures Near the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Thu., 11/12 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Fri., 11/13 Southbound I-87/I-287
from exit 12 to exit 10
Fri., 11/13 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Sat., 11/14 Southbound
from exit 12 to exit 10
Mon., 11/16 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Tue., 11/17 Southbound
5 a.m., Tue., 11/17
Tue. 11/17 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Wed., 11/18 Southbound
from exit 12 to exit 10
Wed., 11/18 8 p.m. – One left lane
9 p.m. – Two left lanes
5 a.m., Thu., 11/19 Southbound
from exit 12 to exit 10
Thu., 11/19 8 p.m. – One left lane
9 p.m. – Two left lanes
5 a.m., Fri., 11/20 Southbound
from exit 12 to exit 10
Fri., 11/20 9 p.m. – Ramp closure 5 a.m., Sat., 11/21 Southbound
exit 10 on-ramp

Tower Construction
Construction will continue on the new bridge’s iconic towers, which will eventually rise 419 feet above the river. Innovative self-climbing jump forms enable TZC workers to build the towers in segments that progressively “jump” up from the foundations to their full height. Within the jump forms, workers assemble steel reinforcement cages that are then encased in concrete, one segment atop the previous one and so on. Eight towers will be constructed on the project’s football-field-long main span pile caps over the coming year, as seen in this animation.

Deck Panel Installation
TZC is continuing to install nearly 6,000 high-strength concrete deck segments for the new crossing’s approach spans. Project cranes are lifting the prefabricated deck panels into place atop previously-installed structural steel girders. The deck segments are prefabricated at an off-site location and barged down river from the project’s Port of Coeymans facility in Albany County. TZC will continue installing the approach span deck sections over the coming year.

Installation of Noise Barriers in South Nyack
Next week will see continued construction of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road in South Nyack. The work involves drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
Westchester and Rockland Marine Units are continuing extensive patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

###

BRIDGE BUILDERS PREPARE FOR POSSIBLE HURRICANE

update

For immediate release: Oct. 1, 2015

BRIDGE BUILDERS PREPARE FOR POSSIBLE HURRICANE
Marine Construction Work Temporarily Halted for Safety

Tappan Zee Constructors, LLC (TZC) is preparing for the potential effects of Hurricane Joaquin, which forecasters say could hit the Hudson Valley region in the coming days. In advance of the storm’s approach, TZC is implementing its storm preparedness plans, temporarily halting marine construction operations and the movement of construction materials, while securing the job site to prevent possible storm damage. By closely monitoring weather conditions and taking appropriate action in advance, TZC will ensure both worker and public safety while minimizing any potential storm-related downtime on the project.

TZC’s inclement weather preparation protocols include having tug boats on the water at all times, inspecting and adjusting all mooring lines, inspecting crane barges and securing all equipment, moving the large majority of cranes to shallow water moorings and taking all smaller crew boats out of the water. Additionally throughout every storm, TZC uses video and GPS to monitor the entire fleet of project vessels from its security operations center.

Governor Andrew M. Cuomo today activated the State Emergency Operations Center in Albany to monitor severe weather that is anticipated to impact southern parts of New York State beginning today and potentially lasting through this weekend.
Additional New York State storm preparedness updates can be found here:
http://www.governor.ny.gov/news

The following construction operations planned for next week will proceed as weather allows:

Steel Girder Installation
TZC will continue installing steel girders near the South Nyack shoreline. Safely accomplishing the work will require reducing River Road to one lane during weekdays between 6 a.m. to 5 p.m. Flag persons will keep traffic moving by alternating the directional flow between north and south.

Smaller girder sections will be lifted into place by cranes from the Rockland trestle. Ironworkers then bolt together the girders and cross beams that will support the new bridge’s concrete road deck. In deeper water, the I Lift NY super crane will continue placing larger girders, averaging two placements a week.

A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

All-Electronic Toll Collection Gantry Work
Construction of the project’s temporary all-electronic toll collection (AETC) system in Rockland County will continue next week with the installation of an overhead gantry above the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to southbound New York State Thruway (I-87/I-287). The work necessitates overnight double-lane closures throughout the coming week. Specific lane closures are listed in the chart below.

 

Lane Closures Near the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Mon., 10/5 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Tue., 10/6 Southbound I-87/I-287
from exits 12 to 10
Tue., 10/6 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Wed., 10/7 Southbound
from exits 12 to 10
Wed., 10/7 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Thu., 10/8 Southbound
from exits 12 to 10
Thu., 10/8 8 p.m. – One right lane
9 p.m. – Two right lanes
6 a.m., Fri., 10/9 Southbound
from exits 12 to 10
Fri., 10/9 8 p.m. – One right lane
9 p.m. – Two right lanes
6 a.m., Sat., 10/10 Southbound
from exits 12 to 10

Tower Construction
The new bridge’s iconic towers will continue rising toward their ultimate height of 419 feet, aided by self-climbing jump forms. The state-of-the-art forms enable TZC workers to build the towers in segments that progressively “jump” up from the foundations to their full height. Within the jump forms, workers assemble steel reinforcement cages that are then encased in concrete, one segment atop the previous one and so on. Eight towers will be constructed on the project’s football-field-long main span pile caps over the coming year, as seen in this animation.

Installation of Noise Barriers in South Nyack
Next week will see continued installation of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road in South Nyack. The work involves drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
Westchester and Rockland Marine Units are continuing extensive patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visithttp://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

###

The New NY Bridge Newsletter October 2015

October 2015
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

Building on remarkable construction achievements so far, Tappan Zee Constructors, LLC (TZC) is now beginning work on the new bridge’s striking main span towers. Utilizing self-climbing jump forms, TZC will construct the 419-foot towers in continuously-rising segments throughout the coming year.

In addition to employing more than 3,000 people to date, the nation’s largest bridge and highway project is enlisting the talents of the next generation of engineers, designers and builders. Through ongoing college internship programs, both the New York State Thruway Authority and Tappan Zee Constructors, LLC are engaging bright young minds to learn from, and contribute to, the New NY Bridge project.

Bridge builders are using 3D technology to create the New NY Bridge in a virtual world. By utilizing state-of-the-art building information modeling (BIM), designers can handle an astonishing amount of information with the utmost efficiency.

The New NY Bridge project educational outreach initiative recently kicked off its third year with a focus on the teamwork and innovation required to build the nation’s largest bridge and highway project. As in previous years, the outreach team will engage students throughout the Hudson Valley and beyond, visiting classrooms and hosting outdoor lectures at the project’s construction viewing platforms in Rockland and Westchester counties.
Frequently Asked Questions
Q:
Will the bridge look exactly like the artist’s renderings that have been made public? 
A:
The design of the bridge is subject to refinement as part of the design-build process. A Visual Quality Panel has been established to gather and consider public input and make recommendations on such characteristics as surface finishes, colors, lighting design, landscaping, and the shared-use bike and pedestrian path.
Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates

Project Update: ICONIC BRIDGE TOWERS CONTINUE RISING

For immediate release: Sept. 10, 2015

ICONIC BRIDGE TOWERS CONTINUE RISING
Preparations for Girder Placement to Temporarily Reduce River Road to One Lane

Next week, the new bridge’s towers will continue rising toward their ultimate height of 419 feet, thanks to self-climbing jump forms. The state-of-the-art forms enable Tappan Zee Constructors, LLC (TZC) workers to build the towers in segments that progressively “jump” up from the foundations to their full height. Within the jump forms, workers assemble steel reinforcement cages that are then encased in concrete, one segment atop the previous one and so on. Eight towers will be constructed on the project’s football-field-long main span pile caps over the coming year, as seen in this animation.

Structural Steel Installation
In preparation for the placement of the new bridge’s westernmost steel girders over River Road in South Nyack, TZC will reduce River Road to one lane between 6 a.m. to 5 p.m., Monday through Friday of next week. Flag persons will keep traffic moving by alternating the directional flow between north and south.

The installation of girders over the river will continue next week and beyond. Smaller girder sections will be lifted into place by cranes from the Rockland trestle near the South Nyack shoreline. Ironworkers then bolt together the steel-blue girders and cross beams that support the new bridge’s concrete road deck. The I Lift NY super crane will continue placing larger girders, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

All-Electronic Toll Collection Gantry Work
Construction of the project’s temporary all-electronic toll collection system in Rockland County is continuing with the installation of roadway sensors during the week of Sept. 14.

Specific lane and ramp closure times are listed in the chart below.

I-287/I-87 Lane and Ramp Closures Near the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Fri., 9/11 8 p.m. – One right lane
9 p.m. – Two right lanes
6 a.m., Sat., 9/12 Southbound
from exits 12 to 10
Mon., 9/14 8 p.m. – One right lane
9 p.m. – Two right lanes
6 a.m., Tue., 9/15 Southbound
from exits 12 to 10
Tue., 9/15 8 p.m. – One right lane
9 p.m. – Two right lanes
6 a.m., Wed., 9/16 Southbound
from exits 12 to 10
Wed., 9/16 8 p.m. – One right lane
9 p.m. – Two right lanes
6 a.m., Thu., 9/17 Southbound
from exits 12 to 10
Thu., 9/17 9 p.m. – One right lane
10 p.m. – Two right lanes
6 a.m., Fri, 9/18 Southbound
from exits 12 to 10
Fri., 9/18 8 p.m. – One right lane
9 p.m. – Two right lanes
6 a.m., Sat., 9/19 Southbound
from exits 12 to 10

Dredging Operations
TZC will continue the second stage of dredging operations near the Westchester shoreline next week as part of the preparation for removing the existing bridge and completing the landing of the new southern span. Dredging is allowed during a three-month period from August 1 to October 31 in specified locations and will be conducted 24/7 to complete the required dredging during the short window of time. The window was established to avoid impacting migration and spawning patterns of endangered sturgeon and other fish species.

Installation of Noise Barriers in South Nyack
Next week will see continued installation of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road in South Nyack. The work involves drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Landing abutment concrete work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
Westchester and Rockland Marine Units are continuing extensive patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

###

 

 
This email was sent to ginny.warsaw@randcommercial.com by info@newnybridgegallery.com |

Rapid removal with SafeUnsubscribe™ | About our service provider.

New NY Bridge Project | 303 South Broadway | Suite 413 | Tarrytown | NY | 10591

Steel Girder Installation Continues

For immediate release: August 20, 2015

STEEL GIRDER INSTALLATION CONTINUES NEAR THE ROCKLAND LANDING

Tappan Zee Constructors, LLC (TZC) will continue installing structural steel girders for the New NY Bridge project next week. Smaller girder sections will be lifted into place by cranes from the Rockland trestle near the South Nyack shoreline. Local ironworkers will then bolt together the steel blue girders and cross beams that will support the new bridge’s concrete road deck.

In addition, the I Lift NY super crane will continue placing larger girder assemblies next week and beyond, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

Two northbound lanes of the New York State Thruway (I-87/I-287) will be closed during the overnights of Monday, August 24 and Tuesday, August 25 across the existing Tappan Zee Bridge to facilitate surveying efforts.

I-287/I-87 Lane and Ramp Closures on the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Mon., 8/24 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Tue., 8/25 Northbound Across the
Tappan Zee Bridge
Tue., 8/25 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Wed., 8/26 Northbound Across the
Tappan Zee Bridge

Dredging Operations Continue
TZC will continue the second stage of dredging operations near the Westchester shoreline as part of the preparation for removing the existing bridge and completing the landing of the new southern span. Dredging is allowed during a three-month period from August 1 to October 31 in specified locations and will be conducted 24/7 to complete the required dredging during the short window of time. The window was established to avoid impacting migration and spawning patterns of endangered sturgeon and other fish species.

Installation of Noise Barriers in South Nyack
Next week also will see continued installation of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road in S. Nyack. The work will involve drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Pile cap foundation construction
  • Placement of Steel Girder assemblies
  • Dredging
  • Main span foundation construction
  • Landing abutment concrete work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
During the summer months, Westchester and Rockland Marine Units will add extra patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

 

New NY Bridge Project August 2015 Monthly Newsletter

An Aerial Tour:

Photos From Above Show Major Progress


The incredible progress on the New NY Bridge project is becoming more and more visible every day. Residents are literally seeing engineering history in the making. As part of their design-build contract with the New York State Thruway Authority, Tappan Zee Constructors, LLC (TZC) is documenting the construction using both still photography and video. TZC regularly uses a helicopter to get a bird’s eye view of the worksite and you can now see the new twin-span bridge rising out of the Hudson River in this slideshow.

READ MORE

As travelers approach the Tappan Zee Bridge from Rockland County, they will soon get a glimpse of the future: An overhead gantry and related equipment is being installed at exit 10 on the southbound New York State Thruway in South Nyack for a temporary all-electronic toll collection (AETC) facility. Following a series of tests this fall, the system will be activated in spring 2016, enabling motorists to pay their toll while maintaining highway speeds. Like the Model-T and the 8-track tape player, the inconvenience of stopping or slowing down to pay a toll soon will be a thing of the past.

 

READ MORE

Over 60 million pounds of steel bars will fortify the new bridge, more than three times as much steel as is in the iconic Eiffel Tower in Paris. Each of the reinforcing steel bars, called rebar, is treated through a process called “hot-dip galvanization” that provides additional protection against rusting.

 

 READ MORE

By the sweat of their brow, construction workers have made impressive progress on the New NY Bridge project. But with near triple digit temperatures increasingly becoming the norm, keeping more than 1,000 workers on the Hudson River at any given time hydrated is of paramount importance.

 

READ MORE

Frequently Asked Questions
Q:
What will happen to the current bridge? 
A:
The current Tappan Zee Bridge will be carefully dismantled, and the structural steel will be recycled. The concrete deck panels, which have been replaced in recent years, will be reused where possible on other Thruway and state Department of Transportation projects.
Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates
HOW TO GET INVOLVED
Follow Us on Twitter

@NewNYBridge

Call the Project Hotline

1-855-TZBRIDGE

(1-855-892-7434)

Community Outreach Centers

Westchester: 2 N. Broadway, Tarrytown, NY

Rockland: 142 Main Street, Nyack, NY

Mon-Fri: 11am-7pm | Sat-Sun: 11am-4pm

Visit the Project Website
Email Us
Construction Viewing Platform

Scenic Hudson RiverWalk Park, Tarrytown, NY

Next to the Tarrytown Senior Center at
240 West Main St.

©2015 New York State Thruway Authority

Tappan Zee Bridge Zipper’s days are numbered

A big yellow bus ran into the wall on the Tappan Zee Bridge, the caller tells the 911 operator.

“It’s not a bus. It’s us,” says Richie Lynch of Valley Cottage, one of the drivers of the barrier-moving machine that is still a strange sight for the uninitiated, even 22 years after first arriving on the bridge. Callers regularly report the vehicle as an accident in progress, Lynch says.

“Some people drive by and take pictures,” says Lynch, who has worked on the bridge for 25 years. “We get a lot of thumbs-ups for giving them the extra lane. And we get a different salute when we’re running late.”

Some call it “The Zipper” — because it acts like a zipper does, sliding the barrier from one spot to another — but Lynch and the four other members of the barrier team just call it “the barrier mover.”

Whatever the name, the 52-foot-long, million-dollar vehicle is now part of the bridge, a welcome sight for bumper-to-bumper commuters on whom it bestows a somewhat speedier ride through the Tappan Zee bottleneck, creating four lanes where there were three. It makes about 600 crossings a year.

In January, a Zipper was added to San Francisco’s storied Golden Gate Bridge. But the Tappan Zee Zipper’s days are numbered.

In December 2016, northbound traffic is scheduled to transfer to the new northbound span of the New New York Bridge. The two barrier movers — there’s an extra on standby, swapped in during maintenance — will be sold and will enter the lore of the Tappan Zee, alongside those pre-EZPass commutation booklets.

VIDEO BELOW: Ride inside the Zipper  

ALSO: What do the new TZ Bridge and a NASCAR track have in common? 

The Zippers — the second-generation of vehicle by California-based Lindsay Transportation Systems, in use since 2007 — move the wall 12 feet to the right, the width of a travel lane, in one fluid motion with every trip across the bridge. It used to take two machines to make the move.

The wall itself is second-generation, too. The original had concrete sections; today’s sections — there are 6,000 of them, each 3 feet long — are T-shaped steel shells with a concrete center.

There is so much more going on than meets the eye when the Tappan Zee Zipper is in motion. The barrier is shaped and reformed through hydraulics and an ingenious machine that acts like a chiropractor on a 3-mile-long Tappan Zee spine, adjusting and releasing tension in the wall — and in rush-hour traffic.

Driving and laying: The Zipper doesn’t drag the wall. It lifts it, snakes it through a double row of wheels in its undercarriage, and places it back on the deck. In a sort of push-me-pull-you configuration, a second driver — facing the shore from which the Zipper departed — “lays” the barrier back in position by keeping a wheel on one of the blue lines on the pavement.

“When you drive on it, all you’re doing is engaging it on the wheels and lifting it up,” Lynch says. “When it gets to the middle of the machine, that’s where it starts to shift it to the other side, and then the conveyor takes it down and sets it back onto the deck.”

“Bogey wheels:” The 104 wheels that engage the T-top and lift the barrier are called “bogey wheels” and glide the barrier up a railing under the vehicle and help it snake into its new position.

A “wow” in the wall: Ernie Feeney, a patrol supervisor and another original Zipper driver, says the wall sometimes gets a kink in it, when a motorist hits it.

“We call it a ‘wow,'” Feeney says. “Maybe somebody spun out and hit the wall. The wall gives now because it’s a giant centipede so your car doesn’t get totally wrecked like it used to be if you had a solid cement wall. A lot of people now just drive off with minor damage.”

When the barrier machine comes across, if there’s just a little “wow” in the wall, they can just drive straight through it. A bigger accident requires a wrecker and a push bar to get it close to its natural line.

Stop the Zipper: There are things that will stop the barrier in its tracks, Lynch says. “If there’s a jumper in the middle of the move, we’ll stop. If there’s a bad accident or if there’s an accident in the left lane or the two left lanes, sometimes we’ll bring the wall up to it and stop to protect them.”

