TAPPAN ZEE CONSTRUCTORS TAKES EXTENSIVE NOISE MITIGATION MEASURES

For immediate release: May 18, 2015

TAPPAN ZEE CONSTRUCTORS TAKES EXTENSIVE NOISE MITIGATION MEASURES FOR SHEET PILE DRIVING AT PIER 1 IN ROCKLAND COUNTY

For the past week, Tappan Zee Constructors, LLC (TZC) has been installing and testing extensive noise mitigation measures in an effort to mitigate noise from vibratory sheet pile driving at Pier 1 off the Rockland shoreline. These efforts have successfully reduced the noise levels by more than 10 decibels. This work is expected to last 1-2 weeks with limited work hours and no sheet pile driving at Pier 1 on Saturdays, Sundays or Memorial Day Monday.

To minimize the effect on the local community, TZC will:

  • Limit the sheet pile driving at Pier 1 to the hours of 8AM-4PM Monday-Friday (none allowed on Saturday, Sunday or Memorial Day Monday)
  • Drive no longer than 30 minutes per hour
  • Use a noise shroud over the vibratory hammer
  • Erect a 40-ft wide x 30-ft tall temporary noise barrier between the work and South Nyack residents
  • Place noise barrier material over the previously driven sheets to reduce noise/vibration levels
  • Proactively reach out to the Village of South Nyack and local homeowners to inform them of the mitigation measures

Noise levels at sensitive receptors and nearby homes are expected to remain within the allowable levels listed in the New NY Bridge project’s Final Environmental Impact Statement as shown in the table below:

To view the New NY Bridge project environmental monitors that are updated every minute of every day go to www.NewNYBridge.com.

table

 

 

 

 

 

Tappan Zee Bridge contracts ensure ‘disadvantaged’ aren’t left out

tjuva@lohud.com11:22 p.m. EDT April 16, 2014

The Tappan Zee Bridge project has been a dream opportunity for small, budding businesses. And companies headed by women and ethnic and racial minorities are getting their own chances to score work on the $3.9 billion bridge replacement project, through a government effort to give a boost to certain groups that have historically been excluded from business opportunities.

The New York State Thruway Authority and bridge builder Tappan Zee Constructors is setting aside $314 million — 10 percent of the bridge construction cost — for companies certified as “disadvantaged business enterprises” by the federal government. Because the federal government is providing a low-interest loan to help pay for the Tappan Zee replacement, it requires that such companies are included. Brian Conybeare, special adviser to Gov. Andrew Cuomo on the project, said the project team has made a big effort to ensure those firms are included, “which will help them prosper, grow their businesses and employ more local workers.” So far, 60 certified DBEs have contributed to the project, totaling $49.7 million in subcontracts.

Here are some of their stories.

 From ironworker to business owner, Mike Aponte can still vividly recall his first day as an ironworker nearly 30 years ago. Aponte, now 48, was assigned to get coffee for crews building a high-rise on Wall Street.

“Never been up that high — I was shaking in my boots, but I didn’t show it to the men. That was some experience,” Aponte recalled.After working his way up from an ironworker to a foreman to a project supervisor, seven years ago Aponte became the president of his own steel construction company, Tyrek Heights Erectors Inc., a certified DBE based in Yonkers.”In general there has been the misconception that you can’t find a qualified a DBE — that’s not true,” he said. “There are many that are capable and put out quality work. We are not taking advantage of it. We actually perform. We know what we are doing.”So far, his company has done steel work at the TZC office on the Hudson Harbor property in Tarrytown. The firm has also removed and installed steel at the West Nyack building where the state police and Thruway Authority facilities will be temporarily relocated during bridge construction.

Still, Aponte has his sights set on the new structure”I would love to be part of the team that is going to erect and build the bridge,” he said. “To say one day to my grandkids, ‘I was part of this bridge,’ would be great.”

 

In the business of construction, Mahopac native Leigh Scirbona has never been daunted by working in a male-dominated industry. In her 20s, she began working for a highway construction company, reviewing contracts and handling project documents. For the last 25 years, Scirbona, now 56, has headed her own general contracting and concrete company, Advanced Contracting Concepts. The company has done work for the Walkway Over the Hudson project, Westchester and state parks and the New York State Bridge Authority. “I still have people who call me and say, ‘Honey, let me speak to your boss,’ ” she said. “It is still entertaining when they do that.” Last year, she expanded the company to construction administrative support services and landed work on the Tappan Zee project.  “A little over a year later, I’m on one of the largest design-build projects in the United States and one of the largest projects in New York state,” she said. “It’s been terrific.”

