September 2016 New NY Bridge Monthly Newsletter

September 2016
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives

The latest batch of aerial photography showcases the New NY Bridge project advancing across the Hudson River. The approaches in Westchester and Rockland continue to take shape with prefabricated road deck panels and enormous steel girder assemblies, installed by the I Lift NY super crane. At the main span, stay cables have begun to connect the burgeoning roadway to the four northern span towers, which each have reached nearly 400 feet in height.
The New NY Bridge project has become a symbol for what the state can accomplish. Watch the new twin-span crossing take shape during the past three years in this new time-lapse video. From steel girders to concrete towers, from piles to road deck, from shoreline to shoreline, the transformation has been amazing.

The New NY Bridge project is reaching new heights this summer as half of the eight iconic main span towers grow closer to completion. The four massive concrete structures on the northern bridge now stand nearly 400 feet above the Hudson River, just a few dozen feet away from their final 419-foot height.

As millions of pounds of steel and concrete are installed above the Hudson River, the New NY Bridge project’s surveyors are using lasers and other state-of-the-art technology to ensure that these materials are placed with pinpoint precision.
Frequently Asked Questions
Q:
Will there be a period when there is no Tappan Zee Bridge to cross?      
A:
No. The plan is to always have a bridge open to traffic during and after construction. Tappan Zee Constructors is currently building both new bridges just north of the existing Tappan Zee Bridge. The new northern span will be completed first and then all traffic will be temporarily shifted from the existing bridge onto the new northern span. The new northern span will be 96 feet wide with enough space for 8 temporary lanes and a center safety divider. Once the landings of the existing bridge are torn down and the pre-built southern span is connected to the landings, then half the traffic will be shifted off the northern span. In the final condition, each new span will have 4 general traffic lanes (all 12 feet wide), breakdown lanes, emergency access/bus lanes and the northern span will include a bike/pedestrian path.

TZ Bridge Tour _ Rand Commercial Day of Learning 7.18.2016

A view from the Hudson River is the best way to view the progress of the New NY Bridge . Rand Commercial agents spent the day navigating the waters and learning about the bridge building process. We lunched and saw the amazing progress that has been made and the daunting task that lies ahead.  A very special “thank you” to Dan Marcy of the New NY Bridge Project who guided us thru the site tour.

13654269_10210069582166827_1129219761141861526_n 13701136_1118892414844972_1520934281411212663_o 13767343_10209287171631571_2366547569189200652_o

13701136_1118892414844972_1520934281411212663_o 13692858_1118892408178306_4150119926181696754_o 13654269_10210069582166827_1129219761141861526_n

Continues Cashless Tolling System Now In Effect

The new NY bridge

Tarrytown Toll Plaza Demolition ContinuesCashless Tolling System Now In Effect

http://www.newnybridge.com/tarrytown-toll-plaza-demolition-continues-cashless-tolling-system-now-in-effect/Demolition of the deactivated toll plaza in Tarrytown continues as Tappan Zee Constructors, LLC (TZC) removes the toll plaza structures on the four right-most lanes of the southbound New York State Thruway (I-87/I-287) in preparation for the next shift in traffic, which is scheduled to occur in late May.

Survey work in the area will necessitate a midday lane closure, detailed in the chart below.

LANE CLOSURES NEAR THE TAPPAN ZEE BRIDGE

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Tue., 5/10 10 a.m. – One right lane 3 p.m. Southbound Thruway
near the former toll plaza

Noise Barrier Construction
TZC will continue constructing noise barriers along the Thruway in South Nyack next week. The work includes constructing noise barrier foundations and excavating soil along the southbound Thruway between the South Broadway bridge and River Road. After the foundations are established, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

TZC also will continue constructing foundation walls for the future highway and shared-use path along the northbound Thruway in South Nyack. The operation is scheduled to continue in the coming months.