Migration lines: Like rush-hour commuters, the barrier is under tension. There are yellow lines on the wall that correspond to lines on the deck. If these migration lines don’t line up, the Zipper driver can adjust huge capstan wheels to add or release tension in the wall to pull or push it back in line.

Hydraulics, Benjamin: “It’s all done by hydraulics,” Lynch says. “Your steering, your brakes, the drive motors, it’s all hydraulics. And those lines and fittings need to be checked every day to make sure they’re not leaking.”

Every 20 feet or so on the flat sections (and farther away on the inclines) there are single open-topped T sections. These “VLB sections” actually control the tension in strands of the barrier. They have hydraulic controls in them and open and close to allow strands of the wall to go slack and be moved. Think of it as pulling a 3-mile-long rope 20 feet at a time. On curves, there are more VLB sections to hold the curve in place until the machine reaches it.

No connection: The barrier mover isn’t connected to the wall. It has to drive onto the wall. When he’s driving, Lynch keeps a control bar centered over the wall ahead of him.

3 miles, 30 minutes: The move takes about 35 to 40 minutes, if the wall is in good shape. “If there’s more tension or compression, it might take a little longer because you have to go through it slower to make the adjustments,” Lynch says.

U-turns possible: Eagle-eyed drivers will notice three 45-foot sections of bridge where the T-tops appear to be hollow. There are three spots on the bridge — near either end and in the middle — where the barrier can be opened to allow for a U-turn.

Hello, I must be going: “The men and all of us are going to miss it,” Lynch says. “And I think the public’s gonna miss it, too. It’s nice to have an extra lane when you need it.”

NYS Thruway employee Rich Lynch drives the barrier-moving machine across the Tappan Zee Bridge, adding a lane northbound. Tania Savayan/The Journal News

http://www.lohud.com/story/news/local/tappan-zee-bridge/2015/07/16/tappan-zee-bridge-zipper-days-numbered/30142559/

The New NY Bridge July Newsletter

July 2015
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

Heavy Metal:

Bridge Starts Taking Shape with Installation of First Section of Structural Steel


Following months of careful planning and with the use of the project’s king of cranes, the New NY Bridge team installed the span’s first section of structural steel on June 17: a 410-foot segment of welded girders that will support the road deck.

READ MORE

With the 2015 recreational boating season hitting full stride this weekend as boaters celebrate Independence Day on the water, the New NY Bridge project team and local law enforcement officials remain committed to helping all boaters navigate safely near the work area. Boaters are reminded to be extra vigilant around commercial vessels and the construction zone, especially the no-wake low-speed zone at the Tappan Zee Bridge.

 

READ MORE

Oyster reefs were once a predominant feature of the Hudson River, supporting vast and diverse communities of aquatic life. But past decades of pollution and overharvesting led to a decline in oyster populations in the area to near-extinction. In recent years, however, there have been promising signs of recovery.

 

 READ MORE

The addition of a third floating concrete batch plant this week enables the New NY Bridge project to shift into an even higher gear. Capable of delivering 180 cubic yards of concrete per hour – more than twice as much as the initial two batch plants combined – the new mixing platform will supply concrete for the new bridge’s remaining foundations and piers as well as its 419-foot towers, which will begin later this summer.

 

READ MORE

After a stunningly beautiful trip down the Hudson River, the first 12′ tall, 400′ long section of structural steel arrived at the New NY Bridge construction site on Thursday June 10, 2015. The girder sections, weighing up to 1,100 tons are assembled at the Port of Coeymans in Albany County and then barged to the project site. The trip can take from 12 to 20 hours depending on weather, tides and other conditions. The individual steel girders, totaling 31 miles in length before assembly, are all made in the USA and will support the road deck of the new twin span bridge. The girders will be set in place by the I Lift NY crane in the coming days.

 

 READ MORE

Frequently Asked Questions
Q:
How can my company apply for subcontracting work on the project?
A:
Businesses interested in obtaining contracts for the New NY Bridge project should reach out to Tappan Zee Constructors, LLC through the TZC website, TappanZeeConstructors.com.
Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates
HOW TO GET INVOLVED
Follow Us on Twitter

@NewNYBridge

Call the Project Hotline

1-855-TZBRIDGE

(1-855-892-7434)

Community Outreach Centers

Westchester: 2 N. Broadway, Tarrytown, NY

Rockland: 142 Main Street, Nyack, NY

Mon-Fri: 11am-7pm | Sat-Sun: 11am-4pm

Visit the Project Website
Email Us
Construction Viewing Platform

Scenic Hudson RiverWalk Park, Tarrytown, NY

Next to the Tarrytown Senior Center at
240 West Main St.

©2015 New York State Thruway Authority

Holiday Traffic Update

update

For immediate release: July 1, 2015

NO LANE CLOSURES SCHEDULED ON NEW NY BRIDGE PROJECT OVER INDEPENDENCE DAY WEEKEND

Multiple Lane Closures During the Overnights of the Week of July 6

In observance of the Independence Day holiday, Tappan Zee Constructors, LLC (TZC) will suspend most construction activities over the Fourth of July weekend. Security and limited maintenance operations will continue throughout the project site. In accordance with New York State’s Drivers First initiative, no construction related lane closures are scheduled on or near the New NY Bridge project site from Thursday morning, July 2 to Monday night, July 6. Drivers First, launched in 2012, prioritizes the convenience of motorists to ensure that traffic disruptions are as minimal as possible for drivers at highway and bridge construction projects across the state.

Boater Safety With the 2015 boating season in full swing, the New NY Bridge project team urges all boaters to use caution on the Hudson River near the construction zone and to take advantage of the extensive safety-related information available on the project website including the 2015 New NY Bridge Boater Safety Guide.

Enhanced marine law enforcement patrols are in effect for the Independence Day holiday weekend. The U.S. Coast Guard, Westchester and Rockland County marine units will be patrolling the area urging all boaters to use caution and follow all safety regulations.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

Following the Holiday, Multiple-Lane Closures and Periodic Traffic Stops During the Overnights of Monday, July 6 through Friday, July 10 During the overnight of Monday, July 6, lane restriping operations will require triple-lane closures of the northbound New York State Thruway (I-87/I-287) from exit 9 (Tarrytown – Sleepy Hollow – US Route 9) to exit 11 (Nyack – South Nyack – US Route 9W). Specific lane closure times are listed in the chart below.

At least one lane will remain open at all times, except during periodic traffic stops lasting up to 10 minutes of all four lanes of the northbound Thruway near exit 11 (Nyack – South Nyack – US Route 9W). To ensure the public’s safety, the New York State Police will stop and hold all traffic approaching the area immediately before the traffic stops go into effect. Motorists will be permitted to enter the Thruway from all ramps during the traffic stops.

Additionally the exit 10 (Nyack – South Nyack – US Route 9W) off-ramp from the northbound Thruway will also be closed during the overnight of Monday, July 6. Drivers will be directed to use exit 11 (Nyack – South Nyack – US Route 9W) as shown below:

During the overnight of Tuesday, July 7, construction operations will require overnight double-lane closures of the northbound Thruway from exit 9 (Tarrytown – Sleepy Hollow – US Route 9) to exit 11 (Nyack – South Nyack – US Route 9W). Specific lane closure times are listed in the chart below.

At least one lane will remain open at all times, except during periodic traffic stops lasting up to 10 minutes of all four lanes of the northbound Thruway near exit 11 (Nyack – South Nyack – US Route 9W.

During the overnights of Wednesday, July 8 through Friday, July 10, construction operations will require triple-lane closures of the southbound Thruway in the area of exit 10 (Nyack – South Nyack – US Route 9W). Specific lane closure times are listed in the chart below.

Additionally the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to the southbound Thruway will be closed from 8 p.m. to 5 a.m. during the overnights of Tuesday, July 7 and Wednesday, July 8. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the following graphic.

Lane closures throughout the coming week are scheduled as follows:

I-287/I-87 Lane and Ramp Closures near the Tappan Zee Bridge
Date: Closures Begin: Closures End: Location:
Mon, 7/6 8 p.m. – One left lane

9 p.m. – Two left lanes

11 p.m. – Three left lanes

4:30 a.m., Tue, 7/7 Northbound,
from exit 9 to exit 11
Mon, 7/6 8 p.m. – Ramp closure 4:30 a.m., Tue, 7/7 Northbound,
exit 10 off-ramp
Tues, 7/7 8 p.m. – One left lane

9 p.m. – Two left lanes

4:30 a.m., Wed, 7/8 Northbound,
from exit 9 to exit 11
Tue, 7/7 8 p.m. – Ramp closure 4:30 a.m., Wed, 7/8 Southbound,

exit 10 on-ramp

Wed, 7/8 8 p.m. – One left lane

9 p.m. – Two left lanes

11 p.m. – Three left lanes

5 a.m., Thu, 7/9 Southbound,
from exit 10 to exit 11
Wed, 7/8 8 p.m. – Ramp Closure 4:30 a.m., Wed, 7/8 Southbound,

exit 10 on-ramp

Thu, 7/9 8 p.m. – One left lane

9 p.m. – Two left lanes

11 p.m. – Three left lanes

5 a.m., Fri 7/10 Southbound,
from exit 10 to exit 11
Fri, 7/10 9 p.m. – One left lane

10 p.m. – Two left lanes

11 p.m. – Three left lanes

6 a.m., Sat 7/11 Southbound,
from exit 10 to exit 11

All planned work is subject to postponement due to weather conditions.

Steel Girder Assemblies As piers are finalized in the coming weeks and months, steel girder assemblies for the approach span of the new bridge will continue being installed by the I Lift NY super crane.

Installation of Noise Barriers in South Nyack Next week will see continued installation of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road. The work will involve drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

River Road in South Nyack River Road utility work will continue over the coming week. The work may require reducing River Road to one lane at times. TZC flag persons will direct traffic as needed and additional signage as well as other safety measures will be in place.

Foundation Work on the New Bridge Marine crews are continuing work on bridge foundations next week by placing reinforcing steel and concrete in the piles, main span pile caps and approach span pile caps. The high-strength concrete is made on site by the project’s floating batch plants. Teams also will erect formwork for the cast-in-place pier columns, which eventually will support the new bridge’s road deck.

Crews also will continue working on the bridge’s landings at the Rockland and Westchester shorelines. The abutments, comprised of steel and concrete, will serve as strong bases where the new crossing meets the landside roadway.

Additionally, TZC will continue concrete placement for bridge foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and is delivered by truck to the Rockland trestle located off the Thruway’s southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.

Additional work includes:

  • Girder installation
  • Pile cap foundation construction
  • Main span foundation construction
  • Landing abutment concrete work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester Landings utility work

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

June 2015 New NY Bridge Newsletter

June 2015
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

The Votes Are In, Tappan Zee Falcon Chicks Are ‘Hudson, Bridge-ette and Zee’:

A Day After Being Named, Falcon Chicks Make Inaugural Flights


Following a week-long campaign in which more than 3,000 ballots were cast, the New NY Bridge project is pleased to announce the winners of its 2015 falcon naming poll: Hudson, Bridge-ette and Zee received the greatest number of votes among 10 candidate names provided by local elementary schools.

READ MORE

When it came to designing the lighting of the New NY Bridge, the project team’s strategy was twofold: accentuate the architectural features of the iconic crossing while at the same time respecting the context in which it is built: the historic Hudson Valley. To achieve this balance-while also maintaining high standards of efficiency and safety-the team engaged Domingo Gonzalez Associates, (DGA) a leading architectural lighting design firm based in New York City.

 

 READ MORE

The New NY Bridge project held its annual public meetings in Westchester and Rockland on May 12 and 14, respectively, to give residents an in-depth briefing about construction progress to date and what lies ahead for the largest bridge and highway project in the nation.

 

READ MORE

The New NY Bridge project crossed another milestone this week with the installation of the first precast pier cap. These large concrete fixtures sit atop completed pier columns and eventually will support the new bridge’s road deck.

 

READ MORE

With the 2015 recreational boating season now underway, the New NY Bridge project team’s partnership with local officials is further enhancing safety on the waters of the Hudson River. As construction intensifies this summer, helping all boaters navigate safely near the work area is a top priority for the project team.

 

 READ MORE

Frequently Asked Questions
Q:
How many lanes will the new bridge have?
A:
The new twin-span bridge will have eight general traffic lanes – four in each direction. Space will also be provided for disabled vehicles, emergency responders and express buses and/or bus rapid transit.
Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates
HOW TO GET INVOLVED
Follow Us on Twitter

@NewNYBridge

Call the Project Hotline

1-855-TZBRIDGE

(1-855-892-7434)

Community Outreach Centers

Westchester: 2 N. Broadway, Tarrytown, NY

Rockland: 142 Main Street, Nyack, NY

Mon-Fri: 11am-7pm | Sat-Sun: 11am-4pm

Visit the Project Website
Email Us
Construction Viewing Platform

Scenic Hudson RiverWalk Park, Tarrytown, NY

Next to the Tarrytown Senior Center at
240 West Main St.

©2015 New York State Thruway Authority

Annual Meeting May 14, 2015

201505554cc8772e022

Members of the New NY Bridge project team will preview upcoming construction activities, discuss the progress thus far, and unveil some new design features at this year’s annual meeting for Rockland County.

Also, there will be a Q&A session with the audience and project leaders from the New York State Thruway Authority and Tappan Zee Constructors.

The annual meeting will be moderated by Brian Conybeare, the project’s special advisor.

WHEN: 6:30-8PM May 14

WHERE: Nyack High School, 360 Christian Herald Road, Nyack.

The Westchester annual meeting is Tuesday at Washington Irving School in Tarrytown.

PHOTO: One of the largest approach span pile caps on the project is carefully placed onto a group of foundation piles by the I Lift NY super crane.

Photo Credit: New York State Thruway Authority.

http://patch.com/new-york/nyack/new-ny-bridge-project-2015-annual-meeting-thursday?utm_source=alert-breakingnews&utm_medium=email&utm_term=community%20corner&utm_campaign=alert

The New NY Bridge Newsletter for May 2015

May 2015
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

[VIDEO]

Super Crane’s First Lift


One of the world’s largest floating cranes successfully completed the first of many enormous lifts for the New NY Bridge project on April 24, 2015, following months of planning and preparation.

READ MORE

As Earth Day is observed, New Yorkers literally can breathe easier, knowing that the New NY Bridge project is being built with some of the cleanest construction equipment in the world.

 

 READ MORE

As the New NY Bridge project begins its most intense stage of construction, one upstate business is busy manufacturing nearly 1,000 concrete deck panels for the crossing’s main span roadway.

 

READ MORE

The New NY Bridge project marked another milestone this spring as Tappan Zee Constructors, LLC placed concrete for the crossing’s northern Westchester abutment. The structure will support the new bridge’s landing and was formed by pouring over 650 cubic yards of concrete in one day. You can watch the entire operation take place in just under a minute.

 

 READ MORE

In addition to educational outreach programs that have reached thousands of students, ongoing public presentations and a comprehensive website, the New NY Bridge project maintains two community outreach centers near the project site. Located in downtown Tarrytown and Nyack, and open seven days a week, the centers provide a window into the largest bridge and highway project in the nation.

 

 READ MORE

Frequently Asked Questions
Q:
How long will the new bridge last?
A:
The New NY Bridge is designed to last 100 years before any major structural maintenance is required.

 

Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates
HOW TO GET INVOLVED
Follow Us on Twitter

@NewNYBridge

Call the Project Hotline

1-855-TZBRIDGE

(1-855-892-7434)

Community Outreach Centers

Westchester: 2 N. Broadway, Tarrytown, NY

Rockland: 142 Main Street, Nyack, NY

Mon-Fri: 11am-7pm | Sat-Sun: 11am-4pm

Visit the Project Website
Email Us
Construction Viewing Platform

Scenic Hudson RiverWalk Park, Tarrytown, NY

Next to the Tarrytown Senior Center at
240 West Main St.

©2015 New York State Thruway Authority

SUPER CRANE SUCCESSFULLY COMPLETES FIRST LIFT ON

update

NEW NY BRIDGE PROJECT
I LIFT NY hoists massive 600-ton foundation element into place today

One of the world’s largest floating cranes this morning successfully completed the first of many enormous lifts for the New NY Bridge project, following months of planning and preparation.

In a carefully coordinated three-and-a-half hour operation on the Hudson River between Westchester and Rockland counties, the I Lift NY super crane hoisted and set one of the project’s largest precast concrete pile caps weighing in at 600 tons.

Video and photos from today’s lift will be posted here.

“We brought in the I Lift NY super crane to reduce construction time and cost, and this first lift is another symbol that the New NY Bridge is officially on the way,” Thruway Acting Executive Director Robert L. Megna. “The crane is a key tool to building the bridge in a safer, more cost-effective, environmentally-friendly way. With savings of more than a billion dollars for tollpayers, this super crane will continue to do great work.”

Owned by Tappan Zee Constructors, LLC, the design-build contractor for the New York State Thruway Authority, the super crane’s extraordinary capabilities save time and money while enhancing quality and safety by allowing large sections of the bridge to be pre-fabricated off-site and shipped by barge to the construction zone.

I Lift NY will continue to lift and place sections of the new twin-span bridge — some weighing from 900 to 1,100 tons — and will assist with the dismantling of the existing 60-year-old Tappan Zee Bridge, reducing costs and shortening the deconstruction process.

The super crane’s boom is 328 feet tall, which is taller than a 30-story building, and can lift up to 1,900 tons, or the equivalent of 12 Statues of Liberty, at once. Despite its enormity, the barge-mounted crane sits high in the water, thereby reducing the need for dredging on the project by 50 percent.

The I Lift NY super crane made a 6,000-mile journey from the San Francisco Bay area in 2014, passing through the Panama Canal.

Since its arrival here in New York, the crane has gone through months of testing, modifications and upgrades including a new high-tech computer operating system and complete replacement of its rigging cables. The most experienced operating engineers in the area also spent months of specialized training to carefully handle this massive machine. Now that the ice has cleared on the Hudson River, the I Lift NY crane is getting to work on the pile caps and later this year will begin placing the even heavier structural steel beams that will carry the road deck across the new spans.

