|
The New NY Bridge Newsletter for January 2017
September 2016 New NY Bridge Monthly Newsletter
|
Project Update: STAY CABLE INSTALLATION CONTINUES
For immediate release: August 4, 2016 STAY CABLE INSTALLATION CONTINUES Tappan Zee Constructors, LLC (TZC) continues to install the new northbound bridges stay cable system. The stay cables are comprised of numerous metal strands, tightly packed in a protective sheath. After the initial installation process, TZC will install additional strands inside the sheath to provide further strength. TZC will install new structural steel sections and stay cables on alternating sides of the towers as work continues. Precast concrete deck panels will also be placed in the erected steel sections to provide a base driving surface. Maintenance Dock Construction Noise Barrier Construction TZC also will continue constructing foundation walls for the future highway and shared-use path along the northbound Thruway in South Nyack. The operation is scheduled to continue in the coming months. Additional work includes:
Boater Safety The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. The U.S. Coast Guard also has established a safety zone encompassing all navigable waters within a 200-yard radius of the largest machine on the project, the I Lift NY super crane, legally registered with the U.S. Coast Guard as the Left Coast Lifter. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. The Eastern RNA will be extremely active and vessels transitioning to and from the eastern shoreline at Tarrytown should approach and depart to the north. The Western RNA will be impassable at times and mariners should stay clear of the area. Boaters are strongly urged to use the center 600 feet of the main channel (when available) to navigate in a north-south direction with no wake at a maximum speed of five knots. Boaters should expect periodic partial closures of the main channel due to construction activities. Tune to Marine Radio Channel 22A for the latest U.S. Coast Guard advisories. Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Mariners are advised to stay clear of all overhead work and maintain a safe distance of 1,000 feet from all construction equipment and support vessels. In addition, all bridge piers and abutments are protected by a 25-yard security zone. Additional temporary navigational lights have been installed on the existing bridge to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard permit requirements, as are all moorings, barges and other equipment. All mariners should consult the latest USCG Local Notice to Mariners before transiting this area. More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site map can be found at NewNYBridge.com/Boater. The page includes an interactive GPS map showing vessel locations on the Hudson River, detailing which vessels are stopped and which are in motion to a new location, for recreational and commercial boaters to get current information on the very active construction zone. The vessel tracking map is for informational purposes and not intended for navigation. All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions. ###
|
New NY Bridge Project August 2016 Newsletter
The outline of the new twin-span crossing is emerging this summer as the project continues to make remarkable progress on the Hudson River. The Rockland and Westchester approaches continue to grow with rows of steel girders and hundreds of precast road deck panels. At the main span towers, crews are also installing sections of steel and roadway, and preparing the area for the new stay cable system.
|
The New York State Thruway Authority announced that Tappan Zee Constructors, LLC has completed installation of the first stay cables on the New NY Bridge project. The stay cables, along with the 419-foot towers, will be the most prominent features of the new 3.1-mile structure. The first two stay cables were installed by TZC on the new northbound bridge’s main span on Thursday, July 21, 2016.
|
|
In just half a year, Tappan Zee Constructors, LLC has transformed the New NY Bridge project site by connecting piers, installing road deck panels and doubling the height of the new main span towers. The iconic structures now rise above the existing Tappan Zee Bridge, with TZC preparing to install the first of nearly 200 stay cables.
|
|
With summer in full swing, the New NY Bridge project is making its most visible advancements to date. Those keen on observing the progress firsthand have a “front row seat” to the action, through the project’s viewing platforms and outreach centers in Tarrytown and Nyack.
|
|
|
New NY Bridge Monthly Newsletter July 2016
Tappan Zee Constructors (TZC) has begun building the roadway for the new bridge’s main span.
In June, TZC installed four large pre-assembled sections of steel, weighing nearly 340,000 pounds each, atop the main span crossbeams. These steel segments will allow the team to build out from the towers one section at a time, attaching stay cables to the structure along the way. Precast concrete deck panels will be placed in the erected steel sections to provide a base driving surface.
|
The New NY Bridge project has made extraordinary progress over the past year, with more than a mile of steel girders in place and new towers rising above the existing Tappan Zee Bridge. You can see the transformation for yourself in this narrated video.
|
Governor Andrew M. Cuomo announced that “Alternative F” was selected as the design for the New NY Bridge project’s shared-use path connections in Westchester and Rockland. The decision followed a thorough review of the alternative’s impacts and benefits to the local communities.
|
|
This Independence Day weekend, the U.S. Coast Guard, the New York State Thruway Authority, Tappan Zee Constructors, LLC (TZC) and local law enforcement are reminding boaters of the safety measures near the extremely active work site.
|
|
TARRYTOWN TOLL PLAZA DEMOLITION CONTINUES
For immediate release: May 5, 2016
TARRYTOWN TOLL PLAZA DEMOLITION CONTINUES
Cashless Tolling System Now In Effect
Demolition of the deactivated toll plaza in Tarrytown continues as Tappan Zee Constructors, LLC (TZC) removes the toll plaza structures on the four right-most lanes of the southbound New York State Thruway (I-87/I-287) in preparation for the next shift in traffic, which is scheduled to occur in late May.
Survey work in the area will necessitate a midday lane closure, detailed in the chart below.
Lane Closures Near the Tappan Zee Bridge
DATE: | CLOSURES BEGIN: | CLOSURES END: | LOCATION: |
Tue., 5/10 | 10 a.m. One right lane | 3 p.m. | Southbound Thruway near the former toll plaza |
Noise Barrier Construction
TZC will continue constructing noise barriers along the Thruway in South Nyack next week. The work includes constructing noise barrier foundations and excavating soil along the southbound Thruway between the South Broadway bridge and River Road. After the foundations are established, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.