Additional work includes:

  • Main span tower construction
  • Support for river-based work from the Rockland trestle
  • Rockland landing retaining walls
  • Survey inspections on the existing bridge
  • Westchester landings utility work
  • Girder assembly placement
  • Bridge road deck installation
  • Drainage structure installations

Boater Safety
Marine units are continuing patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. TZC will also be working in the area left and right of the main navigation channel under the main span of the bridge. TZC will begin working in the main navigation channel, which will result in partial or total closure of same. Additional temporary navigational lights have been installed on the existing bridge to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard permit requirements, as are all moorings, barges and other equipment. All Mariners should consult the latest USCG Local Notice to Mariners before transiting this area.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, construction site maps, can be found here at NewNYBridge.com. The page includes an interactive GPS map showing vessel locations on the Hudson River, detailing which vessels are stopped and which are in motion to a new location for recreational and commercial boaters to get current information on the very active construction zone. The vessel tracking map is for informational purposes and not intended for navigation.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visithttp://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

Tarrytown Toll Plaza Demolition Continues Cashless Tolling System Now In Effect

The New NY Bridge February Newsletter!

February 2016
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives
CLICK HERE FOR COMPLETE ISSUE!

Tappan Zee Constructors, LLC (TZC) recently installed the 650th concrete road deck panel for the westbound span. TZC began placing the panels in early October and is on track to install an additional 6,000 panels by year’s end. The work is occurring on top of recently-installed steel-blue girders, which continue to advance across the Hudson River.

Lanes Remain Open on TZ Bridge thru the Holiday week3end

For immediate release: Dec. 22, 2015

ALL LANES OF NEW YORK STATE THRUWAY (I-87/I-287) WILL REMAIN OPEN FROM THURSDAY, DEC. 24 THROUGH SUNDAY, DEC. 27 TO EASE HOLIDAY TRAVEL

All lanes of the New York State Thruway (I-87/I-287) will remain open from Thursday, Dec. 24 through Sunday, Dec. 27 to help New Yorkers reach their winter holiday destinations. The four-day, lane-closure-free period follows Governor Andrew M. Cuomo’s “Drivers First” initiative, which gives priority to motorists by ensuring that disruptions associated with highway and bridge projects are kept as minimal as possible.

While Tappan Zee Constructors, LLC (TZC) will continue working in several areas of the project during the week of Dec. 22, none of the work will impede traffic. No construction work is scheduled for Christmas Day, Friday, Dec. 25. Safety and security teams will remain on site throughout the holiday period.

All-Electronic Toll Collection Gantry Work
Construction of the project’s temporary all-electronic toll collection (AETC) system in Rockland will continue this week near the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to the southbound Thruway. The work will require overnight closures of two lanes of the southbound Thruway on Tuesday, Dec. 22 and Wednesday, Dec. 23. Specific lane closure times are detailed in the chart below.

Lane Closures Near the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Tue., 12/22 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Wed., 12/23 Southbound I-87/I-287
from exit 12 to exit 10
Wed., 12/23 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Thu., 12/24 Southbound
from exit 12 to exit 10

Installation of Noise Barriers in South Nyack
Next week will see continued construction of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road. The construction work involves drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Main span tower construction
  • Support for river-based work from the Rockland trestle
  • Rockland landing retaining walls
  • Survey inspections on the existing bridge
  • Westchester landings utility work
  • Girder assembly placement
  • Bridge road deck installation

Boater Safety
Marine Units are continuing patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, construction site maps, can be found here at NewNYBridge.com. The page includes an interactive GPS map showing vessel locations on the Hudson River, detailing which vessels are stopped and which are in motion to a new location for recreational and commercial boaters to get current information on the very active construction zone. The vessel tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

###

Tappan Zee Bridge Project Update

update

For immediate release: Dec. 3, 2015

INSTALLATION OF CONCRETE ROAD DECK CONTINUES
Overnight Closure of Southbound Exit 10 On-Ramp on Monday, Dec. 7

Tappan Zee Constructors, LLC (TZC) will begin installing bridge road deck segments near the Rockland shoreline on Thursday, Dec. 10. Project cranes will lift the prefabricated deck panels into place atop previously-installed structural steel girders.

Safely accomplishing the work will require reducing River Road/Piermont Avenue to one lane during weekdays starting on Thursday of next week. Flag persons will keep traffic moving by alternating the directional flow between north and south. TZC will also periodically hold traffic on River Road/Piermont Avenue for 6-minute intervals through Friday, Dec. 18 to enable the safe movement of deck panels and other materials.