New NY Bridge Progress
Under Governor Cuomo’s leadership and with the support of President Barack Obama and the Federal government, the New NY Bridge project has progressed dramatically since construction began in October 2013 following many years of delay. Since October 2011, steps forward include: enactment of new design-build legislation; review and completion of concurrent environmental review and procurement processes; negotiation of a project labor agreement with construction unions; and recommendation from a panel of local leaders and transportation experts for a comprehensive plan for mass transit options for the region – all with an unprecedented level of transparency and community involvement.

About the New NY Bridge
The New NY Bridge’s eight traffic lanes, four breakdown and emergency lanes, and state-of-the-art traffic monitoring systems will mean less congestion for motorists. Designed and constructed to be mass-transit-ready, the new crossing will be able to accommodate bus rapid transit, as well as light rail or commuter rail. The bridge will also include a bike and pedestrian shared-use path. Extensive measures are in place throughout the duration of the project to protect the environment and to monitor the impact of construction on surrounding communities.

I LIFT NY SUPER CRANE SPECIFICATIONS

Type of vessel: Floating Sheerleg Crane
Propulsion: None
Hull material: Steel
Lifting capacity: 1,929 tons
Length: 384 feet
Breadth: 99.8 feet
Depth: 22 feet
Boom length: 328.08 feet
Boom width: 65.7 feet
Min. boom angle for transport: 4 degrees
Min. boom angle for lifting: 19 degrees
Max. boom angle for lifting: 67 degrees
For more information or for photos and video of the I Lift NY super crane’s first lift, go to www.NewNYBridge.com

Tappan Zee viewing area in Nyack could open in June

1406317305000-TZ-Tarrytown-Viewing-Platform-1JPG

LoHud ,Khurram Saeed, ksaeed@lohud.com4:54 p.m. EDT April 21, 2015

Rockland residents will have to wait a couple of more months to get an up-close look of the new Tappan Zee Bridge getting built.

Construction crews this week will begin mobilizing equipment at Memorial Park in Nyack to build a new fishing pier that will house the viewing area.

The 90-foot-long by 30-foot-wide pier should be ready by mid-June, Nyack Village Administrator Jim Politi said.

The observation area at the end of the pier will feature several information panels about the $3.9 billion replacement project and the equipment being used. High-powered telescopes will provide an intimate look at what promises to be an extremely busy construction season.

While the official viewing site in Tarrytown’s RiverWalk Park opened last October, Nyack has run into problems that have led to delays.

Village officials had hoped the rebuilt pier would be ready to open last December.

“It took us three tries to find someone to put the pilings in,” Politi said of the project’s critical foundational element.

Politi said larger companies were too busy and perhaps the work was viewed as too small but all that bidding and rebidding added weeks, if not months, to the $200,000 rebuild of an old fishing pier, which received $150,000 from the state and $50,000 in Tappan Zee community fund money.

Soon after pile driving began at end of August, the project ran into another snag.

Crews installing the 40-foot-long wood piles hit a concrete barge buried along the shore.

“We had to figure out how to get through that,” Politi said.

Nyack Mayor Jen Laird-White turned to the state Thruway Authority for advice, and Tony Canale, one of the geotechnical engineers hired for the Tappan Zee project, helped come up with a solution. Canale lives in Yonkers and teaches a graduate course on foundation engineering at Manhattan College.

“We were happy to utilize some the world-class engineering expertise on the New NY Bridge project to help the village of Nyack with their new fishing pier,” said Brian Conybeare, adviser to Gov. Andrew Cuomo on the project.

With the piles now all in, the custom-made deck, wood railings, tables, benches, lighting and Tappan Zee-related materials remain to be installed.

Politi estimates that work will take the contractor, Ingannamorte and Sons of Tenalfy, N.J., six to eight weeks to complete.

By early summer, he said visitors and Tappan Zee watchers will have a place to “fish or sit and relax” with a “wonderful view” of the rising bridge.

Conybeare said the viewing platform will offer residents “a first-hand look at the historic project unfolding on the Hudson River right in their backyard.”

Twitter: @ksaeed1

If you go

The Westchester viewing platform for Tappan Zee Bridge construction is located at Scenic Hudson RiverWalk Park, 157 W. Main St., Tarrytown.

 

TZ Bridge Project Update and Lane Closures for the Week of March 23, 2015

FLOATING BATCH PLANTS RETURN TO WORK ON THE NEW NY BRIDGE PROJECT
Triple-Lane Closure on Northbound New York State Thruway (I-87/I-287) During Overnight of Wednesday, Mar. 25

Tappan Zee Constructors, LLC’s (TZC) two floating concrete batch plants recently returned to the work site, passed the required testing and soon will begin pumping concrete. The batch plants were taken out of service in December after a silo failed.

The concrete plants move from location to location on the river, providing high-quality concrete where it is needed to build the New NY Bridge project. Their resumption of service will reduce the number of concrete trucks using local roads.

The following lane and exit closures are planned for next week:

Three left lanes of the northbound Thruway (I-87/I-287) will be closed from exit 9 (Tarrytown – Sleepy Hollow – NY Route 9) to exit 10 (Nyack – South Nyack – Route 9W), and including the Tappan Zee Bridge, from 9 p.m., Wednesday, Mar. 25 to 4:30 a.m., Thursday, Mar. 26. One lane will remain open during the closure. The closures are necessary to accommodate road-striping work.

Additionally, road striping will require the closure of the two left (35 mph) E-ZPass lanes at the southbound Thruway toll plaza in Tarrytown from 10 p.m. Friday, Mar. 27 to 5 a.m., Saturday, Mar. 28. The work also will necessitate the closure of the southbound exit 9 off-ramp to Route 9 from 10 p.m., Friday, Mar. 28 to 5 a.m., Saturday, Mar. 28. Traffic that would otherwise use exit 9 will be detoured to exit 8A, as shown below:

map

Turn-by-turn directions for southbound exit 9 closure detour:

  1. Exit onto the exit 8A off-ramp;
  2. At the end of the long ramp, turn right on westbound Route 119/White Plains Road;
  3. Enter westbound I-287, which merges with northbound I-87;
  4. Exit onto the exit 9 off-ramp;
  5. Turn left onto westbound Route 119/White Plains Road; and
  6. Turn left or right on Route 9, depending on your destination. 

Preparations for the Temporary All Electronic Toll Collection system in South Nyack near exit 10 will require a single right-lane closure from 10 a.m. to 3 p.m. on Monday, March 23 and Tuesday, March 24.

Marine operations continue to gear up following the winter shutdown, with crews installing reinforcing steel (rebar) in the main span pile caps and the precast approach span pile caps.

With only a small percentage of piles left to install, pile driving operations will continue next week. The periodic pile driving is restricted to 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.

Crews also will continue working on the bridge’s landings at the Rockland and Westchester shorelines. The abutments, comprised of steel and concrete, will serve as strong bases where the new crossing meets the landside roadway.

TZC will continue limited concrete placement for foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and delivered by truck to the Rockland trestle located off the New York State Thruway’s (I-87/I-287) southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.

Additional work includes:

  • Pile cap foundation construction
  • Main span foundation construction
  • Landing abutment concrete work
  • River Road utility work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge

Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.

Project Update: Winter Weather Limits Operations

WINTER WEATHER CONTINUES TO LIMIT OPERATIONS AT NEW NY BRIDGE PROJECT SITE DURING THE WEEK OF FEBRUARY 9

Freezing temperatures and winter weather in the Hudson Valley continue to limit operations at the New NY Bridge project site. Tappan Zee Constructors, LLC (TZC) has included a two-month winter shutdown in its schedule to account for winter weather conditions.

During the week of February 9, TZC will continue limited operations.

TZC’s inclement weather preparation protocols include having tug boats on the water at all times, inspecting and adjusting all mooring lines, inspecting crane barges and securing all equipment, moving the large majority of cranes to shallow water moorings and taking all smaller crew boats out of the water. Additionally throughout every storm, TZC uses video and GPS to monitor the entire fleet of project vessels from its security operations center.

As weather permits, landside crews are working to assemble formwork that will shape the bridge’s landings on the Rockland and Westchester shorelines. The abutments, which will be made of steel, concrete, will serve as strong bases where the new crossing meets the landside roadways.

Pile Driving and Other Construction Activity

As much as allowed by weather conditions, construction will continue in the Hudson River, where crews are placing the foundations of the new bridge. The work includes pile driving from 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.

TZC also will continue limited concrete placement for foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and delivered by truck to the Rockland trestle located off the New York State Thruway (I-87/I-287) southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp.  The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.

Westchester landing foundation operations continue as crews work to construct the land based piers and abutment for the new bridge.

Additional work includes:

  • Pile cap foundation construction
  • Main span foundation construction
  • River Road utility work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge

Boater Safety

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.

NYS Thruway Lane Closures for Jan 28-29,2015

For immediate release: January 23, 2015 

TWO LANES OF SOUTHBOUND NEW YORK STATE THRUWAY (I-87/I-287) CLOSED OVERNIGHT WEDNESDAY JAN. 28 AND THURSDAY JAN. 29

Two lanes of the southbound New York State Thruway (I-87/I-287) will be closed between The Tappan Zee Bridge Toll Plaza in Tarrytown and exit 8A (Elmsford – NY Route 119 – Saw Mill River Parkway North) during the overnights of Tuesday, January 27 and Wednesday, January 28. The two overnight closures will occur between 7 p.m. and 5 a.m. and are necessary to accommodate work on an electronic message sign facility.

Bridge Abutment Work Continues

Tappan Zee Constructors, LLC (TZC) will continue assembling formwork that will shape the bridge’s landing on the Rockland and Westchester shorelines. The abutments, which will be made of steel, concrete and earth, will serve as strong bases for where the new crossing meets the landside roadway.

Pile Driving and Other Construction Activity
Construction will continue in the Hudson River as crews place the foundations of the new bridge. Work will include pile driving from 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.

TZC will continue limited concrete placement for foundations near the South Nyack shoreline. In the absence of the project’s floating batch plants, which were temporarily taken out of service last month after a silo failed, the concrete for this work will be acquired from local concrete suppliers and will be delivered by truck to the Rockland trestle located off of the New York State Thruway (I-87/I-287) southbound access ramp. Trucks will exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.

Westchester landing foundation operations continue as crews work to construct the land based piers and abutment for the new bridge.

  • Additional work includes:
  • Pile cap foundation construction
  • Main span foundation construction
  • River Road utility work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on existing bridge

Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.

NEW NY BRIDGE BIKE/PEDESTRIAN PATH

More Community Input Wanted on Parking Facility Concepts  for Rockland and Westchester

bike path

Residents and other interested stakeholders are invited to provide comments on the new bridge’s shared-use bike/pedestrian path parking concepts.

Once complete, the New NY Bridge to replace the Tappan Zee will offer Hudson Valley residents a safer and easier commute, as well as a brand new 3.1-mile-long shared-use path for pedestrians and bicycles with stunning Hudson Valley views. The path will be perfect for a leisurely stroll, a challenging run or an exhilarating ride.

 

The project team has been working closely with residents, elected officials and experts for more than a year to develop the best design for visitor parking and other amenities. We completed a comprehensive study to determine the amount of parking needed, and an environmental assessment of the options is underway. Public meetings will be held to present the findings of the environmental assessment and take more comments from the public before any plans are finalized.

 

Now, we want your input on the parking options.

 

Please click here to view parking concepts. Comments will be accepted through Friday, February 13, 2015, and can be made via mail, email or fac (see instructions below). 

 

At the Westchester landing, the parking facility is planned on Thruway Authority property off South Broadway in Tarrytown. This site offers ample space for both parking and amenities.

 

For the Rockland landing, a variety of community-generated concepts are being studied to provide sufficient parking and amenities – including one on Thruway property at exit 10. At the Village of South Nyack’s request, the bike/pedestrian path’s entrance was moved from Smith Avenue to Cornelison Avenue at South Broadway. A $250,000 grant was awarded to the village through the New NY Bridge project’s Community Benefits Program to study the feasibility of redeveloping exit 10.

 

The parking facility concepts can be viewed at NewNYBridge.com/SUP and public comments can be submitted as follows:

 

Mail: Brian Conybeare
Special Advisor to the Governor for the New NY Bridge Project
303 South Broadway, Suite 413
Tarrytown, New York 10591

 

Email: Info@NewNYBridge.com  

 

Fax: 914.524.5455

 

Thank you in advance for your comments!

 

Construction Milestone on the TZ Bridge

Another major construction milestone  on the Tappan Zee Bridge project.

“To get to this point is very big,” Tappan Zee Constructors construction services manager Ro DiNardo told The Journal News.

Over the coming weeks and months, there will be a whirlwind of activity on the $3.9 billion project in Rockland alone.

Watch them build this hulking structure known as an abutment, which is where the new crossing meets land.

http://lohud.us/1BJb9Iy

Lohud  Khurram Saeed, ksaeed@lohud.com, January 9,2015

New Year of Construction Looking Ahead to 2015

New Year of Construction
Looking Ahead to 2015

December 31, 2014 |

With a fleet of approximately 130 floating cranes, barges, tugboats and other vessels working on the New NY Bridge, construction continues to move forward. The coming year will see the completion of the new crossing’s foundations and an increasing number of bridge piers across the Hudson River.

Early in 2015, the I Lift NY super crane will make the first of what will be hundreds of heavy lifts by installing a 600-ton approach span pile cap, a task that no other crane on the job can handle. Next year will also bring the completion of phase one of pile driving (phase two is scheduled for 2017, after the landings of existing bridge are removed); the installation of numerous precast approach-span pile capsby the project’s floating cranes; and the completion of the main-span pile caps, which will support the soaring 419-foot main span towers. The bridge also will begin to take its finished form, as segments of the road deck are mounted on the steel girders that connect the approach span piers. With the placement of thousands of tons of concrete and steel in the coming year, the project is steadily progressing towards completion in 2018.

Individuals keen on observing progress of the New NY Bridge project firsthand are invited to visit the recently opened Westchester viewing platform in Tarrytown’s Scenic Hudson RiverWalk Park. The platform is equipped with telescopes and a spotter’s guide, which describes the wide array of equipment on the river. The Rockland viewing platform, which will be situated in Nyack’s Memorial Park, is under development and is slated to open in early 2015. The project’s day-by-day progress also can be tracked from the comfort of home, thanks to construction cameras situated at various vantage points on and around the project site and accessible from the project website.

Here’s to another year of progress on this historic project in 2015!

http://www.newnybridgegallery.com/updates/new-year-of-constructionlooking-ahead-to-2015/

 

 

 

 

Traffic Update thru Jan 4th to Ease Holiday Travels

For immediate release: December 26, 2014

ALL LANES OF NEW YORK STATE THRUWAY (I-87/I-287) WILL REMAIN OPEN FROM FRIDAY DEC. 26, 2014 THROUGH SUNDAY, JAN. 4, 2015 TO EASE HOLIDAY TRAVEL

All lanes of the New York State Thruway (I-87/I-287) will remain open from Friday, Dec. 26, 2014 through Sunday, Jan. 4, 2015 to help New Yorkers reach their winter holiday destinations. The 10-day lane-closure-free period follows Governor Andrew M. Cuomo’s “Drivers First” initiative, which gives priority to motorists by ensuring that disruptions associated with highway and bridge projects are kept as minimal as possible.

While Tappan Zee Constructors, LLC (TZC) will continue working in several areas of the project during the week of Dec. 29, none of the planned activities will result in the closure of any traffic lanes. No construction work is scheduled for New Year’s Day, Thursday, Jan. 1, 2015, though safety and security teams will remain on site.

Limited concrete placement will continue as TZC progresses the investigation of the recent incident on one of its floating concrete batch plants. The concrete for foundations near the S. Nyack shoreline will be acquired from local concrete suppliers that will be delivered to the site via trucks to the Rockland Trestle off of the New York State Thruway southbound access ramp. The trucks will exit the trestle to the Thruway via the northbound access ramp. This work could begin as soon as this week.

Activities on the Westchester and Rockland landings will continue as originally scheduled as this work has always been planned to receive the needed concrete from trucks to the site.

Continued Demolition of Westchester Landing of Existing Tappan Zee Bridge
Following the removal of sections of deck of the existing Tappan Zee Bridge to make way for the new bridge, the associated supporting piers are being demolished. The majority of this work, which will clear the path for the northbound bridge’s landing and first foundation pier, will be completed during daytime hours.

Pile Driving and Other Construction Activity
Construction will continue in the Hudson River as crews place the foundations of the new bridge. Work will include pile driving from 7 a.m. to 7 p.m., Monday through Wednesday and noon to 7 p.m., Saturday. No pile driving will occur on New Year’s Day, Thursday, Jan. 1, 2015. Operations will resume on Friday, Jan. 2, 2015 at 7 a.m.

A second shift of workers also will continue pile welding, pile cleanout and concrete placement operations associated with foundations.

Work is continuing on the new bridge’s landings on both sides of the river.

Additional work includes:

  • Pile cap foundation construction
  • Main span foundation construction
  • River Road utility work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on existing bridge

Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions

Tappan Zee Bridge December 2014 Newsletter

December 2014
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

The Big Reveal:  

First Piers Completed


Like an artist unveiling a new creation, Tappan Zee Constructors, LLC (TZC) removed enclosing formwork to reveal the first of the New NY Bridge project’s vertical piers on Nov. 13. The column is the first of 86 piers that will stand in procession across the river to support the new bridge’s road deck.

READ MORE

Ever since he piloted his first crane at the precocious age of 12, New Rochelle native Ronald Burgess has been on track to one day take control of a machine as massive as the I Lift NY super crane. Groomed by his father, also a crane operator, Burgess has been an engineer for 30 years and is currently a member of the International Union of Operating Engineers Local 137. His career has included work on high-visibility construction projects including the Yonkers Raceway and even the redecking of the existing Tappan Zee Bridge.

 

READ MORE

As the New NY Bridge begins to rise from the surface of the Hudson River, the New York State Thruway Authority and Tappan Zee Constructors, LLC (TZC) are working together to ensure their growing construction team meets the very highest standards for workplace safety.

 

 READ MORE

To help travelers reach their Thanksgiving destinations, the New York State Thruway Authority and Tappan Zee Constructors, LLC paused certain New NY Bridge construction activities during the latter half of last week to keep all lanes open. While the holiday weekend and late November snow storm have passed, our winter weather driving tips will remain helpful to you in the coming months.