TZC also will continue constructing foundation walls for the future highway and shared-use path along the northbound Thruway in South Nyack. The operation is scheduled to continue in the coming months.
Additional work includes:
- Main span tower construction
- Support for river-based work from the Rockland trestle
- Rockland landing retaining walls
- Survey inspections on the existing bridge
- Westchester landings utility work
- Girder assembly placement
- Bridge road deck installation
- Drainage structure installations
Boater Safety
Marine units are continuing patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.
Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. TZC will also be working in the area left and right of the main navigation channel under the main span of the bridge. TZC will begin working in the main navigation channel, which will result in partial or total closure of same. Additional temporary navigational lights have been installed on the existing bridge to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard permit requirements, as are all moorings, barges and other equipment. All Mariners should consult the latest USCG Local Notice to Mariners before transiting this area.
More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, construction site maps, can be found here at NewNYBridge.com. The page includes an interactive GPS map showing vessel locations on the Hudson River, detailing which vessels are stopped and which are in motion to a new location for recreational and commercial boaters to get current information on the very active construction zone. The vessel tracking map is for informational purposes and not intended for navigation.
All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.
May 2016 New NY Bridge Project Monthly Newsletter
The pair of peregrine falcons that live in a man-made nest box on the existing Tappan Zee Bridge became proud parents once again with the hatching of a nestling on April 10.
The New NY Bridge project team is inviting members of the public to help name the new falcon chick. A week-long naming contest is now underway on the project’s Falcon Cam webpage. Rockland and Westchester students came up with the names. |
On Sunday April 24, travelers on the Tappan Zee Bridge said goodbye to the lines at the Tarrytown toll plaza thanks to cashless tolling. The state-of-the-art technology created a new traffic pattern in the area, eliminating the need for toll booths and speeding commutes across the river.
|
|
Rows of towering piers stand in procession across the Hudson River as the New NY Bridge project steadily moves ahead.
|
|
Years of hard work and careful planning on the New NY Bridge project are paying off as Tappan Zee Constructors recorded several construction milestones.
|
|
Workers on the New NY Bridge project are making swift progress installing steel girders thanks, in part, to recent good weather.
|
|
|
Tappan Zee Bridge Project Update
For immediate release: Dec. 3, 2015
INSTALLATION OF CONCRETE ROAD DECK CONTINUES
Overnight Closure of Southbound Exit 10 On-Ramp on Monday, Dec. 7
Tappan Zee Constructors, LLC (TZC) will begin installing bridge road deck segments near the Rockland shoreline on Thursday, Dec. 10. Project cranes will lift the prefabricated deck panels into place atop previously-installed structural steel girders.
Safely accomplishing the work will require reducing River Road/Piermont Avenue to one lane during weekdays starting on Thursday of next week. Flag persons will keep traffic moving by alternating the directional flow between north and south. TZC will also periodically hold traffic on River Road/Piermont Avenue for 6-minute intervals through Friday, Dec. 18 to enable the safe movement of deck panels and other materials.
Nearly 6,000 high-strength concrete deck panels will be installed for the new crossings approach spans. The panels are prefabricated at an off-site location and barged down river from the projects Port of Coeymans facility in Albany County. TZC will continue installing the approach span deck sections across the river over the coming year.
All-Electronic Toll Collection Gantry Work
Construction of the projects temporary all-electronic toll collection (AETC) system in Rockland will continue near the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to the southbound New York State Thruway (I-87/I-287). The work will necessitate closing the on-ramp during the overnight of Monday, Dec. 7. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the graphic below. This and other work require the specific lane and ramp closures detailed in the chart below.
Lane and Ramp Closures Near the Tappan Zee Bridge
Steel Girder Installation The remaining work over the Metro-North tracks will occur during a Friday overnight later this month, with the entire operation anticipated to conclude by the end of the year. Metro-North has adjusted its schedule slightly to allow the work to be completed. TZC will suspend construction activities when commuter trains pass through the area, resuming when given the all clear instruction by Metro-North. The I Lift NY super crane will continue placing larger girder assemblies across the river, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge. Tower Construction Installation of Noise Barriers in South Nyack Additional work includes:
Boater Safety The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times. More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, construction site maps, can be found here at NewNYBridge.com. The page includes an interactive GPS map showing vessel locations on the Hudson River, detailing which vessels are stopped and which are in motion to a new location for recreational and commercial boaters to get current information on the very active construction zone. The vessel tracking map is for informational purposes and not intended for navigation. Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment. All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions. ### |
TZ Bridge Project Update and Lane Closures for the Week of March 23, 2015
FLOATING BATCH PLANTS RETURN TO WORK ON THE NEW NY BRIDGE PROJECT
Triple-Lane Closure on Northbound New York State Thruway (I-87/I-287) During Overnight of Wednesday, Mar. 25
Tappan Zee Constructors, LLC’s (TZC) two floating concrete batch plants recently returned to the work site, passed the required testing and soon will begin pumping concrete. The batch plants were taken out of service in December after a silo failed.
The concrete plants move from location to location on the river, providing high-quality concrete where it is needed to build the New NY Bridge project. Their resumption of service will reduce the number of concrete trucks using local roads.