Nearly 6,000 high-strength concrete deck panels will be installed for the new crossing’s approach spans. The panels are prefabricated at an off-site location and barged down river from the project’s Port of Coeymans facility in Albany County. TZC will continue installing the approach span deck sections across the river over the coming year.

All-Electronic Toll Collection Gantry Work
Construction of the project’s temporary all-electronic toll collection (AETC) system in Rockland will continue near the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to the southbound New York State Thruway (I-87/I-287). The work will necessitate closing the on-ramp during the overnight of Monday, Dec. 7. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the graphic below. This and other work require the specific lane and ramp closures detailed in the chart below.

Lane and Ramp Closures Near the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Thu., 12/3 8 p.m. – One left lane
9 p.m. – Two left lanes
5 a.m., Fri., 12/4 Southbound I-87/I-287
from exit 11 to exit 10
Fri., 12/4 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Sat., 12/5 Southbound
from exit 11 to exit 10
Mon., 12/7 7 p.m. – One right lane
8 p.m. – Two right lanes
5 a.m., Tue., 12/8 Southbound
from exit 12 to exit 10
Mon., 12/7 9 p.m. – Ramp closure 5 a.m., Tue., 12/8 Southbound
exit 10 on-ramp
Wed., 12/9 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Thu., 12/10 Southbound
from exit 12 to exit 10
Thu., 12/10 8 p.m. – One left lane
9 p.m. – Two left lanes
5 a.m., Fri., 12/11 Southbound
from exit 12 to exit 10
Fri., 12/11 8 p.m. – One left lane
9 p.m. – Two left lanes
5 a.m., Sat., 12/12 Southbound
from exit 12 to exit 10

Steel Girder Installation
Next week, TZC will continue installing structural steel girder assemblies from the new bridge’s Westchester landing in Tarrytown. The assemblies will connect the future westbound span’s on-land abutment to the first offshore support pier in the Hudson River. TZC is installing the girders by literally pushing them west over the Metro-North Railroad Hudson Line’s tracks toward the first pier in the river, as seen in this animation. As the operation progresses, additional girders are being connected to the assembly and pushed farther westward. TZC is closely coordinating the effort with Metro-North Railroad, ensuring that the operation maximizes safety for both workers and the public and minimizes impacts to rail service.

The remaining work over the Metro-North tracks will occur during a Friday overnight later this month, with the entire operation anticipated to conclude by the end of the year. Metro-North has adjusted its schedule slightly to allow the work to be completed. TZC will suspend construction activities when commuter trains pass through the area, resuming when given the “all clear” instruction by Metro-North.

The I Lift NY super crane will continue placing larger girder assemblies across the river, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

Tower Construction
Construction will continue on the new bridge’s iconic towers, which will eventually rise 419 feet above the river. Innovative self-climbing jump forms enable TZC workers to build the towers in segments that progressively “jump” up from the foundations to their full height. Within the jump forms, workers assemble steel reinforcement cages that are then encased in concrete, one segment atop the previous one and so on. Eight towers will be constructed on the project’s football-field-long main span pile caps over the coming year, as seen in this animation.

Installation of Noise Barriers in South Nyack
Next week will see continued construction of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road. The construction work involves drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Support for river-based work from the Rockland trestle
  • Rockland landing retaining walls
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
Marine Units are continuing patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, construction site maps, can be found here at NewNYBridge.com. The page includes an interactive GPS map showing vessel locations on the Hudson River, detailing which vessels are stopped and which are in motion to a new location for recreational and commercial boaters to get current information on the very active construction zone. The vessel tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

###

The New NY Bridge November 2015 Newsletter

November 2015
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

As more and more piers are connected by steel-blue girder assemblies, the New NY Bridge project’s iconic towers continue to advance skyward.

As the summer turns to fall in the Lower Hudson Valley, progress continues to march forward on the New NY Bridge project. More and more of the high strength structural steel-blue girder assemblies are being placed across the Hudson River by Tappan Zee Constructors, LLC (TZC), largely with the help of the massive I Lift NY super crane. At both shorelines, however-where shallow waters prevent the use of the super crane-alternate methods were necessary, including the use of construction platforms. The Westchester landing posed a further shoreline challenge: how to safely install the girders over the Metro-North Railroad Hudson Line tracks?