 

READ MORE

 

 

Read Complete Newsletter here: http://www.newnybridgegallery.com/updates/december-2014-new-ny-bridge-monthly-newsletter/

New NY Bridge Project Monthly Newsletter_ November 2014

November 2014
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

Enter the Super Crane:

I Lift NY Arrives at the New NY Bridge Project 


 Following a 6,000 mile journey that included transit through the Panama Canal, the New NY Bridge project’s I Lift NY super crane arrived at the Hudson River construction site on October 6.

READ MORE

October 16, 2014 marked the first anniversary of permanent construction operations on the New NY Bridge project, and the past year has seen exceptional progress on the foundations of the new crossing. Looking ahead, the project is poised to make even greater and more visible strides in the coming year.

 

 READ MORE 

I Lift NY Completes Journey
I Lift NY Completes Journey
 

The I Lift NY super crane arrived at the New NY Bridge site on October 6. Here is a video of the powerful lifter completing the last leg of its 6,000-mile journey.

 

 READ MORE 

Led by the recently-arrived I Lift NY super crane, an armada of more than 30 floating cranes – each capable of raising immense structural elements with great precision – is hard at work lifting and placing many millions of pounds of components and materials to help build the New NY Bridge. These workhorse machines are critical to keeping the project on schedule for completion in 2018.

 

 READ MORE

Now in its second year, the New NY Bridge Educational Outreach Program continues to engage students of all ages in Westchester, Rockland and beyond. The program reflects Governor Andrew Cuomo’s goal of using the state’s largest infrastructure project to educate tomorrow’s professionals. This year, the team is focusing on the ‘how-it-works’ engineering behind the new bridge’s foundations.

 

 READ MORE 

Those keen on observing firsthand the progress of the New NY Bridge project are invited to the recently-opened Westchester viewing platform in Tarrytown’s Scenic Hudson RiverWalk Park. Located near the Tarrytown Senior Center at 240 West Main Street, the easy-to-access platform provides an unobstructed view of the project site.

 

READ MORE

Frequently Asked Questions
Q: What will happen to the current bridge?
A: The current Tappan Zee Bridge will be carefully dismantled and the structural steel will be recycled. The concrete deck panels, which have been replaced in recent years, will be reused where possible on other Thruway and state Department of Transportation projects.

 

http://campaign.r20.constantcontact.com/render?ca=d87df910-023c-4eb5-b9f6-bcac7d294151&c=4897cfb0-a650-11e3-bc68-d4ae5292c426&ch=49f6ea80-a650-11e3-bcd8-d4ae5292c426

Tappan Zee Bridge Skeleton Takes Shape at Tomkins Cove

Khurram Saeed and Theresa Juva-Brown, tjuva@lohud.com9:11 a.m. EDT October 22, 2014

Less than 15 miles from where the new Tappan Zee Bridge is being built, its steely skeleton is being put together. Dozens of workers are assembling fortified steel cages along the Hudson River.

Less than 15 miles from the Tappan Zee Bridge, the steel skeleton of its replacement is being meticulously pieced together.

“The site is perfect,” Ro DiNardo, construction services manager for bridge builder Tappan Zee Constructors, said. “It’s 18 acres, and it has all the space we needed for these activities.”

For the first time, Tappan Zee Constructors on Tuesday offered a behind-the-scenes look at the bustling staging area at Tomkins Cove, a former power plant next to the Hudson River. DiNardo said its proximity to the bridge is saving time on the $3.9 billion replacement project, which is expected to be completed in 2018.

Here’s a breakdown of what’s happening on site:

Pile reinforcement

The estimated 1,000 hollow piles that are being set in the Hudson River are being fortified with cages made of reinforced steel, also known as rebar.

Bridge columns

Workers are also assembling cages that will ultimately become bridge columns. The steel structures are produced in a factory in New Jersey and dipped in hot zinc to strengthen them. The coiled-up steel is loaded on trucks and delivered to Tomkins Cove.

Using detailed diagrams, crews of five workers spend several days creating the sections, some of which are 20 feet long.

Then, DiNardo said, comes the tricky and most dangerous part: pouring the concrete into the mold that is built around sections of steel.

“We actually have to put men inside there so we can pour from the bottom and work our way up,” said DiNardo, of New City. “There are a lot of safety concerns. We have to have an entire plan together before we put anyone in there.”

Tower work

The structures that will be used to build the bridge’s eight towers are under construction at the site, too.

Each rectangular platform, known as climbing forms, has an opening in the middle where the concrete gets poured to create the towers in sections.

A hydraulic lift will raise the structure, with the platform eventually standing more than 30 stories above water.

“As we build, this will move with us,” DiNardo said of the platform.

The climbing forms are expected to arrive at the project site by barge in February.

Improved safety

Because the staging area sits next to an active railroad, the project team and railroad officials have had to make adjustments.

In the past few months, CSX freight trains were left unattended for up to two hours during crew shift changes, blocking emergency access to the site. In one instance over the summer, a worker who had an allergic reaction to something he ate, had to be brought by boat to a medical facility in Westchester.

Tappan Zee Constructors has just finished building a foot bridge over the tracks to allow emergency responders to reach the site by land.

The bridge builder expects to use Tomkins Cove through 2017. Eventually, the site will likely be used to demobilize cranes and other equipment when the work is done.

 

Fast facts

Tomkins Cove staging area: 18 acres

Workers: Approximately 60 not including subcontractors

Truck traffic: 5 to 20 per day

Barge traffic: 1 to 5 per day

Distance to Tappan Zee Bridge site: 14 nautical miles

Ask us about the Tappan Zee

When: Nov. 1 at 11 a.m.

Where: Pierson Park, Tarrytown

What: Journal News/lohud transportation reporters Theresa Juva-Brown and Khurram Saeed will answer questions and listen to comments about our Tappan Zee Bridge coverage. Join them for the informal chat over coffee and snacks.

New Tappan Zee expected to become top tourism destination

The new bridge’s 3-mile walking and biking path could prove to be a major tourist draw.

Will tourists flock to see the new Tappan Zee Bridge?

The answer is years away but it’s conceivable the world’s widest crossing could one day rank alongside New York’s many treasured landmarks, which include Grand Central Terminal, the Brooklyn Bridge and most recently, the Walkway Over the Hudson.

People walking or biking over the Hudson River between Westchester and Rockland will enjoy six scenic overlooks along the 3-mile path. The northerly view would offer stunning vistas of the water, Hook Mountain and the Sleepy Hollow lighthouse.

“That really is a big draw,” said Larry Oakner, senior partner of strategy and engagement with CoreBrand, a marketing consultant firm in Manhattan.

“It may fall into those hidden gem kind of ideas of what New York state has to offer,” he added.

Although the first of the Tappan Zee’s two spans will open in late 2016, the path won’t be ready until 2018 when it will become part of the northern span that carries traffic into Rockland.

A tourism director’s dream scenario would envision thousands of people arriving on weekends to descend upon the path, while pumping money into shops and restaurants in Tarrytown and the Nyacks. Bicycle clubs from New York City and the region would add it to their routes; out-of-state visitors would opt to stay overnight to take in local attractions, including the first major new bridge to be built in the metropolitan area in half a century.

“Just to simply build the bridge won’t deliver the greatest return for you from a tourism perspective,” said Bill Baker, chief strategist of Total Destination Marketing, an Oregon-based firm that helps communities with branding. “They want reasonable experiences, not to just take a photo of it.”

Baker said the landmark offered a unique opportunity for local businesses.

“The parties need to start talking and planning for it,” he said. “There may be some need to commit some funds and perhaps re-purpose some plans.”

Michael Yanko, whose company is constructing a 132-room hotel in Nyack, is banking on the new bridge and walkway drawing visitors from all over. Located off Exit 11 on the Thruway, Nylo Nyack is expected to open in June 2015, targeting both corporate clients and tourists.

“We will have packages for couples to come from the city and to stay in Nyack for the weekend,” said Yanko, a developer and co-owner of WY Management. “Certainly the bike and pedestrian lane and a beautiful bridge is helping.”

In Tarrytown, plans call for putting up a visitors center with parking for about 100 cars near the bridge on South Broadway. The path will connect to South Nyack but exactly where is far from settled. The village is almost entirely residential, further complicating the parking issue.

Rockland County Legislator Nancy Low-Hogan lives in South Nyack and represents several river villages near the bridge.

“In my mind, the (path) is going to be a tourist attraction. Period. End of story. That means opportunity. It also means challenges and that requires planning,” said Low-Hogan, who has taken up the tourism torch with fellow Legislators Alden Wolfe and Harriet Cornell.

They plan to host a meeting next month with officials from South Nyack, Nyack, Grand View, Piermont and Orangetown to talk about next steps. They later hope to expand the sessions to include other local and regional representatives, business leaders and tourism experts.

“Eventually all of these people have to be in this conversation,” Low-Hogan said.

The state Thruway Authority, which owns the Tappan Zee and its replacement, has not released estimates on how many visitors the path could attract.

Some are looking to learn from the experiences of other elevated pedestrian paths, including the High Line in Manhattan and Walkway Over the Hudson, a mile-long converted railroad bridge connecting Poughkeepsie and Highland that has attracted nearly 3 million visitors since opening in 2009.

David Rocco, a Yorktown Heights resident who served on the Walkway’s board of directors from 2005 to 2010, predicted the Tappan Zee path would become a major tourist destination. He visited San Francisco last summer and took a stroll on the 2-mile walkway on the new San Francisco-Oakland Bay Bridge. He thought of home as he saw people jogging and cycling while taking in spectacular views of San Francisco Bay and Candlestick Point.

“I think it’s going to be magnificent,” Rocco said of the new Tappan Zee. “It’s going to be such a draw for both sides of the river.”

However, he said there was the matter of the traffic noise — “It was loud” — but it didn’t take away from his overall enjoyment.

Tappan Zee officials may want to keep an eye on the Bay Bridge to see if its path ends up giving the Golden Gate Bridge a little friendly competition.

More than 5,500 people showed up to use the Bay Bridge Trail on the first Sunday it opened on Sept. 8, 2013.

John Goodwin, a spokesman for the Bay Area Toll Authority, said while there aren’t updated hard figures, he estimated thousands use the path on a good weather weekend, even though it won’t be completed until June. And driving there requires walking a mile from a parking lot just to reach its entrance.

“We weren’t sure how big of an attraction it would be,” Goodwin said. “It proved to be a major attraction indeed.”

Twitter: @ksaeed1

Ask us about the Tappan Zee

Journal News/lohud transportation reporters Theresa Juva-Brown and Khurram Saeed will answer questions and listen to concerns about the Tappan Zee Bridge project from 11 a.m. to noon on Nov. 1 at Pierson Park in Tarrytown. Join them for the informal one-on-one talk over coffee and snacks.

Tappan Zee fast facts

Bridge type: Cable-stayed

Project cost: $3.9 billion

Construction schedule: 5 years, 2.5 months

Project completed to date: 25 percent

Numbers of spans: 2

Traffic lanes: 4 on each span

Breakdown lanes: 1 on each span

Express bus lane/emergency access lanes: 1 on each span

First span opens: December 2016

Second span opens: November 2017

Project physical completion: April 2018

 

http://www.lohud.com/story/news/local/tappan-zee-bridge/2014/10/17/new-tappan-zee-expected-become-top-tourism-destination/17432371/

2014 New NY Bridge Project Monthly Newsletter

 

Art Show Bridges the Hudson:  

Exhibits on Display this Month


Dozens of art works interpreting the Tappan Zee Bridge and marking the construction of the New NY Bridge will be on display this fall at the new bridge project Community Outreach Centers in Rockland and Westchester. The art was created for the New York State Thruway Authority’s 2014 Bridge Art Show, a juried exhibition that invited local painters, sculptors and photographers to showcase their interpretations of the new bridge design or the existing Tappan Zee Bridge.

READ MORE

The New NY Bridge team’s high standards of quality and precision are crucial to the day-to-day operations of the project. To ensure that the bridge’s foundation piles are welded with consistent accuracy, skilled operators are utilizing advanced mechanical welding machines.

READ MORE

The Hudson Valley is a unique geological formation, created by receding glaciers tens of thousands of years ago. As the colossal sheets of ice melted and formed the Great Lakes, the melt-water rushed down the Palisades and filled the Hudson Valley with enough sediment to bury the Statue of Liberty. This torrential force of nature created the striking Hudson Valley landscape and more recently, a number of geotechnical hurdles for the New NY Bridge project.

READ MORE

 

The New York State Thruway Authority, Tappan Zee Constructors, LLC (TZC) and the U.S. Coast Guard have worked together to establish a safe channel for recreational boaters looking to access Piermont’s popular waterfront. The newly-marked channel is part of the New NY Bridge project team’s ongoing efforts to enhance boater safety in and around the construction area.

RED MOR

Frequently Asked Questions
Q: How long will it take to build the bridge?
A: The northern span of the new twin-span bridge is scheduled to open in December 2016. The completed twin-span bridge, with westbound traffic on the new northern span and eastbound traffic on the new southern span, is scheduled to open in April 2018.
Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates

Building the Backbone of the New NY Bridge


Main Span Bases Rise out of the Hudson

August 7, 2014

Two enormous structures with bases the size of football fields are rising out of the Hudson River at the New NY Bridge project site. These concrete monoliths are the pile caps that will act as the structural backbone for New York’s largest bridge and highway infrastructure project, distributing the weight of the bridge onto dozens of steel foundation piles.

The main span pile caps will support the bridge’s 400-foot towers, and require months of preparation to complete.

To construct these main span pile caps, steel pilings are first driven deep into the riverbed, reaching bedrock hundreds of feet below the surface. Once all the piles are in place, a series of concrete floor panels is pieced together around them, outlining the footprint of the pile cap as the supporting base for its concrete pour. The team then positions heavy steel panels precisely around the edge of this footprint to form a massive tub, which is sealed to be watertight and carefully lowered into the river to bring its base to the proper final level for the concrete pile cap.

Next, workers build the pile cap’s reinforcement system inside this lowered tub. The team installs high-strength steel reinforcement bars, called rebar, to closely-engineered dimensions within the form.

The project’s floating batch plantsare then moved adjacent to the pile cap, and each form is filled with concrete specially formulated for long-term durability. The process continues over many hours until the entire footprint is covered with concrete to the specified depth. Once this steel-reinforced concrete hardens, the backbone of the new structure will have taken shape.

Learn more about how steel piles are transported to the project site, or installed with the well-being of local wildlife in mind.

 

 

Read complete Monthly Newsletter here:

http://www.newnybridgegallery.com/updates/august-2014-new-ny-bridge-monthly-newsletter/

CONSTRUCTION CONTINUES ON THE NEW NY BRIDGE

update

Nighttime and overnight electrical work on the Tarrytown approach to the Tappan Zee Bridge will continue the week of August 4. The I-87 northbound/I-287 westbound right lane will be closed Monday, August 4 through Friday, August 8 from 9 p.m. each evening to 5 a.m. the following morning. The Thruway will remain open to traffic during these operations.

Construction will continue in the Hudson River as crews install foundations for the New NY Bridge. Work will include pile driving between 7 a.m. and 7 p.m., Monday through Friday and 12 noon to 7 p.m. on Saturday.

A second shift of workers will also continue pile welding, pile cleanout and concrete placement operations associated with permanent foundations.

Sheet pile driving at locations on land and near the Rockland landing is temporarily on hold due to high noise levels from the operation. TZC will implement additional noise-reducing measures before resuming these operations. Sheet pile driving will commence once the measures are in place. All other construction activities not associated with driving the sheet piles will continue.

Work will also continue on the Rockland temporary work trestle near the county shoreline, including pile driving to install the temporary foundations needed to support the platform. The trestles will support cranes for the construction of the western-most section of the new bridge.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of five knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are illuminated at night as are all moorings, barges and other equipment.

Lane Closures for New York State Thruway (I-87/I-287):

Monday Aug 4 Northbound, Right Lane near Exit 9 10 a.m. to 3 p.m.
Monday Aug 4 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.
Tuesday Aug 5 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.
Wednesday Aug 6 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.
Thursday Aug 7 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.
Friday Aug 8 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.

Ongoing Operations:

  • Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays
  • Pile cap foundation construction
  • Main span foundation construction
  • Rockland landing construction
  • Westchester landing construction
  • River Road utility work
  • Rockland trestle construction, including pile driving
  • Survey inspections on existing bridge
  • Support for river-based work from the Rockland trestle

NEW NY BRIDGE PROJECT MONTHLY NEWSLETTER

President Obama and Governor Cuomo

 Visit New NY Bridge Project Site


With the Tappan Zee Bridge and the New NY Bridge project site in the background, President Obama stood by the Hudson River to make a push for funding transportation infrastructure. The Highway Trust Fund is projected to be insolvent by the fall, and the President is calling on Congress to […]

READ MORE

07-08-2014

The New NY Bridge team is reaching out to New York firms, suppliers and subcontractors – particularly disadvantaged business enterprises (DBEs) – to aid construction efforts. DBEs are defined by the U.S Department of Transportation as small businesses that are owned and controlled by socially and economically disadvantaged individuals such as women, minorities, veterans or disabled persons.

 

READ MORE

07-01-2014 
 

Road work along highways and ramps presents safety challenges to both motorists and construction crews. The New York State Thruway Authority keeps the public informed and up to date on the latest construction activities to help ensure the safety of motorists as well as Thruway and Tappan Zee Constructors, LLC (TZC) workers.