The following lane and exit closures are planned for next week:
Three left lanes of the northbound Thruway (I-87/I-287) will be closed from exit 9 (Tarrytown Sleepy Hollow NY Route 9) to exit 10 (Nyack South Nyack Route 9W), and including the Tappan Zee Bridge, from 9 p.m., Wednesday, Mar. 25 to 4:30 a.m., Thursday, Mar. 26. One lane will remain open during the closure. The closures are necessary to accommodate road-striping work.
Additionally, road striping will require the closure of the two left (35 mph) E-ZPass lanes at the southbound Thruway toll plaza in Tarrytown from 10 p.m. Friday, Mar. 27 to 5 a.m., Saturday, Mar. 28. The work also will necessitate the closure of the southbound exit 9 off-ramp to Route 9 from 10 p.m., Friday, Mar. 28 to 5 a.m., Saturday, Mar. 28. Traffic that would otherwise use exit 9 will be detoured to exit 8A, as shown below:
Turn-by-turn directions for southbound exit 9 closure detour:
- Exit onto the exit 8A off-ramp;
- At the end of the long ramp, turn right on westbound Route 119/White Plains Road;
- Enter westbound I-287, which merges with northbound I-87;
- Exit onto the exit 9 off-ramp;
- Turn left onto westbound Route 119/White Plains Road; and
- Turn left or right on Route 9, depending on your destination.
Preparations for the Temporary All Electronic Toll Collection system in South Nyack near exit 10 will require a single right-lane closure from 10 a.m. to 3 p.m. on Monday, March 23 and Tuesday, March 24.
Marine operations continue to gear up following the winter shutdown, with crews installing reinforcing steel (rebar) in the main span pile caps and the precast approach span pile caps.
With only a small percentage of piles left to install, pile driving operations will continue next week. The periodic pile driving is restricted to 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.
Crews also will continue working on the bridge’s landings at the Rockland and Westchester shorelines. The abutments, comprised of steel and concrete, will serve as strong bases where the new crossing meets the landside roadway.
TZC will continue limited concrete placement for foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and delivered by truck to the Rockland trestle located off the New York State Thruway’s (I-87/I-287) southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.
Additional work includes:
- Pile cap foundation construction
- Main span foundation construction
- Landing abutment concrete work
- River Road utility work
- Support for river-based work from the Rockland trestle
- Survey inspections on the existing bridge
Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.
More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.
Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.
All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.
New Year of Construction Looking Ahead to 2015
Holiday Travel this week on the TZ Bridge
For immediate release: December 19, 2014
ALL LANES OF NEW YORK STATE THRUWAY (I-87/I-287) WILL REMAIN OPEN FROM WEDNESDAY, DEC. 24 THROUGH SUNDAY, DEC. 28 TO EASE HOLIDAY TRAVEL
All lanes of the New York State Thruway (I-87/I-287) will remain open from Wednesday, Dec. 24 through Sunday, Dec. 28 to help New Yorkers reach their winter holiday destinations. The five-day, lane-closure-free period follows Governor Andrew M. Cuomo’s “Drivers First” initiative, which gives priority to motorists by ensuring that disruptions associated with highway and bridge projects are kept as minimal as possible.
While Tappan Zee Constructors, LLC (TZC) will continue working in several areas of the project during the week of Dec. 22, none of the planned activities will result in the closure of any traffic lanes. No construction work is scheduled for Christmas Day, Thursday, Dec. 25, though safety and security teams will remain on site.
20-Minute closures of the north- and southbound Thruway and other lane closures scheduled for overnight Friday, Dec. 19
The removal of an overhead sign gantry near exit 10 in South Nyack will require the closure of three lanes of the southbound New York State Thruway (I-87/I-287) during the overnight of Friday, Dec. 19. Two lanes will be closed at 9 p.m., followed by a third lane at 12 midnight. One lane will remain open, other than during the periodic complete closures detailed below. The three closed lanes will reopen at 7 a.m., Saturday, Dec. 20.
The operation also will require a series of 20-minute closures of all four lanes on both the north- and southbound Thruway between the hours of 11:59 p.m., Friday, December 19 and 6 a.m., Saturday, December 20. To ensure the safety of the public, the New York State Police will stop and hold all traffic approaching the gantry removal operation immediately before the closures go into effect. Motorists will be permitted to enter the Thruway from all ramps during the closures.
Travelers are advised that delays are likely on both directions of the Thruway during the overnight operation.
Continued Demolition of Westchester Landing of Existing Tappan Zee Bridge
Following the removal of sections of deck of the existing Tappan Zee Bridge to make way for the new bridge, the associated supporting piers are being demolished. The majority of this work, which will clear the path for the northbound bridge’s landing and first foundation pier, will be completed during daytime hours.
Pile Driving and Other Construction Activity
Construction will continue in the Hudson River as crews place the foundations of the new bridge. Work will include pile driving from 7 a.m. to 7 p.m., Monday through Wednesday and noon to 7 p.m., Saturday. No pile driving will occur on Christmas Day, Thursday, Dec. 25 or Friday Dec. 26.
A second shift of workers also will continue pile welding, pile cleanout and concrete placement operations associated with foundations.
Work is continuing on the new bridge’s landings on both sides of the river.
Additional work includes:
- Pile cap foundation construction
- Main span foundation construction
- River Road utility work
- Support for river-based work from the Rockland trestle
- Survey inspections on existing bridge
Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.
More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.
Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.
All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.
