CONSTRUCTION CONTINUES ON THE NEW NY BRIDGE

update

Nighttime and overnight electrical work on the Tarrytown approach to the Tappan Zee Bridge will continue the week of August 4. The I-87 northbound/I-287 westbound right lane will be closed Monday, August 4 through Friday, August 8 from 9 p.m. each evening to 5 a.m. the following morning. The Thruway will remain open to traffic during these operations.

Construction will continue in the Hudson River as crews install foundations for the New NY Bridge. Work will include pile driving between 7 a.m. and 7 p.m., Monday through Friday and 12 noon to 7 p.m. on Saturday.

A second shift of workers will also continue pile welding, pile cleanout and concrete placement operations associated with permanent foundations.

Sheet pile driving at locations on land and near the Rockland landing is temporarily on hold due to high noise levels from the operation. TZC will implement additional noise-reducing measures before resuming these operations. Sheet pile driving will commence once the measures are in place. All other construction activities not associated with driving the sheet piles will continue.

Work will also continue on the Rockland temporary work trestle near the county shoreline, including pile driving to install the temporary foundations needed to support the platform. The trestles will support cranes for the construction of the western-most section of the new bridge.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of five knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are illuminated at night as are all moorings, barges and other equipment.

Lane Closures for New York State Thruway (I-87/I-287):

Monday Aug 4 Northbound, Right Lane near Exit 9 10 a.m. to 3 p.m.
Monday Aug 4 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.
Tuesday Aug 5 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.
Wednesday Aug 6 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.
Thursday Aug 7 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.
Friday Aug 8 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.

Ongoing Operations:

  • Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays
  • Pile cap foundation construction
  • Main span foundation construction
  • Rockland landing construction
  • Westchester landing construction
  • River Road utility work
  • Rockland trestle construction, including pile driving
  • Survey inspections on existing bridge
  • Support for river-based work from the Rockland trestle

New NY Bridge Update August 16, 2013: LOAD TESTING FOR THE TEST PILE PROGRAM BEGINS; LANE CLOSURES ON BRIDGE

bridge

For immediate release: August 16, 2013

LOAD TESTING FOR THE TEST PILE PROGRAM BEGINS;
LANE CLOSURES ON BRIDGE

Tappan Zee Constructors, LLC (TZC) will begin testing both static and lateral loads this week as part of its test pile program.

These load tests are performed to ensure piles are capable of sustaining the design load of the new bridge. Testing will be conducted over a 40-hour period.

Impact pile driving will continue this week as part of the ongoing test pile program and will continue through October at various locations for future pile foundations. This work will be performed from 7 a.m. to 7 p.m. on weekdays and, at times, on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

Overnight lane closures will also be required in both directions on I-87/I-287 and the Tappan Zee Bridge due to various construction activities.

Beginning Monday, August 19 through the morning of Wednesday, August 21, one southbound right hand lane and shoulder between exit 11 and the Tappan Zee Bridge will be closed from 9 p.m. to 6 a.m. for the installation of concrete traffic barriers to facilitate the reconstruction of the Thruway maintenance ramp. Additionally, one southbound right hand lane on the Tappan Zee Bridge will be closed during this period for the installation of structural monitors.

Beginning Wednesday, August 21 through the morning of Saturday, August 24, one northbound right hand lane and shoulder between exit 9 and the Tappan Zee Bridge, as well as one northbound right hand lane on the Tappan Zee Bridge will be closed from 9 p.m. to 6 a.m. for the installation of structural monitors.

Additional geotechnical borings will be conducted on the river at various locations. Operations will run 24 hours a day, Monday through Friday.

TZC will continue dredging operations in the Hudson River as part of the New NY Bridge Project. Dredging will occur through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.

Dredging crews will work 24 hours a day, seven days a week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.