 

READ MORE

06-17-2014 
 

Native to the Hudson River and once plentiful here, the shortnose and Atlantic sturgeon were identified as endangered species and fishing of them was halted in 1996. Since then, the sturgeon population has been growing steadily in the Hudson, one of the species’ most important habitats.…»

 

READ MORE

06-24-2014 
 

The New NY Bridge team is reducing the project’s impact to the environment through the use of construction platforms-known as trestles on either side of the Hudson River. The trestles, which extend 1,000 feet from each shoreline and run parallel to the existing bridge, enable heavy duty machinery to work over shallow water and reduce the […]…»

 

READ MORE

The New NY Bridge project is now accepting submissions for its 2014 Bridge Art Show. The juried exhibit is an opportunity for local artists to showcase their interpretations of the new bridge design or the existing Tappan Zee Bridge.The project’s Visual Quality Panel – which includes Rockland and Westchester representatives involved in the arts, architecture, […]

 

READ MORE

People Behind the New NY Bridge

  

 

Minelly De Coo

Design Production Team Area Manager

Minelly De Coo is an area manager for the design production team, who coordinates efforts between the office and the field. As an environmental specialist, she analyzed sound data and worked with the project’s visual quality panel to help design the project’s noise barriers. Minelly is also involved in the environmental monitoring for the project, overseeing sound monitoring stations and directing crew members in the field. She is notified of any environmental concerns that may arise, and works to see that they are resolved in a timely manner. An invaluable member of the project team, Minelly is proud to see progress on the bridge as it rises out of the Hudson River.  

Frequently Asked Questions 

Q:
A:
The existing bridge has only seven lanes, some of which are narrower than the current standard width of 12 feet. The new bridge will have eight 12-foot-wide lanes. The wide shoulders of the new crossing will greatly reduce the impact of disabled vehicles and accidents, which can cause massive tie-ups on the existing bridge. The incline over the main span will not be as steep, allowing large trucks to maintain consistent speed and reduce engine and braking noise. There will also be gently banked curves to help smooth traffic flow and reduce accidents. The new bridge will also include all-electronic toll collection technology, which allows motorists to pay tolls without slowing down from highway speeds. Motorists without E-ZPass will be automatically billed by mail.
Get Your E-ZPass® “On-the-Go”at the 

View the latest issues of theNew NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates

 

Tappan Zee: Artists prepare for Bridge Art Show

LoHud By Theresa Juva-BrownTjuva@lohud.com11:07 p.m. EDT June 23, 2014

For Kenneth Burns, the Tappan Zee Bridge is a crossing between his bustling city past and his quieter suburban life.

“I love my life up here,” he said. “The bridge gave me that.” After working and living in New York City for decades, the 70-year-old is now retired in New City, where he has spent the past eight years developing himself as a painter. He dabbles in watercolor and acrylics. “I mainly do landscapes, abstract landscapes,” he said. “I’m not ever going to make money out of it — it’s just a joy. It’s fun.”

The 2014 Bridge Art Show

Burns is working on a Tappan Zee painting to submit to the 2014 Bridge Art Show, sponsored by the Tappan Zee project team, along with ArtsWestchester, Rockland Center for the Arts, Rivertown Artists Workshop and Nyack Art Collective.The show, which is accepting entries from the public, has already drawn six submissions since it was announced earlier this month, officials say. “You will recognize the bridge, but it will be kind of a cloudy situation,” Burns said of his piece. “Moody is the the proper word. Not much color involved.” Photographers, painters and sculptors have until July 31 to submit their interpretations of the old and new Tappan Zee.

The project’s visual quality panel will select one winner and two runners-up. All the pieces will be displayed at the project’s community centers in Nyack and Tarrytown. For more show guidelines, see newnybridge.com. Mary Louise Allen, Burns’ wife, said she is excited about the exhibit. “I would love to see what my husband comes up with and see how he stacks up against the other local artists,” she said. “It will help him in his pursuit as an artist. He is always inspired by seeing the work of other artists.”

 

Read Complete article on line here: http://www.lohud.com/story/news/local/tappan-zee-bridge/2014/06/23/tappan-zee-artists-prepare-bridge-art-show/11108353/

 

State to loan $511M for new TZ Bridge

LoHud; Joseph Spector, TJN3:03 p.m. EDT June 16, 2014

1402940492000-nnyb-rend-15

The state’s Environmental Facilities Corp. said today it will loan up to $511 million to the new Tappan Zee Bridge project, a move that will help with the financing of the $3.9 billion project.It’s the latest effort by the state to fund the bridge and limit toll increases when the new 3-mile span across the Hudson River is completed in 2018.“As we continue to see progress on the New NY Bridge, it is essential that actions are taken to protect wildlife and address the project’s environmental impacts – but in a way that doesn’t overburden taxpayers and drivers,” Gov. Andrew Cuomo said in a statement obtained by Gannett.

The loan, which is financed through federal aid, will be used for environmental protection and Hudson River restoration projects related to the bridge’s construction. The projects include protecting water quality and marine life in the Hudson River estuary, including endangered sturgeon, oyster beds and other habitats.The loan comes through the EFC’s Clean Water State Revolving Fund. State officials said it won’t impact other projects.It’s the newest loan for the project. The largest loan, $1.6 billion, was announced last year by the federal Department of Transportation.

With the low-interest loans, state officials said it will help keep tolls down on the new bridge, which is being financed through the state Thruway Authority. The round-trip toll on the current bridge is $5, but there have been concerns that it could go as high as $14 on the new bridge.The Thruway Authority will need to approve the loan and is expected to start using it in August, state officials said.The Environmental Facilities Corp. is the financing arm for the state to provide low-interest loans to local governments and agencies for drinking water, wastewater infrastructure and other clean-water projects.Last year, EFC financed close to $2 billion in clean-water investments statewide, a news release from Cuomo’s office said.

http://www.lohud.com/story/news/politics/politics-on-the-hudson/2014/06/16/state-loan-511m-new-tz-bridge/10627953/

 

FOUNDATION WORK CONTINUES ON THE NEW NY BRIDGE

Bridge Project Update

For immediate release: May 30, 2014

new

FOUNDATION WORK CONTINUES ON THE NEW NY BRIDGE

Construction of the New NY Bridge continues the week of June 2 with pile driving between 7 a.m. and 7 p.m., Tuesday through Friday. A second shift of workers will also continue pile welding operations associated with permanent foundations.

Marine crews are working from the shorelines of Rockland and Westchester counties, moving outward to place permanent foundation piles. Work on the foundations for the main span will continue as well. To learn more about the main span foundation and tower construction see the new “Bridge Rising” animation on NewNYBridge.com

Work will also continue on the Rockland work trestles near the county shorelines, including pile driving to install the temporary foundations needed to support the platforms. The trestle will support cranes for the construction of the western-most sections of the new bridge.

Lane Closures for New York State Thruway (I-87/I-287):

Monday June 2 Southbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Tuesday June 3 Southbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Wednesday June 4 Northbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Thursday June 5 Northbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Friday June 6 Northbound, Right Lane near Exit 10 10 a.m. to 1 p.m.

 

Mariners should be aware that TZC will continue installing permanent piles in the vicinity of the side channels under the existing bridge, weather permitting. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night. An interactive map showing vessel locations on the Hudson River is now available on the project website, NewNYBridge.com, for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.  More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here.

Ongoing Operations:

  • Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays
  • Rockland Landing construction
  • Westchester Landing construction
  • River Road utility work
  • Rockland trestle construction, including pile driving
  • Survey inspections on existing bridge
  • Support for river-based work from the Rockland shoreline
  • Armoring of Dredge channel
  • Construction of Temporary Joint Facility at exit 12

Tappan Zee Bridge contracts ensure ‘disadvantaged’ aren’t left out

tjuva@lohud.com11:22 p.m. EDT April 16, 2014

The Tappan Zee Bridge project has been a dream opportunity for small, budding businesses. And companies headed by women and ethnic and racial minorities are getting their own chances to score work on the $3.9 billion bridge replacement project, through a government effort to give a boost to certain groups that have historically been excluded from business opportunities.

The New York State Thruway Authority and bridge builder Tappan Zee Constructors is setting aside $314 million — 10 percent of the bridge construction cost — for companies certified as “disadvantaged business enterprises” by the federal government. Because the federal government is providing a low-interest loan to help pay for the Tappan Zee replacement, it requires that such companies are included. Brian Conybeare, special adviser to Gov. Andrew Cuomo on the project, said the project team has made a big effort to ensure those firms are included, “which will help them prosper, grow their businesses and employ more local workers.” So far, 60 certified DBEs have contributed to the project, totaling $49.7 million in subcontracts.

Here are some of their stories.

 From ironworker to business owner, Mike Aponte can still vividly recall his first day as an ironworker nearly 30 years ago. Aponte, now 48, was assigned to get coffee for crews building a high-rise on Wall Street.

“Never been up that high — I was shaking in my boots, but I didn’t show it to the men. That was some experience,” Aponte recalled.After working his way up from an ironworker to a foreman to a project supervisor, seven years ago Aponte became the president of his own steel construction company, Tyrek Heights Erectors Inc., a certified DBE based in Yonkers.”In general there has been the misconception that you can’t find a qualified a DBE — that’s not true,” he said. “There are many that are capable and put out quality work. We are not taking advantage of it. We actually perform. We know what we are doing.”So far, his company has done steel work at the TZC office on the Hudson Harbor property in Tarrytown. The firm has also removed and installed steel at the West Nyack building where the state police and Thruway Authority facilities will be temporarily relocated during bridge construction.

Still, Aponte has his sights set on the new structure”I would love to be part of the team that is going to erect and build the bridge,” he said. “To say one day to my grandkids, ‘I was part of this bridge,’ would be great.”

 

In the business of construction, Mahopac native Leigh Scirbona has never been daunted by working in a male-dominated industry. In her 20s, she began working for a highway construction company, reviewing contracts and handling project documents. For the last 25 years, Scirbona, now 56, has headed her own general contracting and concrete company, Advanced Contracting Concepts. The company has done work for the Walkway Over the Hudson project, Westchester and state parks and the New York State Bridge Authority. “I still have people who call me and say, ‘Honey, let me speak to your boss,’ ” she said. “It is still entertaining when they do that.” Last year, she expanded the company to construction administrative support services and landed work on the Tappan Zee project.  “A little over a year later, I’m on one of the largest design-build projects in the United States and one of the largest projects in New York state,” she said. “It’s been terrific.”

When TZC officials called her last year about finding them an office receptionist, Scirbona quickly responded. Not wanting to lose the chance, she worked the job herself for a week until she found someone permanent for the position. Scirbona has six employees as part of the Tappan Zee team, including the project’s documents control manager and a senior administrative assistant, and she hopes to keep expanding the list.The DBE program is critical to ensure all kinds of business owners are included in major infrastructure projects, she said.

“It doesn’t make us less qualified, less intelligent, less capable,” she said. “Without this program, smaller contractors wouldn’t get looked at.”

 

Husband and wife

Cynthia and John Behan share a business, but Cynthia is the one in charge “She really is the boss,” said her husband, co-owner of Behan Planning and Design, a landscape architecture and project planing firm and certified DBE. “She makes all the financial decisions. She makes all the hiring decisions. My role is now securing new work.” Such as the Tappan Zee project. The Behans’ firm, based in Saratoga Springs with a location in New City, has a subcontract with a public relations group hired by TZC. So far, the Behans’ company has helped organize Tappan Zee community outreach meetings and create public newsletters and presentations.

“To have this project that’s running steady for a while, it’s stabilizing for us,” said Cynthia Behan, 58, a landscape architect who also worked on the New City streetscape revitalization. John Behan, also 58, said his wife’s design knowledge is especially helpful when they are asked to put together presentations. “When we get technical documents from the engineers, she can understand the engineer drawings and help present them to the public,” he said. While their Rockland location only has one employee, the couple hopes more work on the project will allow them to hire a second one later this year.

How is a “disadvantaged business enterprise” defined?

The small company must be 51 percent owned by one or more “socially and economically disadvantaged” individuals, which are women and racial and ethnic minority groups.

Business revenue and the owner’s personal net worth are used to determine whether a company qualifies. Government officials conduct personal interviews, business visits and reviews of license and financial records before a firm is certified.

Source: New York State Thruway/U.S. Department of Transportation

TZB firms by the numbers

A total of 135 companies have worked on the project so far, totaling $432 million in subcontracts.

Of those, 60 are considered DBEs, with those subcontracts totaling $49.7 million.

$314 million has been set aside for DBEs

Source: Tappan Zee Constructors

February New NY Bridge Newsletter

newsletter

The New York State Thruway Authority and the New NY Bridge team are proud to present the February issue of the New NY Bridge Newslettera monthly publication designed to keep everyone abreast of the latest news about the project.

 In this issue:

American Made: New York Businesses Benefit From New NY Bridge Project

High Steel Structures, LLC: A Brief Look at One of The Nation’s Pre-Eminent Steel Producer

Reaching the Next Generation: New NY Bridge Project Presents for Science Week

Safety: Personal Protection Equipment (PPE)

Please enjoy the February New NY Bridge Newsletter.

 

Port Expected in Newburgh NY

By James Walshbilde (1)
Times Herald-Record
Published: 2:00 AM – 01/31/14

CITY OF NEWBURGH — A riverfront company aims to build a port on the Hudson from which it can transport decking for the new Tappan Zee Bridge.

Officials of Steelways Inc. and the city will join federal and state officials Friday morning to announce the effort, which Steelways spokeswoman Susan Sullivan said could bring 150 jobs over three years.

Mayor Judy Kennedy and Councilwoman Genie Abrams declined to discuss details of the plan in advance of Friday’s announcement, though both spoke glowingly — in general terms, anyway — of its potential. Among the expected attendees are Rep. Sean Patrick Maloney, D-Cold Spring, state Sen. William Larkin, R-C-Cornwall-on-Hudson, and Assemblyman Frank Skartados, D-Milton.

“This project has such potential,” Kennedy said. “It can truly change the economics of Newburgh.: Abrams said: “It will be very good news for the people of Newburgh, the kind of news we haven’t heard in 50 years.”

Sullivan said the company will bid on Friday to supply precast concrete decking for the new Tappan Zee Bridge. The contract will likely be awarded within a few weeks. Steelways can begin work on the port in April and complete the project by late summer. The company’s website says its 60 waterfront acres already include a shipyard with three sheltered harbors.

It has concrete marine launchways capable of accommodating vessels up to 300 feet long and 125 feet wide, and a marine railway capable of hauling 500-ton vessels. The main shipping channel runs adjacent to Steelways’ main pier, according to the site.

A resolution adopted Monday by the City Council expressed its “conceptual support of the Port of Newburgh project,” saying it will boost Newburgh’s economy by creating high-paying jobs and providing job-training opportunities for city residents.

Thomas Wright, a co-owner of Atlas Industries, a furniture designer and maker in the city, said who gets the potential jobs is important. “Jobs are great, but where do the people eat and live?” Wright said. “Are they people from Middletown driving to a parking lot, or people in Newburgh walking from their home in the city?”

Newburgh was once such a busy port that it had its own U.S. Customs office. Sailing ships were built at the waterfront in the 18th century. Navy ships were docked in Newburgh for repairs and reconstruction during World War II, said Mary McTamaney, the city’s historian. The Newburgh waterfront was where farmers brought their produce for shipping to New York City and beyond. “We were a transportation city,” McTamaney said. “We brought the goods of Orange County and the region to market, mostly downriver.”

jwalsh@th-record.com

http://www.recordonline.com/apps/pbcs.dll/article?AID=/20140131/NEWS/401310366

Super Crane Clears the Panama Canal

bilde

For immediate release: January 17, 2014

I LIFT NY SUPER CRANE COMPLETES TRANSIT THROUGH PANAMA CANAL,
CONTINUES JOURNEY TOWARD NEW NY BRIDGE PROJECT SITE

The I Lift NY super crane’s journey to the New NY Bridge project began on Dec. 22 and continues as the floating crane completed its transit through the Panama Canal on Jan. 17. Updated information about the journey, including photos and video, will be available at NewNYBridge.com.

The recently nicknamed I Lift NY super crane is owned by Tappan Zee Constructors, LLC (TZC) and is officially registered with the U.S. Coast Guard as the Left Coast Lifter.

TZC resumed operations this week after severe winter weather and icy conditions required the suspension of work on the river for one week for safety purposes. Foundation construction of the New NY Bridge will continue beginning Monday, as weather permits, with the ongoing installation of permanent piles.

The northbound, right-hand lane and shoulder of the New York State Thruway (I-87/I-287) near exit 10 in Nyack will be closed from 10 a.m. to 3 p.m. on Tuesday, Jan. 20, through Thursday, Jan. 23, to allow for work on the northbound access ramp.  The same lanes will be closed on Friday, Jan. 24 from 10 a.m. to 1 p.m.

Mariners should be aware that TZC will continue installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) – 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website at NewNYBridge.com under the “Boater Safety” icon.

Ongoing Operations:

  • Rockland access ramp modifications
  • Armoring of dredge channel
  • River Road utility work
  • Test pile program
  • Permanent pile installation
  • Temporary Rockland trestle construction, including pile driving on weekdays 7 a.m. to 7 p.m.
  • Survey inspections on existing bridge
  • Support for river-based work from the Rockland shoreline
  • Reinforcement steel pre-assembly at bridge yard

A Colossal Bridge Will Rise Across The Hudson

 

TZ Under construction

Expected to last 50 years, the Tappan Zee Bridge also known a “The Longest Bridge in New York” is rebuilding what might be the “Widest Bridge in the World”.

Read the complete article here:  http://www.nytimes.com/2014/01/20/nyregion/a-colossal-bridge-will-rise-across-the-hudson.html?hp&_r=0

 

GIANT FLOATING CRANE PREPARES FOR PASSAGE THROUGH THE PANAMA CANAL, EN ROUTE TO NEW NY BRIDGE PROJECT

bilde

The new NY bridge

For immediate release: January 10, 2014

GIANT FLOATING CRANE PREPARES FOR PASSAGE THROUGH THE PANAMA CANAL, EN ROUTE TO NEW NY BRIDGE PROJECT

The journey that began late last month for one of the world’s largest floating cranes continues as it prepares to pass through the Panama Canal this weekend.

The crane, known as the Left Coast Lifter, is expected to begin its passage through the Panama Canal as soon as Saturday, Jan. 11, and updated information on its journey will be available at NewNYBridge.com. It departed from Oakland, California, on Dec. 22, escorted by tug boats, and is expected to arrive in New York at the end of the January.

A fourth construction camera is now live and is also available on the project website. The public can stay up-to-date on the progress of the New NY Bridge project with views from this camera, which captures construction as viewed from Tarrytown, as well as through those already live from Rockland County, Westchester County and on the bridge. An interactive archive calendar also allows viewers to take a look back at progress already made.