UPDATED: VIEWING PLATFORMS TAKE SHAPE AS CONSTRUCTION CONTINUES ON THE NEW NY BRIDGE PROJECT
For immediate release: September 5, 2014
UPDATED: VIEWING PLATFORMS TAKE SHAPE AS CONSTRUCTION CONTINUES ON THE NEW NY BRIDGE PROJECT
Construction on the New NY Bridge viewing platform in Nyack took another step forward this past week as Nyack officials broke ground on a new fishing pier in Memorial Park. The pier will be the site of the Rockland viewing platform. The plan for the site is the result of months of collaboration between village officials and the New NY Bridge project team
Viewing platforms in Nyack and at Scenic Hudson RiverWalk Park in Tarrytown will provide residents and visitors with an unobstructed and easily accessible view of the historic project’s progress and will include spotter’s guides, informational signs and high tech binoculars.
The installation of the new bridge’s pile caps will continue the week of Sept. 8. The caps, which cover the foundation piles installed in the river, are large hollow tubs that are fabricated offsite. The forms weigh several hundred tons and are barged to the project site for installation. Once in place, they are filled with reinforcing steel and concrete.
Construction will continue in the Hudson River as crews place the foundation for the New NY Bridge. Work will include pile driving between 7 a.m. and 7 p.m., Monday through Friday and 12 noon to 7 p.m. on Saturday.
A second shift of workers will also continue pile welding, pile cleanout and concrete placement operations associated with permanent foundations.
TZC will also continue construction on the new bridge’s Westchester landing, drilling holes into the bedrock for the foundation. This drilling process will produce less noise than the impact pile driving alternative, and TZC has installed sound mitigation to further reduce noise levels for the eight-week operation. The work will continue to the new westbound abutment in Westchester over the next few weeks.
Sheet pile installation at the Rockland landing is complete at this time. The sheet piles will allow TZC to excavate soil in that location and construct the westbound landing for the new bridge.
Work will continue on the Rockland work trestle near the shoreline, including pile driving and cofferdam installation. The trestle will support equipment used for the construction of the westernmost section of the new bridge.
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of five knots, and to use extreme caution on the river at all times.
More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.
Mariners should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.
Lane Closures for New York State Thruway (I-87/I-287):
Monday | Sept 08 | Northbound, Left Lane near Exit 9 | 9 a.m. to 3 p.m. |
Tuesday | Sept 09 | Northbound, Left Lane near Exit 9 | 9 a.m. to 3 p.m. |
Wednesday | Sept 10 | Southbound, Right Lane near Exit 9 | 10 a.m. to 3 p.m. |
Ongoing Operations:
- Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays
- Pile Cap foundation construction
- Main Span foundation construction
- Rockland Landing construction
- Westchester landing construction
- River Road utility work
- Rockland trestle construction, including pile driving
- Survey inspections on existing bridge
- Support for river-based work from the Rockland trestle
Tappan Zee Bridge path critic teams with South Nyack
South Nyack beefs up its TZ Task Force as it tackles surrounding the new crossing’s bike and walking path.
Following a public outcry, the three members of South Nyack’s bridge task force quickly decided to hit the reset button, asking the Tappan Zee project team to work with them to take another look at where the path would end in the village, where people would park and other local impacts.
The task force also made another move: it added Toolan to its team, along with Nancy Willen, who recently retired from the Clarkstown Highway Department.
Toolan, a land surveyor currently working on the Second Avenue subway project in Manhattan, has remained active since that contentious meeting with village and project officials at Nyack College. In many ways, he represents the other village residents who spoke that night, those skeptical of the state’s intentions and worried about the dangers that drivers in search of parking in neighborhoods would pose to residents.
A resident since 2007, Toolan, his wife and three children live on Cornelison Avenue, not far from the proposed site for the path’s terminus at the corner of his street and South Broadway. That terminus would be directly across from a southbound entrance to the Thruway.
“I’m pretty directly affected by what’s happening with that” path, Toolan said, describing its location “an afterthought” on the state’s part.
Rather than just complain, Toolan has been trying to come up with solutions, as he’s well-versed in blueprints and design technicalities.
Even before joining the task force, he met with project engineers to pitch a plan. It’s a bit complicated but basically allows Interchange 10 to remain a construction staging area for the duration of building, but eliminates the need to circle entirely around the interchange. Instead, he envisions a roundabout near South Franklin Street. He calls for reconnecting Route 9W back to Hillside Avenue to handle two-way traffic and closing off the Thruway entrance on South Broadway, so the ramp can be used for parking.
Though he has no hard cost figures, he admits it would carry “quite a price tag.”
“It’s kind of grandiose, but it all makes sense,” Toolan said. He also belongs to the Tappan Zee Gateway Alliance, a recently formed group concerned about the location of the shared path.
A rendering of Toolan’s proposal will be included in a meeting to update the community of the different ideas. It may take place this month.
Toolan remains a pragmatist though. He said ending the path at Cornelison as originally planned remains “a huge possibility.”
But it won’t be for a lack of effort from him and others in the community.
“I know there’s a lot of animosity you can get wrapped up in, but I would rather get a good solution than focus on what was done in the past,” Toolan said.
Willen, a 10-year resident of South Nyack, acknowledged that while she had to catch up with the rest of the volunteer task force, her experience working as confidential secretary to the highway superintendent for 16 years made her familiar with some of the issues and players involved.
Connie Coker, a member of the village task force, was excited to see what the two newest members would bring to the conversation.
“I think they’re both really going to add a lot,” Coker said.
Twitter: @ksaeed1
Port Expected in Newburgh NY
CITY OF NEWBURGH — A riverfront company aims to build a port on the Hudson from which it can transport decking for the new Tappan Zee Bridge.
Officials of Steelways Inc. and the city will join federal and state officials Friday morning to announce the effort, which Steelways spokeswoman Susan Sullivan said could bring 150 jobs over three years.