Ongoing operations:
· Test pile program
· Rockland bulkhead construction (including fence & gates) and Dock Extension at Rockland (under existing bridge)
· Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline

Rockland:
TZC will continue fencing and sidewalk work along River Road in South Nyack north of the existing bridge. This work is part of the bulkhead construction area and will be performed on weekdays between 7 a.m. and 3 p.m. At times, River Road will be limited to one lane with flag persons in place to ensure the safe flow of traffic.

Residents will vote on Tappan Zee Bridge noise barriers

LoHud June 27, 2013 Written By Khurrum Saeed

http://www.lohud.com/apps/pbcs.dll/article?AID=2013306270071

TZC

About 400 Rockland and Westchester residents have until July 11 to decide whether they want noise barriers on and near the new Tappan Zee Bridge.

Four areas are under consideration for the noise walls, which will range from 10 to 18 feet in height depending on their location, a project official said.

Different neighborhoods are voting on their noise barriers in their area. The vote is legally binding under federal law.

Residents have also been asked to choose a look for the barriers that will help guide the final design.

If approved, the $2 million noise walls would be part of the new $4 billion project to replace the Tappan Zee Bridge and would be added during its five-year construction phase.

Last year, a group of South Nyack residents successfully demanded to be included in the vote since their property — Salisbury Point Cooperative — sits along the Thruway and will be even closer to the new bridge than the existing span.

“They really got smart because of the ruckus that we raised,” Salisbury Point resident John Brown said of the state Thruway Authority.

Brown planned to cast his vote Thursday in favor of adding the extra layer of noise protection and sensed most people in his complex were with him.

Salisbury Point board president Catherine McCue said she was grateful the state reconsidered and involved them in the process, along with dozens of homeowners in South Nyack and Upper Grandview. In all, 268 people in Rockland were sent ballots and 106 in Westchester.

The barriers and their appearance were discussed at a Thursday night meeting at the Best Western hotel in Nyack.

Two meetings held in Westchester earlier this week brought out about 50 residents, some from The Quay and Tappan Landing Road complexes.

In order for the barriers to move ahead, at least 50 percent of the ballot holders must vote, and a simple majority must vote in favor of building them.

Watch The New NY Bridge Animation

Tappan Zee Constructors recommended to build new Tappan Zee Bridge

Tappan Zee Bridge Presentation: The state Thruway Authority on Dec. 5, 2012 released three designs to build a new Tappan Zee Bridge. The $3.1 billion bid from Tappan Zee Constructors has apparently won the state’s recommendation. Video by WGRZ/wgrz.com

Tappan Zee Constructors has won the state’s advisory committee recommendation to build the new Tappan Zee Bridge for $3.1 billion, a source close to the selection process told The Journal News on Wednesday.

The consortium, which includes the company that built the existing 3-mile Tappan Zee 57 years ago, offered the least expensive bridge plan among the three teams competing for one of the largest public works projects in the country.

The suggested design for the Tappan Zee replacement, a cable-stayed bridge, has oddly angled towers on each span, a feature so unique it’s never been used in the United States, a state official said. He added that he knows of only one bridge — in Russia — with a similar element.

The twin-span bridge would also include a concrete deck on top of steel girders. Like the other two options, it would be strong enough to carry trains in the future. In addition, it would have deck connections in four places that can be used to turn traffic around in emergencies.

The crossing would have 35 piers in the river and be made up of 350-foot long spans to create the road deck. Those spans would be six times longer than the current ones. The proposal also calls for less dredging during construction than the state initially said would be required.

The Thruway Authority on Wednesday released the three proposals for the new bridge, but did not identify each team’s proposal, citing federal rules.

“To get a bridge to this point in a year was really a fantastic accomplishment,” Gov. Andrew Cuomo said at a presentation at the Capitol.

Officials also announced that the state’s 38-member review panel had chosen the $3.1 billion bid because “they determined it was the best value,” said Brian Conybeare, a special adviser on the project.