While most of the new bridge’s steel-blue girder assemblies are being placed across the Hudson River with the barge-based I Lift NY super crane, the location from the Westchester landing to the first pier in the river is inaccessible to the monumental machine. Tappan Zee Constructors, LLC is using an innovative yet simple alternative method to install the girders in this area, as detailed in this video.

New NY Bridge fans looking for a firsthand view of construction from the Rockland shoreline now have a “front row seat” to the action. Nyack’s new fishing pier at Memorial Park is now open and offers spectators a sweeping view of the Hudson River and the bustling project site.

After successfully installing structural steel girders between the Westchester abutment and a nearby pier, Tappan Zee Constructors, LLC (TZC) moved forward with the next stage of operations this week. In a remarkable feat of engineering, crews carefully pushed the massive steel-blue materials further west, over the Metro-North Railroad Hudson Line and toward the next pier in the Hudson River.
Frequently Asked Questions
Q:
Why does the current Tappan Zee Bridge need to be replaced? 
A:
The Governor Malcolm Wilson Tappan Zee Bridge opened to traffic in 1955 and is a vital artery for residents, commuters, travelers, and commercial traffic. The bridge, which was designed to carry up to 100,000 vehicles per day, currently handles an average of 138,000 daily, and traffic congestion and delays are regular occurrences. Heavy traffic, narrow lanes and the lack of emergency shoulders contribute to congestion and frustration for motorists and can create unsafe driving conditions. As a result, the bridge has twice the average accident rate per mile as the rest of the 574-mile Thruway system. In recent years, hundreds of millions of dollars have been spent to maintain and repair the bridge. If the current bridge were not being replaced, the state would need to spend an additional $3 to $4 billion over the next 20 years to ensure its structural integrity.

BRIDGE BUILDERS PREPARE FOR POSSIBLE HURRICANE

update

For immediate release: Oct. 1, 2015

BRIDGE BUILDERS PREPARE FOR POSSIBLE HURRICANE
Marine Construction Work Temporarily Halted for Safety

Tappan Zee Constructors, LLC (TZC) is preparing for the potential effects of Hurricane Joaquin, which forecasters say could hit the Hudson Valley region in the coming days. In advance of the storm’s approach, TZC is implementing its storm preparedness plans, temporarily halting marine construction operations and the movement of construction materials, while securing the job site to prevent possible storm damage. By closely monitoring weather conditions and taking appropriate action in advance, TZC will ensure both worker and public safety while minimizing any potential storm-related downtime on the project.

TZC’s inclement weather preparation protocols include having tug boats on the water at all times, inspecting and adjusting all mooring lines, inspecting crane barges and securing all equipment, moving the large majority of cranes to shallow water moorings and taking all smaller crew boats out of the water. Additionally throughout every storm, TZC uses video and GPS to monitor the entire fleet of project vessels from its security operations center.

Governor Andrew M. Cuomo today activated the State Emergency Operations Center in Albany to monitor severe weather that is anticipated to impact southern parts of New York State beginning today and potentially lasting through this weekend.
Additional New York State storm preparedness updates can be found here:
http://www.governor.ny.gov/news

The following construction operations planned for next week will proceed as weather allows:

Steel Girder Installation
TZC will continue installing steel girders near the South Nyack shoreline. Safely accomplishing the work will require reducing River Road to one lane during weekdays between 6 a.m. to 5 p.m. Flag persons will keep traffic moving by alternating the directional flow between north and south.

Smaller girder sections will be lifted into place by cranes from the Rockland trestle. Ironworkers then bolt together the girders and cross beams that will support the new bridge’s concrete road deck. In deeper water, the I Lift NY super crane will continue placing larger girders, averaging two placements a week.

A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

All-Electronic Toll Collection Gantry Work
Construction of the project’s temporary all-electronic toll collection (AETC) system in Rockland County will continue next week with the installation of an overhead gantry above the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to southbound New York State Thruway (I-87/I-287). The work necessitates overnight double-lane closures throughout the coming week. Specific lane closures are listed in the chart below.