Mayor Judy Kennedy and Councilwoman Genie Abrams declined to discuss details of the plan in advance of Friday’s announcement, though both spoke glowingly — in general terms, anyway — of its potential. Among the expected attendees are Rep. Sean Patrick Maloney, D-Cold Spring, state Sen. William Larkin, R-C-Cornwall-on-Hudson, and Assemblyman Frank Skartados, D-Milton.
“This project has such potential,” Kennedy said. “It can truly change the economics of Newburgh.: Abrams said: “It will be very good news for the people of Newburgh, the kind of news we haven’t heard in 50 years.”
Sullivan said the company will bid on Friday to supply precast concrete decking for the new Tappan Zee Bridge. The contract will likely be awarded within a few weeks. Steelways can begin work on the port in April and complete the project by late summer. The company’s website says its 60 waterfront acres already include a shipyard with three sheltered harbors.
It has concrete marine launchways capable of accommodating vessels up to 300 feet long and 125 feet wide, and a marine railway capable of hauling 500-ton vessels. The main shipping channel runs adjacent to Steelways’ main pier, according to the site.
A resolution adopted Monday by the City Council expressed its “conceptual support of the Port of Newburgh project,” saying it will boost Newburgh’s economy by creating high-paying jobs and providing job-training opportunities for city residents.
Thomas Wright, a co-owner of Atlas Industries, a furniture designer and maker in the city, said who gets the potential jobs is important. “Jobs are great, but where do the people eat and live?” Wright said. “Are they people from Middletown driving to a parking lot, or people in Newburgh walking from their home in the city?”
Newburgh was once such a busy port that it had its own U.S. Customs office. Sailing ships were built at the waterfront in the 18th century. Navy ships were docked in Newburgh for repairs and reconstruction during World War II, said Mary McTamaney, the city’s historian. The Newburgh waterfront was where farmers brought their produce for shipping to New York City and beyond. “We were a transportation city,” McTamaney said. “We brought the goods of Orange County and the region to market, mostly downriver.”
http://www.recordonline.com/apps/pbcs.dll/article?AID=/20140131/NEWS/401310366
Super Crane Clears the Panama Canal
For immediate release: January 17, 2014
I LIFT NY SUPER CRANE COMPLETES TRANSIT THROUGH PANAMA CANAL,
CONTINUES JOURNEY TOWARD NEW NY BRIDGE PROJECT SITE
The I Lift NY super crane’s journey to the New NY Bridge project began on Dec. 22 and continues as the floating crane completed its transit through the Panama Canal on Jan. 17. Updated information about the journey, including photos and video, will be available at NewNYBridge.com.
The recently nicknamed I Lift NY super crane is owned by Tappan Zee Constructors, LLC (TZC) and is officially registered with the U.S. Coast Guard as the Left Coast Lifter.
TZC resumed operations this week after severe winter weather and icy conditions required the suspension of work on the river for one week for safety purposes. Foundation construction of the New NY Bridge will continue beginning Monday, as weather permits, with the ongoing installation of permanent piles.
The northbound, right-hand lane and shoulder of the New York State Thruway (I-87/I-287) near exit 10 in Nyack will be closed from 10 a.m. to 3 p.m. on Tuesday, Jan. 20, through Thursday, Jan. 23, to allow for work on the northbound access ramp. The same lanes will be closed on Friday, Jan. 24 from 10 a.m. to 1 p.m.
Mariners should be aware that TZC will continue installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.
The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) – 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website at NewNYBridge.com under the “Boater Safety” icon.
Ongoing Operations:
- Rockland access ramp modifications
- Armoring of dredge channel
- River Road utility work
- Test pile program
- Permanent pile installation
- Temporary Rockland trestle construction, including pile driving on weekdays 7 a.m. to 7 p.m.
- Survey inspections on existing bridge
- Support for river-based work from the Rockland shoreline
- Reinforcement steel pre-assembly at bridge yard
GIANT FLOATING CRANE PREPARES FOR PASSAGE THROUGH THE PANAMA CANAL, EN ROUTE TO NEW NY BRIDGE PROJECT
For immediate release: January 10, 2014
GIANT FLOATING CRANE PREPARES FOR PASSAGE THROUGH THE PANAMA CANAL, EN ROUTE TO NEW NY BRIDGE PROJECT
The journey that began late last month for one of the world’s largest floating cranes continues as it prepares to pass through the Panama Canal this weekend.
The crane, known as the Left Coast Lifter, is expected to begin its passage through the Panama Canal as soon as Saturday, Jan. 11, and updated information on its journey will be available at NewNYBridge.com. It departed from Oakland, California, on Dec. 22, escorted by tug boats, and is expected to arrive in New York at the end of the January.
A fourth construction camera is now live and is also available on the project website. The public can stay up-to-date on the progress of the New NY Bridge project with views from this camera, which captures construction as viewed from Tarrytown, as well as through those already live from Rockland County, Westchester County and on the bridge. An interactive archive calendar also allows viewers to take a look back at progress already made.
As weather permits, Tappan Zee Constructors, LLC (TZC) will continue construction of the foundation of the New NY Bridge with ongoing installation of permanent piles. TZC plans to begin full production again on Monday, Jan. 13, assuming temperatures rise and ice clears the river.
On Monday, Jan. 13 and Tuesday, Jan. 14, the southbound, right-hand lane and shoulder of the New York State Thruway (I-87/I-287) near exit 10 in Nyack will be closed from 10 a.m. to 3 p.m. On Wednesday, Jan. 15 and Thursday, Jan. 16, the northbound, right-hand lane and shoulder of the Thruway (I-87/I-287) near exit 10 in Nyack will be closed from 10 a.m. to 3 p.m., to allow for work on the northbound maintenance ramp.