As weather permits, Tappan Zee Constructors, LLC (TZC) will continue construction of the foundation of the New NY Bridge with ongoing installation of permanent piles. TZC plans to begin full production again on Monday, Jan. 13, assuming temperatures rise and ice clears the river.

On Monday, Jan. 13 and Tuesday, Jan. 14, the southbound, right-hand lane and shoulder of the New York State Thruway (I-87/I-287) near exit 10 in Nyack will be closed from 10 a.m. to 3 p.m. On Wednesday, Jan. 15 and Thursday, Jan. 16, the northbound, right-hand lane and shoulder of the Thruway (I-87/I-287) near exit 10 in Nyack will be closed from 10 a.m. to 3 p.m., to allow for work on the northbound maintenance ramp.

Mariners should be aware that TZC will be installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) – 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website at NewNYbridge.com under the “Boater Safety” icon.

Ongoing Operations:

• Rockland access ramp modifications
• Armoring of dredge channel
• River Road utility work
• Test pile program
• Permanent pile installation
• Temporary Rockland trestle construction, including pile driving on weekdays 7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline
• Reinforcement steel pre-assembly at bridge yard

Giant crane Left Coast Lifter on way to build new Tappan Zee Bridge

 Ocean voyage expected to take 6 to 8 weeks

LoHud December 31, 2013 Theresa Juva Brown

http://www.lohud.com/videonetwork/2968321291001/Left-Coast-Lifter-heads-for-Tappan-Zee-Bridge-project

The gargantuan crane that will help build the new Tappan Zee Bridge is on its way.

New video released by bridge builder Tappan Zee Constructors shows the Left Coast Lifter passing under the Golden Gate Bridge in San Francisco this week as it begins its 6,000-mile voyage to the Hudson River. The journey is expected to take six to eight weeks. The 400-foot-long floating crane — one of the world’s largest — will travel down the West Coast, through the Panama Canal, across the Gulf of Mexico, up the East Coast and through New York Harbor.

The Left Coast Lifter, previously used on the San Francisco-Oakland Bay Bridge project, can lift 1,750 metric tons, or 12 times the weight of the Statue of Liberty. It will help install the huge deck panels on the new Tappan Zee and demolish the existing Tappan Zee in 2017.

The crane is owned by Fluor Corp. and American Bridge Co., two of the companies that make up Tappan Zee Constructors.

bilde

 

Read complete article here: http://www.lohud.com/article/20131231/NEWS02/312310014/Giant-crane-Left-Coast-Lifter-on-way-to-build-new-Tappan-Zee-Bridge-(video)?nclick_check=1

Construction Continues From US9 to TZ Bridge

new

For immediate release: December 6, 2013

INSTALLATION OF PERMANENT PILES CONTINUES,
TARRYTOWN RAMP FROM US9 SOUTH TO TAPPAN ZEE BRIDGE CLOSES

Construction activities continue on the foundations for the New NY Bridge with the ongoing installation of permanent piles.

The entrance ramp to the Tappan Zee Bridge (I-87 northbound/I-287 westbound) from South Broadway (Route 9) in Tarrytown is now closed to traffic for the duration of the New NY Bridge project. Signs are in place to direct motorists to the entrance ramp located nearby on White Plains Road (Route 119.)

As a result of the closure, motorists who wish to travel northbound/ westbound on the Thruway are directed to bear right immediately after the closed ramp, onto what is referred to as the “jughandle” for Route 119. Motorists will proceed approximately 0.2 miles east on Route 119, turning right onto the I-87 northbound/I-287 westbound entrance ramp.
Walkways along South Broadway will be maintained for pedestrian use.

Tappan Zee Constructors, LLC (TZC) will utilize the area surrounding the ramp for storage and staging, which will in turn reduce the amount of construction traffic on local roadways. Complete closure is required for the construction of the New NY Bridge in order to ensure safety for motorists and project workers.

Excavation and preparation work for installation of permanent sound barriers continues along I-87 northbound /I-287 westbound in the area south of exit 10 in Rockland County. From Monday, Dec. 9 to Thursday, Dec. 12, one northbound right-hand lane and shoulder on I-87/I-287 near exit 10 in Nyack will be closed from 10 a.m. to 3 p.m. and Friday, Dec. 13 from 10 a.m. to 1 p.m.

Mariners should be aware that TZC will be installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard in the future may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website under the “Boating Safety” icon.

Ongoing operations:
• Rockland access ramp modifications
• Armoring of dredge channel
• River Road utility work
• Test pile program
• Rockland Dock Extension – finishing work under existing bridge
• Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline
• Reinforcement steel pre-assembly at bridge yard

 

###

Inaugural Newsletter of the New NY Bridge

 

MonthlyNewsletter_Nov_2013 (3) Page 001

 

The New York State Thruway Authority and the New NY Bridge team are proud to launch the first issue of the New NY Bridge Newsletter, a monthly publication designed to keep everyone abreast of the latest news about the project.

The newsletter, produced in partnership with Tappan Zee Constructors, LLC (TZC), is one of many outreach tools employed to keep residents of Rockland and Westchester counties and the entire region informed about the New NY Bridge Project — the largest transportation infrastructure project in North America. Please enjoy the inaugural issue of the New NY Bridge Newsletter.

 

Read the complete Newsletter document here: MonthlyNewsletter_Nov_2013 (3)

Tappan Zee Bridge; A Video Introduction

Click here: A Bridge to a New Era Video

 

The Tappan Zee Bridge today can be nearly synonymous with traffic, from spectacular jams on the steel superstructure to residual delays clogging streets in Tarrytown and Nyack. The bridge almost 60 years ago was heralded for linking two villages, two counties and carrying “possibly (the) most modern super highway in the world,” according to the Rockland Journal-News. As the region and its residents ready to watch Tappan Zee 2.0 cross the Hudson River, The Journal News looks at the beginnings of the first bridge and what the second one may bring.

Read more:  http://tappanzeebridge.lohud.com

 

Feds Will Loan Up to $1.6 Billion for TZ Bridge Construction

A Big Loan  for a Big Project

New City Patch, Posted by  (Editor) , 
patch
Photo credit: Carlos Gonzalez
Photo credit: Carlos Gonzalez

The U.S. Department of Transportation has approved a loan of up to $1.6 billion through its Transportation Infrastructure Finance and Innovation Act (TIFIA) program for construction of a new Tappan Zee Bridge.

The loan is the largest ever in the history of the TIFIA program.

The Secretary’s approval comes after the DOT’s Credit Council met this morning to review the loan application, said Congresswoman Nita Lowey (D, Westchester-Rockland).

Yesterday, Lowey wrote a letter urging the DOT to expedite consideration of the TIFIA application. It can be viewed here.

“This is a huge milestone for the construction of a New Tappan Zee Bridge, a critical link in our region’s infrastructure system and lifeline for commuters and businesses,” she said in a statement. “I am excited that the DOT has approved the largest ever TIFIA loan for a transportation project and that the work on a new bridge can continue to move forward.”

Actual construction started last week. Patch has that and all the TZB news on our dedicated page.

Gov. Andrew Cuomo said, “”Approval of New York State’s request for this loan is great news for the tens of thousands of commuters who depend on the Tappan Zee every day, for communities in the Lower Hudson Valley, and for our entire state.

“This is a huge win for New York State, creating thousands of jobs, and an endorsement of one of the most ambitious infrastructure projects in our history. It shows that despite over a decade of delay, New York can continue to build big,” Cuomo said.

Plans for a new bridge to replace the Tappan Zee were first discussed in 1999, and over the next 11 years, $88 million in taxpayer dollars was spent, 430 meetings were held, 150 concepts were considered, according to the governor’s office.

State Assemblyman David Buchwald said, “Today’s announcement is a victory for all New Yorkers. It reaffirms our progress on building the new Tappan Zee Bridge that is essential for our region’s economic vitality. I applaud Governor Cuomo for his leadership through each phase of this important project.”

Harriet Cornell, Chairwoman of the Rockland County Legislature, said the new bridge would be an important addition to the nation’s transportation network.

“Governor Cuomo has made this project a signature issue, and the federal government recognized its significance by granting the largest TIFIA loan in history,” Cornell said. “This bridge will provide economic development, thousands of jobs during construction, access to the entire Northeast and will be a magnificent sight spanning the Hudson River. This is wonderful news.”

Westchester County Executive Rob Astorino also congratulated the governor; but, he pointed out there are still financial issues to be dealt with.

“I congratulate Governor Cuomo on this good news. The next step is how do we finance the rest of the bridge and the mass transit improvements to and from the bridge, while keeping tolls as low as possible,” Astorino said. “The governor has my full support to help the state come up with the best financing plans possible.”

http://newcity.patch.com/groups/transportation/p/feds-will-loan-up-to-16-billion-for-tz-bridge-construction-newcity?ncid=newsltuspatc00000001&evar4=picks-1-post&newsRef=true

 

Parking TZ Construction workers a challenge in Tarrytown

October 12, 2013 Theresa Juva-Brown

The consortium building the new Tappan Zee Bridge is learrning that finding parking for its workers can feel just as complicated as dredging the bottom of the Hudson River.

Tappan Zee Constructors is already renting an office and 135 parking spaces on the property of Hudson Harbor, a condominium complex in Tarrytown. To accommodate the growing number of construction workers, TZC wants to add up to 165 parking spaces there.

But doing so would violate Tarrytown’s zoning code, which calls for that vacant area to eventually be used for condominiums, village officials say.

The rule also requires that Hudson Harbor’s parking lots be used by people who live or work there.

The new parking area would be used by bridge workers who would take boats from a nearby pier to construction sites on the river.

“What’s embedded in the zoning code is the municipal desire not to have parking lots all over the place — that’s why (Hudson Harbor) is not zoned for parking and it’s slated for development,” Tarrytown Mayor Drew Fixell said. “Having a parking lot for construction work on the Tappan Zee Bridge was not envisioned for this.”

Fixell noted that there were other parking areas TZC could consider in or near the village, but those options may not be as convenient and could involve paying for permits.

TZC declined to comment on the parking proposal. State officials and a Hudson Harbor spokesman did not respond to requests for comment.

Village Administrator Mike Blau said trustees would have to approve a zoning code amendment to allow the new lot. He added that several Hudson Harbor residents have expressed to him their concern about the idea.

Trustees are expected to discuss TZC’s proposal next week and make a decision in the coming weeks, Blau said.

 

Read complete article here: http://www.lohud.com/article/20131012/NEWS/310120108

New Tappan Zee Bridge spurs interest in nearby commercial parcels; Vacant commercial sites now sold, leased

bilde

LoHud October 15, 2013 Written by Theresa Juva-Brown

The Tappan Zee Bridge replacement project is giving new life to vacant commercial properties that have languished since the Great Recession.

The site of the former Lovett power plant in Stony Point, for instance, sat unused for years before bridge builder Tappan Zee Constructors recently signed a lease with NRG Energy to assemble bridge pieces there. As part of the deal, Stony Point could collect up to $500,000 in permit fees over the next five years.

It’s been a similar situation in West Nyack, where the former Journal News printing plant at 160 N. Route 303 hasn’t had a tenant in three years, said Timothy Hauser of the Hauser Bros., the real estate investment company that owns the site.

That will change this spring, when state police and the New York State Thruway Authority temporarily move from Tarrytown to the 42,000-square foot warehouse that is currently being renovated.

Tappan Zee Constructors is relocating those operations because it plans to tear down the current barracks/Thruway offices on North Broadway and use the area for bridge construction equipment.

“We’re giving them a piece of property at a fair market value rate, and they are taking the expenses off my lap that I have to struggle to pay,” Hauser said of the parcel on Route 303 near Thruway Exit 12. Just before the deal was reached in April, the asking price for the warehouse was $6.25 per square foot, according to the website of Rand Commercial Services, which was involved with the agreement.

Hauser said the five-year lease could be extended, but for now the site’s future remains wide open.

“It’s one of the best locations in the entire county for any type of business — a car dealer, hotel. It’s a discussion already,” he said.

The recent deals, even if they are for just five years, help the local real estate industry but also the region’s optimism about the overall economy, said Paul Adler, vice president of Rand Commercial.

“People are understanding that this is the beginning of the growth,” he said. “What we’re seeing is just enough to nudge us out of this recession.”

“There is income, and there is enough time to plan what to do after five years now that the landlord has cash flow,” he added. “These 5-year injections of confidence in the market are going to spur smart growth.”

The new bridge, especially the thousands of workers the project will bring, helped convince Howard Josephs to purchase a commercial parcel in Nyack last month.

Josephs, a partner with Josephs Group, bought slightly less than an acre near Route 59 and Waldron Avenue.

A gas station and fast food joint once operated there, but the site has been dormant for years, he said.

After the land is remediated this winter, he plans to build a 5,000-square foot restaurant and retail center.

He declined to disclose how much he paid for the site.

“It’s a very busy corner, and we see it as the gateway to Nyack,” he told The Journal News. “I think the bridge (project) will definitely bring a lot of people for a number of years.”

The project is also giving a lift to property owners in Westchester.

Tappan Zee Constructors moved into its main office on White Plains Road in Tarrytown this spring and is leasing a satellite office on the grounds of Hudson Harbor, a residential complex on the Tarrytown waterfront.

Farrokh Hormozi, an economics professor at Pace University in Pleasantville, said property owners who are leasing instead of selling is a sign that they expect their assets to gain significant value after the new bridge is completed. He said more businesses and people will want to live and work near the future Tappan Zee. “It’s all facilitated by a more comfortable ride across the bridge,” he said.

Read complete article here:http://www.lohud.com/apps/pbcs.dll/article?AID=/201310142341/NEWS/310140063

 

Original Tappan Zee Bridge parts will be salvaged for other projects

Written by: Khurram Saeed; Twitter: @ksaeed1

bilde

Though the Tappan Zee Bridge is destined for demolition in a few years, some of its  parts and equipment may find new life elsewhere.

The state Thruway Authority intends to save elements of the bridge when it’s torn down in 2017 to make way for its $3.9 billion replacement. The authority has provided a  list of  materials to be saved in its contract with Tappan Zee Constructors, the team designing and building the new crossing.

The list includes  150 concrete deck panel units from the bridge’s causeway; 15,000 feet of steel barrier installed on them; the movable barrier and the machines that shift it; the bridge’s necklace lighting; light stanchions; fiber-optic cables and other equipment.

“Anything that can be salvaged by others will be salvaged,” said Ted Nadratowski, the Thruway’s interim director of maintenance and operations.

The elements will be used for other Thruway projects. Nadratowski said the precast deck panels, for example, could be shortened and used as small culverts on the Thruway.

Recent rehabilitation work includes $385 million to replace much of the road deck on the Tappan Zee since 2007. The project is largely complete and is expected to wrap up by the end of this month, Nadratowski said.

Reusing some of the old bridge was a good idea, said Assemblyman Tom Abinanti, D-Mount Pleasant.

“The old adage of reduce, reuse and recycle applies here,” he said.

Abinanti said he was “disappointed” that Thruway officials didn’t put more emphasis on finding another use for the bridge. He was among those who pitched the idea of using the old bridge as a park. But that wouldn’t be possible since the new southern span will meet land where the current bridge sits.

Still, he suggested part of the bridge could have been reused or the landing redesigned to incorporate fishing piers or some amenity for the public.

“They never did a serious study of how can you use the existing structure in some way, shape or form,” Abinanti said. “I like the idea of reusing it any way you can.”

http://www.lohud.com/article/20130919/NEWS02/309170068

Regulators release Hudson River restoration plan

Written by : Associated Press

ALBANY, N.Y. — A draft plan released by state regulators on Tuesday will guide efforts to restore and protect the Hudson River Estuary from the Troy dam to the Tappan Zee Bridge.

The Department of Environmental Conservation is taking public comment on the plan until the end of October and is holding public information sessions Wednesday afternoon at Margaret Norrie State Park in Staatsburg and Sept. 24 at Columbia Greene Community College in Hudson.

The plan identifies four priority habitats for restoration: tidal wetlands, shallows, shorelines and tributaries. It says those habitats are important to the overall health of the ecosystem but have been degraded or destroyed on a large scale by development.

About half the estuary’s shoreline remains in a natural state, but the rest has been engineered with walls and other structures to protect property or support transportation, recreation or industrial activities.

Besides harming wildlife, loss of shoreline wetlands and shallows has made riverside communities more vulnerable to flooding by removing natural barriers that protect against weather extremes and rapid sea level rise, authorities said.

“Restoration of healthy habitats will provide benefits for fish, birds, turtles, crabs, mammals and invertebrate animals and to the residents of the Hudson River Valley and the state of New York,” DEC Commissioner Joe Martens said in a prepared statement.

Habitats in the estuary, which is tidal up to the federal dam at Troy, have been damaged since the early 1800s by navigational dredging, filling of wetlands, construction of the railroad along sensitive shoreline habitats and construction of dams in tributaries.

The habitat restoration plan is intended to be used by community groups, governments, scientists and conservation organizations.

Restoration actions identified in the plan include dam removal and culvert improvement in tributaries to promote fish passage; invasive-species control programs; preservation of existing shore land habitat; and use of environmentally sound methods of shoreline stabilization where necessary to protect property.

ROCKLAND TEMPORARY TRESTLE CONSTRUCTION BEGINS

update

For immediate release: August 23, 2013

Work is scheduled to begin the week of August 26 on the Rockland trestle, which is the second temporary work platform to be constructed as part of the New NY Bridge Project.

The work will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to a maximum of 7 a.m. to 7 p.m. on weekdays and, occasionally, on Saturdays from 12 noon to 7 p.m. The trestle is a work platform that will eventually support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required near the Rockland shoreline

Impact pile driving will continue as part of the ongoing test pile program and will continue through October at various locations for future pile foundations. This work will be performed from 7 a.m. to 7 p.m. on weekdays and, occasionally, on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

Beginning Monday, August 26 through Wednesday, August 28, one northbound right hand lane and shoulder on I-87/I-287 between the existing Tappan Zee Bridge and Interchange 11 in Nyack will be closed from 9 a.m. to 3 p.m. for the installation of concrete traffic barriers to delineate traffic from the construction zone to ensure safety for traveling public and work crews.

Additional geotechnical borings to support design will be conducted on the river at various locations. Operations will run 24 hours a day, Monday through Friday.