 

Lane Closures Near the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Mon., 10/5 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Tue., 10/6 Southbound I-87/I-287
from exits 12 to 10
Tue., 10/6 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Wed., 10/7 Southbound
from exits 12 to 10
Wed., 10/7 8 p.m. – One left lane
9 p.m. – Two left lanes
6 a.m., Thu., 10/8 Southbound
from exits 12 to 10
Thu., 10/8 8 p.m. – One right lane
9 p.m. – Two right lanes
6 a.m., Fri., 10/9 Southbound
from exits 12 to 10
Fri., 10/9 8 p.m. – One right lane
9 p.m. – Two right lanes
6 a.m., Sat., 10/10 Southbound
from exits 12 to 10

Tower Construction
The new bridge’s iconic towers will continue rising toward their ultimate height of 419 feet, aided by self-climbing jump forms. The state-of-the-art forms enable TZC workers to build the towers in segments that progressively “jump” up from the foundations to their full height. Within the jump forms, workers assemble steel reinforcement cages that are then encased in concrete, one segment atop the previous one and so on. Eight towers will be constructed on the project’s football-field-long main span pile caps over the coming year, as seen in this animation.

Installation of Noise Barriers in South Nyack
Next week will see continued installation of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road in South Nyack. The work involves drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
Westchester and Rockland Marine Units are continuing extensive patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visithttp://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

###

Steel Girder Installation Continues

For immediate release: August 20, 2015

STEEL GIRDER INSTALLATION CONTINUES NEAR THE ROCKLAND LANDING

Tappan Zee Constructors, LLC (TZC) will continue installing structural steel girders for the New NY Bridge project next week. Smaller girder sections will be lifted into place by cranes from the Rockland trestle near the South Nyack shoreline. Local ironworkers will then bolt together the steel blue girders and cross beams that will support the new bridge’s concrete road deck.

In addition, the I Lift NY super crane will continue placing larger girder assemblies next week and beyond, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

Two northbound lanes of the New York State Thruway (I-87/I-287) will be closed during the overnights of Monday, August 24 and Tuesday, August 25 across the existing Tappan Zee Bridge to facilitate surveying efforts.

I-287/I-87 Lane and Ramp Closures on the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Mon., 8/24 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Tue., 8/25 Northbound Across the
Tappan Zee Bridge
Tue., 8/25 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Wed., 8/26 Northbound Across the
Tappan Zee Bridge

Dredging Operations Continue
TZC will continue the second stage of dredging operations near the Westchester shoreline as part of the preparation for removing the existing bridge and completing the landing of the new southern span. Dredging is allowed during a three-month period from August 1 to October 31 in specified locations and will be conducted 24/7 to complete the required dredging during the short window of time. The window was established to avoid impacting migration and spawning patterns of endangered sturgeon and other fish species.

Installation of Noise Barriers in South Nyack
Next week also will see continued installation of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road in S. Nyack. The work will involve drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Pile cap foundation construction
  • Placement of Steel Girder assemblies
  • Dredging
  • Main span foundation construction
  • Landing abutment concrete work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
During the summer months, Westchester and Rockland Marine Units will add extra patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

 

TZ Bridge Traffic Updates For the Week of June 15, 2015

update

For immediate release: June 12, 2015

CONSTRUCTION STARTING ON NOISE BARRIERS ALONG SOUTHBOUND NEW YORK STATE THRUWAY (I-87/I-287) IN SOUTH NYACK

After months of preparation, crews will begin installing foundations for noise barriers along the southbound New York State Thruway (I-87/I-287) between the South Broadway bridge and River Road. The work will involve drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Continued Overnight Triple-Lane Closures of Southbound Thruway
Weekday overnight triple-lane closures of the southbound Thruway will occur from Monday night, June 15 through Saturday morning, June 20. Closures will start at 8 p.m. with the closing of one lane near exit 11 (Nyack – South Nyack – US Route 9W) to the Tappan Zee Bridge, followed by a second lane at 9 p.m. and a third at 11 p.m. All lanes will reopen by 6 a.m. the following weekday. The closures on Friday, June 19 will start with a single lane at 9 p.m., a second lane at 11 p.m. and a third at 11:59 p.m. All lanes will reopen by 8 a.m., Saturday, June 20.