When TZC officials called her last year about finding them an office receptionist, Scirbona quickly responded. Not wanting to lose the chance, she worked the job herself for a week until she found someone permanent for the position. Scirbona has six employees as part of the Tappan Zee team, including the project’s documents control manager and a senior administrative assistant, and she hopes to keep expanding the list.The DBE program is critical to ensure all kinds of business owners are included in major infrastructure projects, she said.

“It doesn’t make us less qualified, less intelligent, less capable,” she said. “Without this program, smaller contractors wouldn’t get looked at.”

 

Husband and wife

Cynthia and John Behan share a business, but Cynthia is the one in charge “She really is the boss,” said her husband, co-owner of Behan Planning and Design, a landscape architecture and project planing firm and certified DBE. “She makes all the financial decisions. She makes all the hiring decisions. My role is now securing new work.” Such as the Tappan Zee project. The Behans’ firm, based in Saratoga Springs with a location in New City, has a subcontract with a public relations group hired by TZC. So far, the Behans’ company has helped organize Tappan Zee community outreach meetings and create public newsletters and presentations.

“To have this project that’s running steady for a while, it’s stabilizing for us,” said Cynthia Behan, 58, a landscape architect who also worked on the New City streetscape revitalization. John Behan, also 58, said his wife’s design knowledge is especially helpful when they are asked to put together presentations. “When we get technical documents from the engineers, she can understand the engineer drawings and help present them to the public,” he said. While their Rockland location only has one employee, the couple hopes more work on the project will allow them to hire a second one later this year.

How is a “disadvantaged business enterprise” defined?

The small company must be 51 percent owned by one or more “socially and economically disadvantaged” individuals, which are women and racial and ethnic minority groups.

Business revenue and the owner’s personal net worth are used to determine whether a company qualifies. Government officials conduct personal interviews, business visits and reviews of license and financial records before a firm is certified.

Source: New York State Thruway/U.S. Department of Transportation

TZB firms by the numbers

A total of 135 companies have worked on the project so far, totaling $432 million in subcontracts.

Of those, 60 are considered DBEs, with those subcontracts totaling $49.7 million.

$314 million has been set aside for DBEs

Source: Tappan Zee Constructors

CREWS MOBILIZE FOLLOWING WINTER WEATHER SHUTDOWN; PILE DRIVING RESUMES ON NEW NY BRIDGE PROJECT

new

Project Update

For immediate release: February 21, 2014

Tappan Zee Constructors, LLC (TZC) resumed marine operations and pile driving this week as icy conditions cleared in the Hudson River and crews could safely go back to work. Pile driving operations will continue next week and a second shift of workers will be onsite to resume welding on the piles that will become the permanent foundation for the New NY Bridge.

Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays.

Beginning the week of Feb. 24, crews will conduct nighttime geotechnical investigations on the Westchester approach to the existing bridge, in the vicinity of the toll plaza. Lane closures to support these operations will be in place from 8 p.m. to 5 a.m., as needed, to minimize disruptions to traffic. This geotechnical investigation will confirm the soil conditions and ultimately allow the team to further streamline the design of the Westchester landings.

Lane Closures for New York State Thruway (I-87/I-287):

Monday Feb. 24 Southbound, Right Lane Near Toll Plaza 8 p.m. to 5 a.m.
Tuesday Feb. 25 Southbound, Right Lane Near Toll Plaza 8  p.m. to 5 a.m.
Wednesday Feb. 26 Southbound, Right Lane Near Toll Plaza 8  p.m. to 5 a.m.
Thursday Feb. 27 Northbound, Right Lane Near Toll Plaza 8  p.m. to 5 a.m.
Friday Feb. 28 Northbound, Right Lane Near Toll Plaza 8  p.m. to 5 a.m.

Mariners should be aware that TZC will continue installing permanent piles in the vicinity of the side channels under the existing bridge, weather permitting. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) – 300 yards north and 200 yards south of the existing Tappan Zee Bridge. The U.S. Army Corps of Engineers has issued a modified permit for additional temporary mooring locations during construction of the new bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information and the modified mooring permit map can be found on the project website at NewNYBridge.com under the “Boater Safety” icon.

Ongoing Operations:
• Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays
• Rockland access ramp modifications
• River Road utility work
• Test pile program
• Permanent pile installation
• Temporary Rockland trestle construction, including pile driving on weekdays 7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline
• Reinforcement steel pre-assembly at bridge yard

No Construction For Christmas Day!

The new NY bridge

For immediate release: December 20, 2013

NO CONSTRUCTION ACTIVITIES PLANNED FOR CHRISTMAS DAY, RAMP RE-OPENS TO ACCOMMODATE HOLIDAY TRAVELERS

No construction activities are scheduled for the New NY Bridge project on Christmas Day, Wednesday, Dec. 25, and the Tarrytown entrance ramp from South Broadway to the Tappan Zee Bridge has been temporarily re-opened to traffic to accommodate holiday travelers.