Mariners should be aware that TZC will be installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.
The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) – 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website at NewNYbridge.com under the “Boater Safety” icon.
Ongoing Operations:
• Rockland access ramp modifications
• Armoring of dredge channel
• River Road utility work
• Test pile program
• Permanent pile installation
• Temporary Rockland trestle construction, including pile driving on weekdays 7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline
• Reinforcement steel pre-assembly at bridge yard
New NY Bridge Update January 03, 2014: NEW NY BRIDGE PROJECT SUSPENDS OPERATIONS TODAY, TOMORROW DUE TO WINTER STORM
For immediate release: January 03, 2014
NEW NY BRIDGE PROJECT SUSPENDS OPERATIONS TODAY, TOMORROW DUE TO WINTER STORM
Due to severe weather conditions, Tappan Zee Constructors, LLC (TZC), suspended scheduled project operations for today and tomorrow, but a small crew remains on site to continuously monitor conditions and respond immediately to any weather-related issues.
Normal operations are scheduled to resume Monday, as crews continue construction of the foundation of the New NY Bridge with the ongoing installation of permanent piles.
Subsurface utility investigations will take place in Tarrytown the week of Jan. 6. To facilitate this operation, the northbound right-hand lane of the New York State Thruway (I-87/I-287) near the approach to the Tappan Zee Bridge in Tarrytown will be closed on Monday, Jan. 6 and Tuesday, Jan. 7, from 10 a.m. to 3 p.m.
>From Tuesday, Jan. 7, through Thursday, Jan. 9, the northbound right-hand lane and shoulder of the Thruway (I-87/I-287) near exit 10 in Nyack will be closed from 10 a.m. to 3 p.m. The same section of roadway will be closed on Friday, Jan. 10, from 10 a.m. to 1 p.m., to allow for work on the northbound maintenance ramp.
Mariners should be aware that Tappan Zee Constructors, LLC (TZC) will be installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.
The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) – 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website at NewNYbridge.com under the “Boater Safety” icon.
Ongoing Operations:
• Rockland access ramp modifications
• Armoring of dredge channel
• River Road utility work
• Test pile program
• Permanent pile installation
• Temporary Rockland trestle construction, including pile driving on weekdays 7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline
• Reinforcement steel pre-assembly at bridge yard
No Construction For Christmas Day!
For immediate release: December 20, 2013
NO CONSTRUCTION ACTIVITIES PLANNED FOR CHRISTMAS DAY, RAMP RE-OPENS TO ACCOMMODATE HOLIDAY TRAVELERS
No construction activities are scheduled for the New NY Bridge project on Christmas Day, Wednesday, Dec. 25, and the Tarrytown entrance ramp from South Broadway to the Tappan Zee Bridge has been temporarily re-opened to traffic to accommodate holiday travelers.
Referred to as Ramp E by the New York State Thruway Authority, the ramp from Route 9 southbound to I-87/I-287 was closed earlier this month to allow Tappan Zee Constructors, LLC (TZC) to utilize the area surrounding the ramp for construction access to keep construction vehicles off local streets, perform underground utility work and shift Thruway traffic headed toward the Tappan Zee Bridge onto the ramp area in 2014.
The ramp, which has routinely closed for bridge-related maintenance projects, will close again in January and will remain closed for the duration of the project. Its complete closure is required for the construction of the New NY Bridge, and to ensure safety for the traveling public and construction workers.
Excavation and preparation for the installation of permanent sound barriers continues along I-87 northbound/I-287 westbound in the area south of exit 10 in Rockland County.
This weekend, one of the countrys most famous floating cranes will weigh anchor and begin its journey, traveling from Oakland Harbor, near San Francisco, to the site of the New NY Bridge project. Named The Left Coast Lifter for its use in the replacement of the eastern span of the San FranciscoOakland Bay Bridge, the floating crane will be used in the construction of the New NY Bridge.
A highly experienced crew of mariners will guide the 400-foot-long crane along the West Coast, through the Panama Canal and the Gulf of Mexico, and then up the East Coast before arriving in the Hudson River. The trip is approximately 6,000-miles long and will take between six and eight weeks to complete.
Mariners should be aware that TZC will be installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.
The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website at NewNYbridge.com under the Boater Safety icon.
Ongoing Operations:
• Rockland access ramp modifications
• Armoring of dredge channel
• River Road utility work
• Test pile program
• Permanent pile installation
• Temporary Rockland trestle construction, including pile driving on weekdays7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline
• Reinforcement steel pre-assembly at bridge yard
West Nyack buildings demolished to clear way for ‘Palisades Plaza’
LoHud By Akiko Matsuda November 27, 2013
http://m.lohud.com/RocklandNews/article?a=2013311260048&f=1168
Demolition work in West Nyack has made the way for a strip mall, to be known as Palisades Plaza. – Akiko Matsuda/The Journal News
WEST NYACK — A triangular lot with three buildings that was an eyesore for years will soon become a strip mall with a restaurant.
The 2.36-acre site is east of Route 303 and south of the New York State Thruway. The lot originally consisted of three separate properties: a single-story mixed-use office and light manufacturing building, a former state police barracks, and a former Texaco station.
Those buildings were all demolished recently. On Tuesday, heavy machinery was crushing chunks of concrete left behind.
The development is the latest sign of life to spring out of disused lots in the Tappan Zee Bridge corridor.