Triple-lane closures of the southbound Thruway in the same area also are planned for the overnight of Saturday, June 13, with a single lane closing at 7 p.m., followed by a second lane at 11 p.m. and a third at 1 a.m., Sunday, June 14. All lanes will reopen by 11 a.m., Sunday, June 14.

All planned work is subject to postponement due to weather conditions.

Single-Lane Closures of Northbound Thruway During Morning Commuting Periods on June 18 and 19
Single-lane closures of the northbound Thruway will occur on Thursday, June 18 and Friday, June 19. The closures will start at 5 a.m. near the Tappan Zee Bridge to exit 11 (Nyack – South Nyack – US Route 9W). The lane will reopen by 2 p.m. both days.

River Road in South Nyack
River Road utility work will continue during the week of June 15. The work may require reducing River Road to one lane at times. TZC flag persons will direct traffic as needed and additional signage as well as other safety measures will be in place.

Foundation Work on the New Bridge
Marine crews are continuing work on bridge foundations next week by placing reinforcing steel and concrete in the piles, main span pile caps and approach span pile caps. The high-strength concrete is made on site by the project’s floating batch plants. Teams also will erect formwork for the cast-in-place pier columns, which eventually will support the new bridge’s road deck.

Crews also will continue working on the bridge’s landings at the Rockland and Westchester shorelines. The abutments, comprised of steel and concrete, will serve as strong bases where the new crossing meets the landside roadway.

Construction of pier 1 located near River Road in South Nyack will continue with the installation of sheet piles. The sheet piles support the surrounding soil while the foundation for the new bridge pier is constructed. Pile driving is restricted to 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday. TZC is implementing noise-reducing measures, including sound-absorptive temporary noise barriers, to protect nearby residents. The project’s environmental compliance team will be on site to monitor noise levels during the operation.

Additionally, TZC will continue concrete placement for bridge foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and is delivered by truck to the Rockland trestle located off the Thruway’s southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.

Additional work includes:

  • Pile cap foundation construction
  • Main span foundation construction
  • Landing abutment concrete work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester Landings utility work

Boater Safety
During the summer months, Westchester and Rockland Marine Units will add extra patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.
Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

TZ Bridge Traffic Update

update

EXIT 10 ON-RAMP TO SOUTHBOUND NEW YORK STATE THRUWAY (I-87/I-287) CLOSED TONIGHT, FRIDAY, MAY 29
Triple-Lane Closures, Periodic Traffic Stops of Southbound Thruway in South Nyack During Overnights the Week of June 1

The exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to the southbound New York State Thruway (I-87/I-287) will be closed from 9 p.m., Friday, May 29 to 5 a.m., Saturday, May 30. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the following graphic. The closure will allow Tappan Zee Constructors, LLC (TZC) to safely move equipment needed to place concrete slabs for a new temporary all-electronic toll collection system that will be employed until a permanent system is constructed in the location of the current toll plaza in Tarrytown.

Additionally, weekday overnight triple-lane closures of the southbound Thruway will occur from Monday night, June 1 through Saturday morning, June 6. Closures will start at 7 p.m. with the closing of one lane near exit 11 (Nyack – South Nyack – US Route 9W) to the Tappan Zee Bridge, followed by a second lane at 9 p.m. and a third at 10:30 p.m. All lanes will reopen by 6 a.m. the following weekday or 8 a.m. the following Saturday.

Additionally, a double-lane closure is planned for the overnight of Saturday, May 30, with a single lane closing at 7 p.m., followed by a second lane at 11 p.m. The lanes will reopen by 10 a.m., Sunday, May 31.

The lane closures are necessary to allow TZC to modify the highway for the temporary all-electronic toll collection system.