The three proposals pegged the replacement cost between $3.1 billion and $4 billion, all much less than the initial construction price tag of $5.2 billion. Still, the proposal prices are preliminary estimates and don’t include another $600 to $800 million for expenses such as financing and management, state officials said.

American Bridge Co., which built the Tappan Zee, and Fluor Enterprises are members of the recommended Tappan Zee Constructors team. Those two firms are also involved in the $6.4 billion reconstruction of the San Francisco–Oakland Bay Bridge. A joint venture involving Kiewit Infrastructure and Skanska USA and a partnership of Bechtel Infrastructure and Tutor Perini also submitted proposals.

The construction time for each proposal was more than five years. Work is expected to begin next year.

Though the state’s panel has selected Tappan Zee Constructors, the Thruway Authority board makes the final decision. The board is set to vote for a winning team on Dec. 17. Until then, officials said the public can weigh in on the proposals on the bridge project’s website: http://www.newnybridge.com.

The design review team’s recommendations will be a major factor in the final decision, said Thomas Madison, the Thruway Authority’s executive director.

The contract award will have a ripple effect for homeowners in Rockland and Westchester.

A group of six neighbors in South Nyack are waiting to learn if they’ll remain in their homes during construction or they’ll be bought out, as most of them want. The state originally planned to take the homes but reversed that decision in May. The homeowners have asked the state to reconsider.

Homeowners said state officials have told them the contract award would allow the state to finally make a decision.

“It would be good to finally come to some kind of closure because everything has been up in the air for the longest time,” said John Cameron, who has lived in his South Broadway home with his wife, Hope Elliott Cameron, for the past six years.

A state official told Cameron and his neighbors they have reason to be “optimistic,” which he believes means the state will ask the winning bidder to buy the homes, he said.

Not everyone was satisfied with Wednesday’s developments, though.

Veronica Vanterpool, executive director of Tri-State Transportation Campaign, charged that the state’s preview of the proposals was incomplete. Her group has pushed for the plan to include mass transit along the Interstate 287 corridor.

“The proposals are still unclear about what mass transit ready means,” Vanterpool said in an email to The Journal News. “We look forward to an announcement of the TZB transit task force so these details can be hammered out. The proposals came in significantly below the projected $5.2 billion price tag, creating a greater opportunity to incorporate low-cost, bus rapid transit improvements into the project.”

Riverkeeper, the Hudson River’s leading advocacy group, was also not eager to endorse any of the proposals. Riverkeeper has criticized the state’s plan for not adequately addressing how the project could harm marine life.

“Riverkeeper is not surprised that the state has identified a reduced dredging option,” president Paul Gallay said. “We and the rest of the public need more information as to how this will affect the project’s overall environmental impacts, and we will seek to have those discussions with the state as soon as possible.”

Al Samuels, president of the Rockland Bussiness Association, said he agreed with the selection committee’s recommendation, which he said “makes the most sense.”

Plans for the new bridge have moved swiftly since last year, when the Obama Administration named it one of 14 top priority infrastructure projects across the country. In September, the Federal Highway Administration gave final approval to the project’s environmental study, allowing the replacement plan to proceed

It remains unclear, however, whether the federal government will give the state a low-interest loan. In its loan application, the state had said a new bridge could cost up to $5.9 billion. Without a significant loan, state officials warned of soaring tolls. Officials had said the current $5 cash toll could rise to $14.

Rockland Legislature Chairwoman Harriet Cornell said Wednesday she wants to know what a smaller price tag means for those toll increases.

“I’ve talked for years about not putting the tolls on the backs of commuters,” Cornell said.

 

New Tappan Zee Bridge Project Update : Video

New Tappan Zee Bridge Project – Project Meeting July 25, 2012

Here is the video:

The New Tappan Zee Project :Video

Executive Director Thomas J Madison on the LoHud Editorial Spotlight discusses the new Tappan Zee Bridge and its impact on the Hudson Valley:

 

Some property information provided by CoStar, Loopnet, HGAR, Yelp, Rand Commercial Services and other public sources.