Developer Lawrence Adler of East Syracuse has gone before the Clarkstown Planning Board for his plans to build a 13,900-square-foot strip mall at the site, combining the three lots into one.
“Palisades Plaza” will include four retail stores and a restaurant with drive-thru service. Names of the future occupants are not mentioned in the application.
Adler and Ira Emanuel, an attorney representing the developer, did not return phone and email messages seeking comment.
Clarkstown Principal Town Planner Joe Simoes said the developer has taken all the necessary steps with regulatory jurisdictions.
At its meeting last month, the Clarkstown Planning Board granted final approval for the project, and the developer is in the process of getting Planning Board Chairwoman Shirley Thormann’s signoff.
The Tappan Zee Bridge replacement project has been stimulating the local real estate scene, as bridge builder Tappan Zee Constructors is leasing properties for temporary construction staging areas.
The former Journal News printing plant at 160 N. Route 303 — just north of the proposed Palisades Plaza — is slated to become a temporary home for state police and the New York state Thruway Authority.
Simoes said he didn’t believe the strip mall project was prompted by the bridge construction because the developer has been unsuccessfully trying to bring new businesses to the site for some time.
Because it’s an oddly shaped property that was partly zoned “residential,” it has been difficult to develop, Simoes said. Most recently, a mini-storage project was proposed, but the plan didn’t work out, he said.
The zoning issue has been resolved, making a way for the strip mall.
Simoes said the new development would be good for the community.
“It’s been such an eyesore for years that it’s an improvement,” he said.
Twitter: @LohudAkiko
Inaugural Newsletter of the New NY Bridge
The New York State Thruway Authority and the New NY Bridge team are proud to launch the first issue of the New NY Bridge Newsletter, a monthly publication designed to keep everyone abreast of the latest news about the project.
The newsletter, produced in partnership with Tappan Zee Constructors, LLC (TZC), is one of many outreach tools employed to keep residents of Rockland and Westchester counties and the entire region informed about the New NY Bridge Project — the largest transportation infrastructure project in North America. Please enjoy the inaugural issue of the New NY Bridge Newsletter.
Read the complete Newsletter document here: MonthlyNewsletter_Nov_2013 (3)
TZ Bridge Pre-Construction Activities Continue
For immediate release: October 11, 2013
NEW NY BRIDGE PROJECT
PRE-CONSTRUCTION ACTIVITIES CONTINUE
Second shift operations will continue on the river from 3:30 p.m. to 12 midnight on weekdays in preparation for permanent construction activities.
This work is primarily to support activities for the daytime pile driving operations and is limited by the project’s noise level restrictions. Pile driving will be limited to the hours of 7 a.m. to 7 p.m. on weekdays and, occasionally, from 12 noon to 7 p.m. on Saturdays.
Construction of the Rockland County trestle will continue. This work will include daytime pile driving to install the temporary foundation piles needed to support the platform. The trestle is a work platform that will support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required.
From Tuesday, October 15 to Friday, October 18, one southbound right hand lane and shoulder on I-87/I-287 between exit 9 and exit 11 will be closed from 9 a.m. to 3 p.m. for shoulder work.
Additionally, utility work will continue on River Road in South Nyack. This work will be performed from 6:30 a.m. to approximately 6 p.m. for the next three weeks and has been coordinated with and approved by the Village of South Nyack. The work will reduce the roadway to one lane during daytime hours and flaggers will be onsite to safely direct motorists on River Road. During non-work hours, the road will have temporary coverings in place that may create uneven surfaces. Motorists and bicyclists should slow down and use extreme caution in the area.
Mariners should be aware that TZC will be installing piles in the vicinity of the side channels. Both temporary and permanent piles are illuminated at night.
The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area.
If necessary, the Coast Guard in the future may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website, NewNYBridge.com, under the boating safety icon.
E-ZPass tags are now available for purchase at the New NY Bridge Community Outreach Centers in Tarrytown and Nyack.
The pre-packaged E-ZPass tags can be purchased for $25 and are ready for immediate use. E-ZPass users avoid delays when traveling through toll plazas, receive a discount on every Thruway toll they pay, and enjoy the convenience of using E-ZPass in fifteen states: Delaware, Illinois, Indiana, Maine, Maryland, Massachusetts, New Hampshire, New Jersey, New York, North Carolina, Ohio, Pennsylvania, Rhode Island, Virginia, and West Virginia.
E-ZPass tags have a $25 value and are active upon purchase. The first $15 is immediately available for toll usage, and the remaining $10 becomes available once the tag is registered online or by phone. E-ZPass provides a five percent savings on Thruway tolls and offers toll discounts on many other roadways.
The Community Outreach Centers for the new bridge project were established last year as a gathering place and source of information for the community regarding the New NY Bridge. They are located at:
• 303 South Broadway in Tarrytown, and
• 142 Main Street in Nyack.
The centers are open Monday through Friday, 11 a.m. to 7 p.m.; Saturday and Sunday, 11 a.m. to 4 p.m.
Ongoing operations:
• Dredging operations will continue 24/7
• Test pile program
• Rockland Dock Extension under existing bridge
• Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
• Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline
The New York Bridge Quarterly Newsletter
The NewNYBridge releases it quarterly Newsletter.
Check out the construction progress and what the future holds for the TappanZee Bridge project.
Visit: www.TheNewNyBridge.com
New NY Bridge Update August 16, 2013: LOAD TESTING FOR THE TEST PILE PROGRAM BEGINS; LANE CLOSURES ON BRIDGE
For immediate release: August 16, 2013
LOAD TESTING FOR THE TEST PILE PROGRAM BEGINS;
LANE CLOSURES ON BRIDGE
Tappan Zee Constructors, LLC (TZC) will begin testing both static and lateral loads this week as part of its test pile program.