Tappan Zee Constructors (TZC) will continue dredging operations in the Hudson River as part of the New NY Bridge Project. Dredging will occur through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.

Dredging crews will work 24/7 starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.

Ongoing operations:
– Test pile program

– Rockland bulkhead construction (including fence & gates) and Dock Extension at Rockland (under existing bridge)

– Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.

– Survey inspections on existing bridge

– Mobilization at the exit 10 staging area

– Support for river-based work from the Rockland shoreline
Rockland:
TZC will be installing temporary noise barriers along the right of way adjacent to I-87/I-287 near Ferris Lane. Fencing and sidewalk work will continue along River Road in South Nyack north of the existing bridge. This work is part of the bulkhead construction area and will be performed on weekdays between 7 a.m. and 3 p.m. At times, River Road will be limited to one lane with flag persons in place to ensure the safe flow of traffic.

New NY Bridge Update August 16, 2013: LOAD TESTING FOR THE TEST PILE PROGRAM BEGINS; LANE CLOSURES ON BRIDGE

bridge

For immediate release: August 16, 2013

LOAD TESTING FOR THE TEST PILE PROGRAM BEGINS;
LANE CLOSURES ON BRIDGE

Tappan Zee Constructors, LLC (TZC) will begin testing both static and lateral loads this week as part of its test pile program.

These load tests are performed to ensure piles are capable of sustaining the design load of the new bridge. Testing will be conducted over a 40-hour period.

Impact pile driving will continue this week as part of the ongoing test pile program and will continue through October at various locations for future pile foundations. This work will be performed from 7 a.m. to 7 p.m. on weekdays and, at times, on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

Overnight lane closures will also be required in both directions on I-87/I-287 and the Tappan Zee Bridge due to various construction activities.

Beginning Monday, August 19 through the morning of Wednesday, August 21, one southbound right hand lane and shoulder between exit 11 and the Tappan Zee Bridge will be closed from 9 p.m. to 6 a.m. for the installation of concrete traffic barriers to facilitate the reconstruction of the Thruway maintenance ramp. Additionally, one southbound right hand lane on the Tappan Zee Bridge will be closed during this period for the installation of structural monitors.

Beginning Wednesday, August 21 through the morning of Saturday, August 24, one northbound right hand lane and shoulder between exit 9 and the Tappan Zee Bridge, as well as one northbound right hand lane on the Tappan Zee Bridge will be closed from 9 p.m. to 6 a.m. for the installation of structural monitors.

Additional geotechnical borings will be conducted on the river at various locations. Operations will run 24 hours a day, Monday through Friday.

TZC will continue dredging operations in the Hudson River as part of the New NY Bridge Project. Dredging will occur through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.

Dredging crews will work 24 hours a day, seven days a week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.

Ongoing operations:
· Test pile program
· Rockland bulkhead construction (including fence & gates) and Dock Extension at Rockland (under existing bridge)
· Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline

Rockland:
TZC will continue fencing and sidewalk work along River Road in South Nyack north of the existing bridge. This work is part of the bulkhead construction area and will be performed on weekdays between 7 a.m. and 3 p.m. At times, River Road will be limited to one lane with flag persons in place to ensure the safe flow of traffic.

DREDGING OPERATIONS AND TEST PILE PROGRAM IMPACT PILE DRIVING CONTINUE

For immediate release: August 9, 2013

update

Tappan Zee Constructors, LLC (TZC) will continue 24-hour-a day dredging operations in the Hudson River as part of the New NY Bridge Project.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.

Dredging will occur over a three-month period from August 1 through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.

Dredging crews will work 24-hours-a-day, seven-days-a-week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.

Impact pile driving will continue this week as part of the ongoing test pile program and will continue through October 31 at various locations for future pile foundations. This work will be performed from 7 a.m. to 7 p.m. on weekdays and, at times, on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

Ongoing operations:
· Test pile program
· Geotechnical land borings
· Rockland bulkhead construction (including fence & gates) and Dock Extension at Rockland (under existing bridge)
· Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Rockland and Westchester environmental monitor installations
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline

Westchester:
Ongoing geotechnical boring activities will continue to support the developing design for the New NY Bridge Project.

Rockland:
TZC will continue fencing and sidewalk work along River Road in South Nyack north of the existing bridge. This work is part of the bulkhead construction area and will be performed between 7 a.m. and 3 p.m. Monday through Friday. River Road will be limited at times to one lane with flag persons in place to control traffic safely.

Pile Driving Set To Begin This Week

The New Tappan Zee Bridge

For immediate release: July 26, 2013

TEST PILE PROGRAM IMPACT PILE DRIVING SET TO BEGIN,
ROCKLAND THRUWAY DOCK CONSTRUCTION GETTING UNDERWAY

Tappan Zee Constructors, LLC (TZC) is scheduled to begin impact pile driving as part of the ongoing test pile operation this week. The test pile installation will continue over the next two to three months at the proposed locations of the foundations for the New NY Bridge. The test pile program will verify subsurface conditions in the river and the structural capacity of the pilings.

Under the Final Environmental Impact Statement, the hours of impact pile driving are restricted to 7 a.m. to 7 p.m., Monday through Friday and 12:00 noon to 7 p.m. on Saturday. There is no impact pile driving allowed at night or on Sundays. Noise monitors are in place along the Rockland and Westchester shorelines and the data is available at www.NewNYBridge.com.

Construction of the New York State Thruway’s temporary dock at the Rockland Maintenance facility on River Road in South Nyack will begin the week of July 29. TZC will reconstruct a maintenance dock that was damaged during Superstorm Sandy. This new dock will allow the Thruway to continue its normal maintenance work on the existing Tappan Zee as the construction activities for the New NY Bridge get underway.

Orange and Rockland Utilities will install new utility poles near River Road in South Nyack to support utility relocations which are needed for the New NY Bridge project. These operations may require temporary lane closures and will be performed by the utility.

Ongoing operations:
· Test pile program
· Rockland bulkhead construction
· Temporary Westchester trestle construction including pile driving on weekdays from
7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Rockland and Westchester environmental monitor installations
· Geotechnical land borings
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline

Westchester:
Survey crews will be conducting surveys in the toll plaza area in Tarrytown on Wednesday, July 31 requiring temporary closures of toll lanes conducted one at a time.

Rockland:
Geotechnical boring operations to investigate subsurface soil conditions will be conducted in the northbound lanes of I-87/I-287 and will require a temporary lane closure between the existing bridge to Interchange 10 in South Nyack from 10 a.m. to 3 p.m. on Monday, July 29 through Wednesday, July 31. Southbound lane closures will be required from Interchange 10 to the existing bridge between 10 a.m. and 3 p.m. on Thursday, August 1 and from 10 a.m. to 2 p.m. Friday, August 2.

VOTING SHOWS MAJORITY FAVOR NOISE BARRIERS FOR THE NEW NY BRIDGE

update

Project Update

For immediate release: July 19, 2013

Last month, the New York State Thruway Authority, the New York State Department of Transportation (NYSDOT), and the Federal Highway Administration (FHWA) invited local residents tovote on the placement of proposed noise barriers for the New NY Bridge Project.

“The public has spoken and they overwhelmingly support the construction of sound reducing traffic noise barriers as part of the New NY Bridge Project,” said Brian Conybeare, Governor Cuomo’s Special Adviser for the New NY Bridge Project. “This is another way we trying to make this the most inclusive and transparent infrastructure project in the history of the state. We will continue to include input from local residents and other stakeholders as the project moves forward.”

Noise barriers are recommended as a form of traffic noise abatement only if they are determined to be both feasible and reasonable. According to Thruway and NYSDOT noise policies, as well as FHWA noise regulations, once a noise barrier is deemed both feasible and reasonable, ‘benefited receptors’, defined as property owners and/or residents of properties that would receive at least a five decibel reduction in noise level as a result of the proposed noise barriers, have an opportunity to cast a vote either for or against its construction.

Public meetings were held in both Westchester and Rockland counties during the week of June 23. At the meetings, Tappan Zee Constructors, LLC explained the locations and heights of the proposed walls for the areas that met the noise mitigation requirements, along with any possible aesthetic preferences.

The voting results show the benefitted receptors overwhelmingly favor having noise barriers constructed as part of the New NY Bridge project. Overall, 306 ballots were sent to benefited receptors. The tabulated results from the vote appear below:

Barrier

Votes For

Votes Against

Results

Westchester East Sound Barrier

87

1

98% FOR BARRIER

Westchester West Sound Barrier

2

0

100% FOR BARRIER

Rockland North Sound Barrier

96

5

95% FOR BARRIER

Rockland South Sound Barrier

31

2

94% FOR BARRIER

ONGOING PRECONSTRUCTION ACTIVITIES CONTINUE ON THE NEW NY BRIDGE PROJECT

The new NY bridge

For immediate release: July 5, 2013

ONGOING PRECONSTRUCTION ACTIVITIES CONTINUE ON THE NEW NY BRIDGE PROJECT

Tappan Zee Constructors, LLC (TZC, LLC) will continue preconstruction activities the week of July 8 in Westchester and Rockland Counties.

Ongoing operations:

– Cleaning and preparation for future construction of the Thruway’s Rockland Bulkhead
– Construction of the temporary Westchester work trestle which includes pile driving operations that will occur between 7 a.m. and 7 p.m.
– Survey inspections on existing bridge
– Rockland environmental monitor installations continue
– Geotechnical land borings
– Mobilization at the Exit 10 staging area
– Support for river-based work from the Rockland shoreline

Lane closures will be in place on the right lane of northbound I-87/I-287 on Monday, Tuesday and Friday from 10 a.m. to 3 p.m. for installation of instrumentation to monitor the existing bridge during construction. Lane closures will also be in place on the southbound right lane of I-87/I-287 Wednesday and Thursday from 10 a.m. to 3 p.m. for the same activity.

Neighboring community takes sound-proofing offer; 2 more complexes consider funds to mitigate noise

Lohud;  June 25, 2013  Written by Theresa Juva-Brown

Neighbors want more than noise reducing windows

http://www.lohud.com/videonetwork/2507049237001/TZB-neighbors-offered-noise-protections

Nearly a week after Tappan Zee Constructors offered to spend $4.2 million on noise-reducing windows and doors for some bridge neighbors, only one community has officially accepted the proposal.

Bradford Mews has agreed to Tappan Zee Constructor’s offer to shell out $1 million for special doors and windows in the South Nyack rental community, project officials confirmed.

Meanwhile, Salisbury Point in South Nyack and The Quay in Tarrytown continue to mull the offer; leaders from both groups met separately with the project team on Tuesday. The money being offered is part of a $20 million fund split between the state and Tappan Zee Constructors to pay for community improvements during construction of the new Tappan Zee Bridge.

When Tappan Zee Constructors announced the $4.2 million deal last week, leaders of Salisbury Point and The Quay slammed it for not addressing all their concerns. At The Quay, an 89-unit condominium complex, residents had asked for a pool enclosure and new fencing, in addition to the window and doors.

“It looks like it’s not going to happen and that’s very frustrating and depressing for us all,” said Alice Goldberg, president of the board.

Tuesday’s meeting with project officials focused on the types of windows Tappan Zee Constructors would pay for, she said. Goldberg said she is confident residents will reach an agreement with the builders.

The Quay’s proposal calls for windows with varying degrees of sound proofing based on the condo’s distance from the bridge construction.

Tappan Zee Constructors also denied Salisbury Point’s requests for security fencing and a pool cover. Thruway Authority spokesman Daniel Weiller criticized residents for expecting a pool dome.

“Some of the groups are asking for the project to pay for extras that have nothing to do with noise, such as a swimming pool dome, and it would be irresponsible to use the budget for the new bridge to pay for things like that,” he said in an email. “The goal is to find a fair and reasonable solution to help them install quality noise-reducing windows and doors, not to write a blank check.”

Goldberg disputed Weiller’s claim, arguing that “we have been cautious and very conservative” with the requests, adding that a cover for the pool would protect it from construction pollution.

The Quay’s residents, along with other Tarrytown and Rockland residents, are also considering designs for permanent noise barriers on the new span and around it. Officials have scheduled public meetings this week to explain options to Westchester and Rockland residents who received ballots in the mail.

Meetings will be held at 7 p.m. Wednesday at 303 S. Broadway in Tarrytown and 7 p.m. Thursday at the Best Western in Nyack.

http://www.lohud.com/article/20130625/NEWS/306250099?gcheck=1

 

Tappan Zee Constructor’s Designing The New Tappan Zee Bridge

Lohud; June 18, 2013 By Theresa Juva-Brown and Khurram Saeed

bilde

TARRYTOWN — With technical diagrams covering the walls and rows of workers hunched over laptops at portable tables, it’s a world of deadlines and engineering calculations at the headquarters of Tappan Zee Constructors on White Plains Road.

Despite long days, there’s a quiet excitement to the hard effort of designing and building the new Tappan Zee Bridge.

“You can feel the buzz in this office when you come in here, I don’t care what time of day — it’s buzzing,” TZC president Darrell Waters said on Friday during an exclusive sit-down with The Journal News, joined by Walter Reichert, TZC’s vice president. Waters and Reichert are employees of Fluor Corp. and Granite Construction, two of the four companies that make up TZC.

From the project’s $3.9 billion price tag to the pair of 400-foot cranes set to arrive by barge this week, virtually every aspect of the bridge replacement is on a grand scale, including Waters’ attitude about such a challenge.

“I’m a big job guy,” Waters said. “They don’t get any bigger than a big job in New York — it’s like playing baseball.”

The pair of veteran civil engineers also worked on the new World Trade Center, making the Tappan Zee project their second high-profile job in recent years. And it’s not a typical bridge project.

“This one’s from scratch,” Reichert said. “All the way up, it’s brand new. You don’t get very many opportunities in the New York area to do that.”

The colossal undertaking keeps TZC’s top bridge designers and engineers busy 12 to 13 hours a day. The team is so enthusiastic, Waters and Reichert have to remind them that it’s a marathon task, not a sprint.

“It’s five years’ worth of work, so you have got to be careful,” Waters said. “Even though you might want to work 16, 18 hours a day, if you do that, you can’t make it. We have to watch each other’s back.”

“We can’t afford to have everyone burn out,” Reichert added.

How the span will emerge

Construction will be kicked into high gear by next year, with 20 cranes, 60 barges, and two floating concrete batch plants in the river, not to mention the giant Left Coast Lifter, one of the largest floating cranes in the world.

Crews will work in the middle of the river, as well as along both shores. Piles will be driven into the river and the bridge foundations will be placed on top. Columns will then begin to rise from the foundations. Bridge decks will then be placed on the columns.

If all goes according to plan, by late next year residents might even be able to see some parts of the bridge’s towers, which will reach more than 400 feet in height.

To speed construction, some components, such as structural steel, will be assembled at several staging areas along the river.

“If it was a normal bridge you would build everything on site,” Reichert said. “A couple of miles away from here we can pre-fab sections of it. That type of thing helps you cut the time.”

Meanwhile, Hudson Harbor, a townhouse complex in Tarrytown, will be used as a place to load workers onto boats that will take them to the barges, TZC leaders said.

A journey to the river bottom

Because of the unique composition of the ground beneath the Hudson River, the biggest challenge for TZC is designing the bridge’s foundations. Ideally, TZC would lodge all of the pilings deep into bedrock, but only half the bridge, mostly near the Westchester shore, sits on solid rock. Bedrock is about 750 feet down near Rockland and virtually unreachable for bridge builders.

As a result, TZC will rely on friction created by the piles and the surrounding sand and soil to hold up the new spans. Those piles will have to be about 350 feet in length – each longer than a football field – in order produce sufficient friction, Reichert said.

“When you have 300 feet of material above it, even though it may not be all that cohesive or dense, it’s still a lot of pressure on it,” Reichert said.

Starting next month, TZC will install test piles along the bridge’s footprint to determine the length of the piles needed during construction. Recently completed soil testing also provided valuable data about the composition of the soil below.

“So far we don’t see anything different than what we expected,” Waters said. “There’s minor differences but nothing that bothers us yet. The proof of that comes with the test pile program.”

 

http://m.lohud.com/localheadlines/article?a=2013306170090&f=1166

 

Tappan Zee Bridge: Feds, state assure South Nyack of toll removal

Lohud June 15, 2013; author Khurram Saeed

Federal and state authorities have assured South Nyack officials in writing that temporary equipment that will be used to collect Tappan Zee Bridge tolls electronically in South Nyack will be removed when the new crossing is completed.

The Federal Highway Administration approved a change that updates the language in the $4 billion project’s final environmental review and its official record of decision confirming the toll facility will leave its interim home at Exit 10 on the Thruway in five years or so.

The state Thruway Authority on Thursday also made its position clear in a letter to South Nyack Mayor Bonnie Christian.

“Upon completion of the new bridge with its permanent toll facilities in Tarrytown, the temporary gantry with toll equipment will be removed from Interchange 10,” project director Peter Sanderson wrote.

South Nyack officials had been demanding the guarantees because they wish to commercially redevelop the Exit 10 interchange.

Project officials have said the toll gantry is expected to be erected next year and tested for six months before being used.

An environmental monitor was installed recently at Interchange 10 so the public can keep track of noise, dust and vibration levels.

Project officials also confirmed, as first reported in The Journal News last week, that Tappan Zee Constructors will install the monitors at Bradford Mews Apartments on Piermont Avenue and Ferris Lane, a residential street in Grand View. In Rockland, there are already monitors at Salisbury Point Cooperative in South Nyack; on River Road, south of Grand View Village Hall; and near the Thruway’s Interchange 12 in West Nyack.

Preparation for the start of full-blown construction of the new parallel spans is continuing. During the next two weeks, two large barge-mounted cranes that will be used to place permanent piles for the bridge will arrive in the area. Crews will assemble and moor each crane until the test pile work begins in the middle of next month. The cranes will be stationed on the north side of the bridge closer to the Rockland side of the Hudson River. Despite the imposing size, neither of these cranes are as large as the Left Coast Lifter, which is set to arrive at the end of this year.

Project officials said work also will begin next week on the Thruway Authority’s bulkhead area along River Road in South Nyack. Work includes clearing the site and construction of a larger bulkhead that will be used for equipment staging.