Referred to as “Ramp E” by the New York State Thruway Authority, the ramp from Route 9 southbound to I-87/I-287 was closed earlier this month to allow Tappan Zee Constructors, LLC (TZC) to utilize the area surrounding the ramp for construction access to keep construction vehicles off local streets, perform underground utility work and shift Thruway traffic headed toward the Tappan Zee Bridge onto the ramp area in 2014.

The ramp, which has routinely closed for bridge-related maintenance projects, will close again in January and will remain closed for the duration of the project. Its complete closure is required for the construction of the New NY Bridge, and to ensure safety for the traveling public and construction workers.

Excavation and preparation for the installation of permanent sound barriers continues along I-87 northbound/I-287 westbound in the area south of exit 10 in Rockland County.

This weekend, one of the country’s most famous floating cranes will weigh anchor and begin its journey, traveling from Oakland Harbor, near San Francisco, to the site of the New NY Bridge project. Named “The Left Coast Lifter” for its use in the replacement of the eastern span of the San Francisco—Oakland Bay Bridge, the floating crane will be used in the construction of the New NY Bridge.

A highly experienced crew of mariners will guide the 400-foot-long crane along the West Coast, through the Panama Canal and the Gulf of Mexico, and then up the East Coast before arriving in the Hudson River. The trip is approximately 6,000-miles long and will take between six and eight weeks to complete.

Mariners should be aware that TZC will be installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website at NewNYbridge.com under the “Boater Safety” icon.

Ongoing Operations:
• Rockland access ramp modifications
• Armoring of dredge channel
• River Road utility work
• Test pile program
• Permanent pile installation
• Temporary Rockland trestle construction, including pile driving on weekdays7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline
• Reinforcement steel pre-assembly at bridge yard

Neighboring community takes sound-proofing offer; 2 more complexes consider funds to mitigate noise

Lohud;  June 25, 2013  Written by Theresa Juva-Brown

Neighbors want more than noise reducing windows

http://www.lohud.com/videonetwork/2507049237001/TZB-neighbors-offered-noise-protections

Nearly a week after Tappan Zee Constructors offered to spend $4.2 million on noise-reducing windows and doors for some bridge neighbors, only one community has officially accepted the proposal.

Bradford Mews has agreed to Tappan Zee Constructor’s offer to shell out $1 million for special doors and windows in the South Nyack rental community, project officials confirmed.

Meanwhile, Salisbury Point in South Nyack and The Quay in Tarrytown continue to mull the offer; leaders from both groups met separately with the project team on Tuesday. The money being offered is part of a $20 million fund split between the state and Tappan Zee Constructors to pay for community improvements during construction of the new Tappan Zee Bridge.

When Tappan Zee Constructors announced the $4.2 million deal last week, leaders of Salisbury Point and The Quay slammed it for not addressing all their concerns. At The Quay, an 89-unit condominium complex, residents had asked for a pool enclosure and new fencing, in addition to the window and doors.

“It looks like it’s not going to happen and that’s very frustrating and depressing for us all,” said Alice Goldberg, president of the board.

Tuesday’s meeting with project officials focused on the types of windows Tappan Zee Constructors would pay for, she said. Goldberg said she is confident residents will reach an agreement with the builders.

The Quay’s proposal calls for windows with varying degrees of sound proofing based on the condo’s distance from the bridge construction.

Tappan Zee Constructors also denied Salisbury Point’s requests for security fencing and a pool cover. Thruway Authority spokesman Daniel Weiller criticized residents for expecting a pool dome.

“Some of the groups are asking for the project to pay for extras that have nothing to do with noise, such as a swimming pool dome, and it would be irresponsible to use the budget for the new bridge to pay for things like that,” he said in an email. “The goal is to find a fair and reasonable solution to help them install quality noise-reducing windows and doors, not to write a blank check.”

Goldberg disputed Weiller’s claim, arguing that “we have been cautious and very conservative” with the requests, adding that a cover for the pool would protect it from construction pollution.

The Quay’s residents, along with other Tarrytown and Rockland residents, are also considering designs for permanent noise barriers on the new span and around it. Officials have scheduled public meetings this week to explain options to Westchester and Rockland residents who received ballots in the mail.

Meetings will be held at 7 p.m. Wednesday at 303 S. Broadway in Tarrytown and 7 p.m. Thursday at the Best Western in Nyack.

http://www.lohud.com/article/20130625/NEWS/306250099?gcheck=1

 

Some property information provided by CoStar, Loopnet, HGAR, Yelp, Rand Commercial Services and other public sources.