These load tests are performed to ensure piles are capable of sustaining the design load of the new bridge. Testing will be conducted over a 40-hour period.
Impact pile driving will continue this week as part of the ongoing test pile program and will continue through October at various locations for future pile foundations. This work will be performed from 7 a.m. to 7 p.m. on weekdays and, at times, on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.
Overnight lane closures will also be required in both directions on I-87/I-287 and the Tappan Zee Bridge due to various construction activities.
Beginning Monday, August 19 through the morning of Wednesday, August 21, one southbound right hand lane and shoulder between exit 11 and the Tappan Zee Bridge will be closed from 9 p.m. to 6 a.m. for the installation of concrete traffic barriers to facilitate the reconstruction of the Thruway maintenance ramp. Additionally, one southbound right hand lane on the Tappan Zee Bridge will be closed during this period for the installation of structural monitors.
Beginning Wednesday, August 21 through the morning of Saturday, August 24, one northbound right hand lane and shoulder between exit 9 and the Tappan Zee Bridge, as well as one northbound right hand lane on the Tappan Zee Bridge will be closed from 9 p.m. to 6 a.m. for the installation of structural monitors.
Additional geotechnical borings will be conducted on the river at various locations. Operations will run 24 hours a day, Monday through Friday.
TZC will continue dredging operations in the Hudson River as part of the New NY Bridge Project. Dredging will occur through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.
Dredging crews will work 24 hours a day, seven days a week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.
The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.
The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.
Ongoing operations:
· Test pile program
· Rockland bulkhead construction (including fence & gates) and Dock Extension at Rockland (under existing bridge)
· Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline
Rockland:
TZC will continue fencing and sidewalk work along River Road in South Nyack north of the existing bridge. This work is part of the bulkhead construction area and will be performed on weekdays between 7 a.m. and 3 p.m. At times, River Road will be limited to one lane with flag persons in place to ensure the safe flow of traffic.
DREDGING OPERATIONS BEGIN, TEST PILE PROGRAM IMPACT PILE DRIVING ONGOING
Project Update
For immediate release: August 2, 2013
Tappan Zee Constructors, LLC (TZC) began 24 hour a day dredging operations today in the Hudson River as part of the New NY Bridge Project.
The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use extreme caution within 1,000 feet of all construction barges as a safety precaution.
The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com.
Dredging will occur over a three-month period from August 1 through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.
Dredging crews will work 24 hours a day, seven days a week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being processed and properly disposed at offsite locations.
Impact Pile driving began this week as part of the ongoing test pile program and will continue over the next three months at various locations for future pile foundations. This work will be performed 7 a.m. to 7 p.m. on weekdays and at times on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions test structural load capacities in preparation for construction of the new bridge’s permanent foundation.
Ongoing operations:
· Test pile program
· Rockland bulkhead construction (including fence & gates)
· Dock Extension at Rockland (under existing bridge)
· Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Rockland and Westchester environmental monitor installations
· Geotechnical land borings
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline
Westchester:
Limited test-boring operations will continue on Thruway property near the Irving Neighborhood in Tarrytown. The work is scheduled to be conducted between the hours of 7 a.m. and 5 p.m. Monday, August 5 through Wednesday, August 6.
Rockland:
TZC, LLC will reconstruct the sidewalk along River Road in S. Nyack north of the existing bridge. This is part of the Bulkhead construction area and will be performed between 7 a.m. and 3 p.m. Monday, August 5 and Tuesday, August 6. River Road will be limited to one lane with flag persons in place to control traffic safely.
Survey activity will occur in the southbound lanes of I-87/I-287 and will require a temporary lane closure between exit 10 and the existing bridge from 10 a.m. to 3 p.m. Monday, August 5 and Tuesday, August 6.
NEW NY BRIDGE TEST PILE PROGRAM STARTS NEXT WEEK
For immediate release: July 12, 2013
NEW NY BRIDGE TEST PILE PROGRAM STARTS NEXT WEEK
Beginning the week of July 15, Tappan Zee Constructors, LLC will install the first test piles for the New NY Bridge.
The test pile operations will be conducted over the next three months at proposed locations for pile foundations. Work will start at the main span footings. Piles will be placed by utilizing both vibratory and impact installation techniques. The test pile program will verify subsurface conditions in preparation for the construction of the bridge’s permanent foundation.
Multiple crews will conduct night time boring operations along I-87/I-287 in both Westchester and Rockland Counties. The night time operations are necessary due to lane closure restrictions during day time hours that are in place to keep traffic flowing over the current bridge. Boring operations will begin at exit 10 in Rockland County and move west into Westchester County.
Ongoing operations
– Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
– Survey inspections on existing bridge
– Rockland environmental monitor installations continue
– Geotechnical land borings
– Mobilization at the exit 10 staging area
– Support for river-based work from the Rockland shoreline
Westchester:
Night time boring operations to investigate subsurface soil conditions will be conducted in the southbound shoulder of I-87/I-287 and will require a temporary right lane closure between the existing bridge and exit 9 on Friday, July 19 from 9 p.m. to 6 a.m.
Rockland:
Night time boring operations to investigate subsurface soil conditions will be conducted in the southbound shoulder of I-87/I-287 and will require a temporary right lane closure between exit 10 and the existing bridge from 9 p.m. to 6 a.m. beginning Monday, July 15 through Thursday, July 18.