Tappan Zee Bridge Update: Two more monitors planned in Rockland

LoHud Jun 8, 2013 Written By Khurram Saeed

http://www.lohud.com/article/20130607/NEWS03/306070051/Tappan-Zee-Bridge–2-more-monitors-planned-in-Rockland?source=nletter-news

The New Tappan Zee Bridge

A South Nyack apartment complex and a residential street in Grand View may soon be home to devices to monitor noise, dust and vibrations during construction of the new Tappan Zee Bridge.

Tappan Zee Constructors is working on finalizing details to install environmental monitors at Bradford Mews Apartments on Piermont Avenue and Ferris Lane, a project official told The Journal News on Friday afternoon.

South Nyack Mayor Bonnie Christian on said Friday morning that the monitors would be installed this weekend, but that’s not the case, the official said.

However, a monitor was recently installed at Interchange 10 of the Thruway in South Nyack, and another is set to go up next week on River Road, just south of Grand View Village Hall near Orangetown’s sewage pumping station.

That would bring to four the total number of monitors in Rockland, with two more on the horizon.

Devices were installed a few weeks ago at South Nyack’s Salisbury Point Cooperative, across from Bradford Mews, and near the Thruway’s Interchange 12 in West Nyack.

South Nyack has been working with the bridge’s design-builder to find suitable locations since TZC proposed putting up the shoebox-sized devices in front of Village Hall and Elizabeth Place Park, both in the village.

“We had them go around again and give a look,” Christian said. “They came up with these two alternatives (Bradford Mews and Ferris Lane). There may be other sites to come.”

Christian said discussions will continue with TZC about other appropriate locations so residents can keep an eye on potential quality of life disturbances during the five-year construction of the twin-span crossing.

Four environmental monitors in Tarrytown are already in place.

Data from all of the devices can be viewed at http://newnybridgegall- ery.com/noise/.

Pre-Construction Activities Continue on the New NY Bridge Project

The new NY bridge

For Immediate Release: May 31, 2013

Pre-Construction Activities Continue on the New NY Bridge Project

No new pre-construction activities are slated for the week of June 3, 2013. Environmental monitors continue to be installed in Rockland County as the New York State Thruway Authority (NYSTA) and Tappan Zee Constructors, LLC finalize specific installation locations. The monitors continually record noise, vibration and air quality for the duration of the project. All readings can be viewed at www.NewNYbridge.com.

Test boring operations in the Hudson River continue as does work on the temporary Westchester trestle. The trestle is a work platform that will support a crane for the construction of the new bridge. The 1,000-foot long platform reduces the amount of dredging required and allows crews to work from the water and not from the Westchester shoreline. Work on the Westchester trestle will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to the hours between 7 a.m. and 7 p.m. Monday through Friday.

Westchester:
Surveying, utility exploration and test boring work continues for the New NY Bridge Project during the week of June 3, 2013. The work being performed in the shoulder area will require a temporary right lane closure on northbound I-87/I-287 between Exit 9 and the toll plaza on Wednesday and Thursday from 10 a.m. to 3 p.m. There will also be a temporary right lane closure on southbound I-87/I-287 between the toll plaza and Exit 9 from 10 a.m. to 3 p.m. on Friday.

Rockland:
Mobilization work continues at Exit 10 where Tappan Zee Constructors, LLC will store materials for construction, trailers for work operations and equipment as well as use the staging area for employee parking.

Marine support from the Rockland shoreline will continue the week of June 3, 2013.

 

No Work Scheduled for Memorial Day Weekend

 

update

For immediate release: May 24, 2013

No Work Scheduled for Memorial Day Weekend

In observance of Memorial Day Weekend, Tappan Zee Constructors, LLC will not work on May 25, 26 or 27, 2013. The New York Thruway Authority and TZC, LLC would like to extend gratitude to the men and women of the United States Armed Forces who have sacrificed greatly to protect the freedom of this nation. When work resumes on Tuesday May 28, 2013, environmental monitors will continue to be installed in Rockland County. The first monitor readings from Rockland and Westchester are available online. The will monitors continually record noise, vibration and air quality for the duration of the project. All readings can be viewed at www.NewNYbridge.com.

Test Boring operations in the Hudson River will continue as will work on the temporary Westchester trestle. The trestle is a work platform that will support a crane for the construction of the new bridge. The 1,000-foot long platform reduces the amount of dredging required and allows crews to work from the water and not from the Westchester shoreline. Work on the Westchester trestle will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to the hours between 7 a.m. and 7 p.m. Tuesday through Friday.

Westchester:
Surveying work and soil sampling for the New NY Bridge Project will continue during the week of May 28. The work being performed in the shoulder area will require a temporary right lane closure on southbound I-87/I-287 between the toll plaza and Exit 9. The lane closure will be in place from 10 a.m. to 3 p.m. Tuesday to Thursday and 10 a.m. to 2 p.m. on Friday.

Rockland:
Limited test-boring operations will continue on Thurway land under the existing bridge and just to the north at the proposed bridge locations. The work is scheduled to be conducted between the hours of 7 a.m. and 5 p.m. Tuesday through Friday.

Surveying work and soil sampling performed in the shoulder area will require a lane closure in the right lane of southbound I-87/I-287 between the Rt. 9W Bridge and the current Tappan Zee Bridge structure. The lane closure will be in place from 10 a.m. to 3 p.m. Tuesday to Thursday and 10 a.m. to 2 p.m. on Friday.

ROCKLAND ENVIRONMENTAL MONITORS TO BE INSTALLED

update

For immediate release: May 17, 2013 


Installation of the Rockland environmental monitors is scheduled to begin the week of May 20. These construction monitoring devices, which monitor vibration, noise, and air quality, will be in place for the duration of the New NY Bridge project.

Work on the Westchester trestle continues this week and will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to the hours between 7 am and 7 pm Monday through Friday. The trestle is a work platform that will support a crane for the construction of the easternmost 1,000 feet of the new bridge. The 1,000-foot long platform helps reduce the amount of dredging required and allows the crews to work from the water and not from the Westchester shoreline. Environmental monitoring is in place and can be viewed at www.newnybridge.com.

Surveying work and soil sampling for the New NY Bridge Project will continue during the week of May 20 as engineering crews conduct more design surveys at various locations in Rockland and Westchester in the vicinity of the project, including the Westchester access road location on New York State Thruway property in Tarrytown.

Preconstruction geotechnical investigations will continue as small barge-based drilling equipment will work at various locations throughout the project footprint in the Hudson River. The crews are conducting preconstruction geotechnical surveys to determine soil conditions where future piles will be installed for the new span. Noise levels from the equipment will be at a minimum. The river-based operations will run continuously 24 hours a day Monday through Friday and possibly Saturday.

Westchester:
Surveying work and soil sampling for the New NY Bridge Project will continue during the week of May 20.

Rockland:
Limited test-boring operations will continue on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on New York State Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 am and 5 pm Monday through Friday.

Soil sampling will be conducted in the area of New York State Thruway during daytime hours; this operation will not cause lane closures and should not affect traffic.

Tappan Zee Constructors, LLC. has no lane closures scheduled on River Road in South Nyack.

Tappan Zee Bridge spectator areas may be set up during work

LoHud ; By Theresa Juva-Brown and Khurram Saeed

May 4, 2013

bridge

The massive effort to build a new Tappan Zee Bridge will create a grand spectacle on the river that likely will draw crowds of curious onlookers.

While Tarrytown has plenty of public waterfront where official viewing areas can be set up, that’s not the case across the river. Because there are no public spaces along the South Nyack shore, residents there are concerned that people will wander onto their properties to watch the $3.9 billion project take shape.

Trespassing is already a problem at South Nyack’s Salisbury Point, co-op Vice President Judy Hirschhorn said. The 120-unit riverfront complex has a front-row view of the Tappan Zee that often attracts outside visitors who make themselves at home on the complex’s sprawling lawn. Some cyclists are also notorious for urinating in Salisbury Point’s bushes, she said.

Residents worry that when heavy construction starts on the new Tappan Zee, spectators from all over will flock to their parking lots to get a glimpse of the action.

“We think it’s going to be a huge problem,” she said.

Nyack Mayor Jen Laird-White said some people might go to Nyack’s Memorial Park to get unimpeded — but distant — views of the construction.

One resident has proposed getting the project team to help overhaul Memorial Park, including moving the parking lot to Nyack Municipal Marina and building a pedestrian bridge over the inlet to connect the two areas, she said.

Meanwhile, leaders in Tarrytown are already looking at the village’s waterfront for possible viewing stations, including Losee and Pierson parks and the River Walk.

David Aukland, Tarrytown’s liaison to the project, said he envisions an area where people could not only watch construction but also learn about the project.

“We know the public is interested, and we’d rather them have clear information than have them guess,” he said.

The area, which he said would likely be created by the Thruway Authority and Tappan Zee Constructors, could include binoculars and signs that explain the work. The signs could also feature tags people scan with their smartphones to get information about local wildlife and history, he said.

That would be similar to the approach taken by another huge public works project, the reconstruction of the San Francisco-Oakland Bay Bridge, which has a designated viewing area. The location offers information on the bridge’s history and great views of the self-anchored suspension portion of the new Bay Bridge East Span, said John Goodwin, spokesman for the Metropolitan Transportation Commission.

Brian Conybeare, Gov. Andrew Cuomo’s special adviser on the Tappan Zee Bridge project, said the project team is discussing possible viewing sites with officials on both sides of the river.

“The goal is to find safe, accessible, public areas where people can view the project and take pictures once construction gets going, but no final determination on locations has been made,” he said in an email.

In addition to asking the project team for security fencing and cameras, Salisbury officials plan to post more trespassing signs and work with South Nyack-Grand View police to keep an eye out for unwelcome visitors.

Hirschhorn said measures need to be in place soon. Dredging of the river bottom is set to start in August and will likely attract attention, she said.

“We can’t have people walking all over our property,” she said.

www.NewNYBridge.com

For immediate release: May 3, 2013

The new NY bridge

WESTCHESTER TEMPORARY TRESTLE CONSTRUCTION SCHEDULED TO BEGIN

Work is expected to begin during the week of May 6 on the Westchester trestle, which is the first of the temporary work trestles to be constructed as part of the New NY Bridge project.

The work will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to a maximum of 7:00am to 7:00pm Monday through Friday and is expected begin on Friday May 10. The trestle is a work platform that will support a crane for the construction of the easternmost 1000 feet of the new bridge. The 1000-foot long platform helps reduce the amount of dredging required and allows the crews to work from the water and not from the Westchester shoreline.

In addition, two mooring buoys will be installed in the Hudson River on the Rockland side of the channel. These will be utilized to secure work barges and will be on site for the duration of the project.

Surveying work and soil sampling for the New NY Bridge Project will continue during the week of May 6 as engineering crews conduct more design surveys at various locations in Rockland and Westchester in the vicinity of the project, including the Westchester haul road location on New York State Thruway property in Tarrytown.

Preconstruction geotechnical investigations will continue as small barge-based drilling equipment will work at various locations throughout the project footprint in the Hudson River. The crews are conducting preconstruction geotechnical surveys to determine soil conditions where future piles will be installed for the new span. Noise levels from the equipment will be at a minimum. The river-based operations will run continuously 24 hours a day Monday through Friday and possibly Saturday.

Westchester:
Limited test-boring operations will continue on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 am and 5 pm Monday through Friday.

Rockland:
At times traffic on River Road near the South Nyack-Grand View border will be restricted to one lane during weekday daytime hours for utility investigations. Signs and flag persons will be in place to help keep traffic flowing safely.

Limited test-boring operations may start on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 am and 5 pm Monday through Friday.

 

 

https://tappanzeebridge.randcommercial.com/922/

Are you a business looking to secure work related to the New NY Bridge project?

New City Patch; April 23, 201

By Krista Madsen

http://newcity.patch.com/articles/tappan-zee-bridge-business-to-business-forums-f6ab42a7?ncid=newsltuspatc00000001

The New York State Thruway Authority, Tappan Zee Constructors, New York State Department of Labor and the New NY Works Program will provide information for businesses wanting to learn about contract opportunities related to the new Tappan Zee Bridge project 10 a.m. Wednesday at the Crowne Plaza in Suffern.

Representatives of Tappan Zee Constructors, the NYS Dept. of Labor and Brian Coneybeare, special advisor to Gov. Andrew Cuomo on the project, will be among those making presentations.

To register for this event, visit:
http://www.labor.ny.gov/careerservices/new-ny-bridge.shtm

There will also be an event 2:30 p.m. today (April 23, 2013) at the Westchester Marriott in Tarrytown.

Watch The New NY Bridge Animation

Tappan Zee Constructors recommended to build new Tappan Zee Bridge

Tappan Zee Bridge Presentation: The state Thruway Authority on Dec. 5, 2012 released three designs to build a new Tappan Zee Bridge. The $3.1 billion bid from Tappan Zee Constructors has apparently won the state’s recommendation. Video by WGRZ/wgrz.com

Tappan Zee Constructors has won the state’s advisory committee recommendation to build the new Tappan Zee Bridge for $3.1 billion, a source close to the selection process told The Journal News on Wednesday.

The consortium, which includes the company that built the existing 3-mile Tappan Zee 57 years ago, offered the least expensive bridge plan among the three teams competing for one of the largest public works projects in the country.

The suggested design for the Tappan Zee replacement, a cable-stayed bridge, has oddly angled towers on each span, a feature so unique it’s never been used in the United States, a state official said. He added that he knows of only one bridge — in Russia — with a similar element.

The twin-span bridge would also include a concrete deck on top of steel girders. Like the other two options, it would be strong enough to carry trains in the future. In addition, it would have deck connections in four places that can be used to turn traffic around in emergencies.

The crossing would have 35 piers in the river and be made up of 350-foot long spans to create the road deck. Those spans would be six times longer than the current ones. The proposal also calls for less dredging during construction than the state initially said would be required.

The Thruway Authority on Wednesday released the three proposals for the new bridge, but did not identify each team’s proposal, citing federal rules.

“To get a bridge to this point in a year was really a fantastic accomplishment,” Gov. Andrew Cuomo said at a presentation at the Capitol.

Officials also announced that the state’s 38-member review panel had chosen the $3.1 billion bid because “they determined it was the best value,” said Brian Conybeare, a special adviser on the project.

The three proposals pegged the replacement cost between $3.1 billion and $4 billion, all much less than the initial construction price tag of $5.2 billion. Still, the proposal prices are preliminary estimates and don’t include another $600 to $800 million for expenses such as financing and management, state officials said.

American Bridge Co., which built the Tappan Zee, and Fluor Enterprises are members of the recommended Tappan Zee Constructors team. Those two firms are also involved in the $6.4 billion reconstruction of the San Francisco–Oakland Bay Bridge. A joint venture involving Kiewit Infrastructure and Skanska USA and a partnership of Bechtel Infrastructure and Tutor Perini also submitted proposals.

The construction time for each proposal was more than five years. Work is expected to begin next year.

Though the state’s panel has selected Tappan Zee Constructors, the Thruway Authority board makes the final decision. The board is set to vote for a winning team on Dec. 17. Until then, officials said the public can weigh in on the proposals on the bridge project’s website: http://www.newnybridge.com.

The design review team’s recommendations will be a major factor in the final decision, said Thomas Madison, the Thruway Authority’s executive director.

The contract award will have a ripple effect for homeowners in Rockland and Westchester.

A group of six neighbors in South Nyack are waiting to learn if they’ll remain in their homes during construction or they’ll be bought out, as most of them want. The state originally planned to take the homes but reversed that decision in May. The homeowners have asked the state to reconsider.

Homeowners said state officials have told them the contract award would allow the state to finally make a decision.

“It would be good to finally come to some kind of closure because everything has been up in the air for the longest time,” said John Cameron, who has lived in his South Broadway home with his wife, Hope Elliott Cameron, for the past six years.

A state official told Cameron and his neighbors they have reason to be “optimistic,” which he believes means the state will ask the winning bidder to buy the homes, he said.

Not everyone was satisfied with Wednesday’s developments, though.

Veronica Vanterpool, executive director of Tri-State Transportation Campaign, charged that the state’s preview of the proposals was incomplete. Her group has pushed for the plan to include mass transit along the Interstate 287 corridor.

“The proposals are still unclear about what mass transit ready means,” Vanterpool said in an email to The Journal News. “We look forward to an announcement of the TZB transit task force so these details can be hammered out. The proposals came in significantly below the projected $5.2 billion price tag, creating a greater opportunity to incorporate low-cost, bus rapid transit improvements into the project.”

Riverkeeper, the Hudson River’s leading advocacy group, was also not eager to endorse any of the proposals. Riverkeeper has criticized the state’s plan for not adequately addressing how the project could harm marine life.

“Riverkeeper is not surprised that the state has identified a reduced dredging option,” president Paul Gallay said. “We and the rest of the public need more information as to how this will affect the project’s overall environmental impacts, and we will seek to have those discussions with the state as soon as possible.”

Al Samuels, president of the Rockland Bussiness Association, said he agreed with the selection committee’s recommendation, which he said “makes the most sense.”

Plans for the new bridge have moved swiftly since last year, when the Obama Administration named it one of 14 top priority infrastructure projects across the country. In September, the Federal Highway Administration gave final approval to the project’s environmental study, allowing the replacement plan to proceed

It remains unclear, however, whether the federal government will give the state a low-interest loan. In its loan application, the state had said a new bridge could cost up to $5.9 billion. Without a significant loan, state officials warned of soaring tolls. Officials had said the current $5 cash toll could rise to $14.

Rockland Legislature Chairwoman Harriet Cornell said Wednesday she wants to know what a smaller price tag means for those toll increases.

“I’ve talked for years about not putting the tolls on the backs of commuters,” Cornell said.

 

New Tappan Zee Bridge Project Update : Video

New Tappan Zee Bridge Project – Project Meeting July 25, 2012

Here is the video:

The New Tappan Zee Project :Video

Executive Director Thomas J Madison on the LoHud Editorial Spotlight discusses the new Tappan Zee Bridge and its impact on the Hudson Valley:

 

Some property information provided by CoStar, Loopnet, HGAR, Yelp, Rand Commercial Services and other public sources.