During the weekday and weekend overnight closures, at least one lane will remain open at all times, except during periodic traffic stops lasting up to 10 minutes of all four lanes of the southbound Thruway near exit 11 (Nyack – South Nyack – US Route 9W), which will occur between 8 p.m. and 5 a.m. during the overnights of Thursday, June 4 and Friday, June 5. To ensure the public’s safety, the New York State Police will stop and hold all traffic approaching the area immediately before the traffic stops go into effect. Motorists will be permitted to enter the Thruway from all ramps during the traffic stops. The complete traffic stops are necessary to move equipment from the right shoulder to the left shoulder.

All planned work is subject to postponement due to weather conditions.

River Road in South Nyack
River Road utility work will continue during the week of June 1. The work may require reducing River Road to one lane at times. TZC flag persons will direct traffic as needed and additional signage as well as other safety measures will be in place.

Foundation Work on the New Bridge
Marine crews will continue working on the foundations for the new bridge next week by placing reinforcing steel and concrete in the piles, main span pile caps and approach span pile caps. The high-strength concrete is made on site by the project’s floating batch plants. Teams also will erect formwork for the cast-in-place pier columns, which eventually will support the new bridge’s road deck.

While the current phase of pile driving is anticipated to end soon, pile driving will continue next week. Pile driving is restricted to 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.

Crews also will continue working on the bridge’s landings at the Rockland and Westchester shorelines. The abutments, comprised of steel and concrete, will serve as strong bases where the new crossing meets the landside roadway.

Construction of pier 1 located near River Road in South Nyack will continue with the installation of sheet piles. The sheet piles support the surrounding soil while the foundation for the new bridge pier is constructed. TZC is implementing noise-reducing measures, including sound-absorptive temporary noise barriers, to protect nearby residents. The project’s environmental compliance team will be on site to monitor noise levels during the operation.

Additionally, TZC will continue concrete placement for bridge foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and is delivered by truck to the Rockland trestle located off the Thruway’s southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.

Additional work includes:

  • Pile cap foundation construction
  • Main span foundation construction
  • Landing abutment concrete work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester Landings utility work

Boater Safety
During the summer months, Westchester and Rockland Marine Units will add extra overnight patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

TAPPAN ZEE CONSTRUCTORS TAKES EXTENSIVE NOISE MITIGATION MEASURES

For immediate release: May 18, 2015

TAPPAN ZEE CONSTRUCTORS TAKES EXTENSIVE NOISE MITIGATION MEASURES FOR SHEET PILE DRIVING AT PIER 1 IN ROCKLAND COUNTY

For the past week, Tappan Zee Constructors, LLC (TZC) has been installing and testing extensive noise mitigation measures in an effort to mitigate noise from vibratory sheet pile driving at Pier 1 off the Rockland shoreline. These efforts have successfully reduced the noise levels by more than 10 decibels. This work is expected to last 1-2 weeks with limited work hours and no sheet pile driving at Pier 1 on Saturdays, Sundays or Memorial Day Monday.

To minimize the effect on the local community, TZC will:

  • Limit the sheet pile driving at Pier 1 to the hours of 8AM-4PM Monday-Friday (none allowed on Saturday, Sunday or Memorial Day Monday)
  • Drive no longer than 30 minutes per hour
  • Use a noise shroud over the vibratory hammer
  • Erect a 40-ft wide x 30-ft tall temporary noise barrier between the work and South Nyack residents
  • Place noise barrier material over the previously driven sheets to reduce noise/vibration levels
  • Proactively reach out to the Village of South Nyack and local homeowners to inform them of the mitigation measures

Noise levels at sensitive receptors and nearby homes are expected to remain within the allowable levels listed in the New NY Bridge project’s Final Environmental Impact Statement as shown in the table below:

To view the New NY Bridge project environmental monitors that are updated every minute of every day go to www.NewNYBridge.com.

table

 

 

 

 

 

Help Name the Falcon Chicks!

For immediate release: May 20, 2015

CAST YOUR VOTES TO NAME THE TAPPAN ZEE FALCON CHICKS!
Voting Open Until 6 p.m., Wednesday, May 27

The New NY Bridge project invites you to vote in a week-long poll to name the recently-hatched Tappan Zee falcons—called eyases (“EYE-a-sez”)—that are nesting with their parents atop the existing bridge. The 10 suggested names are the product of the imaginations of Rockland and Westchester elementary school students.

The chicks, two females and one male, were recently tagged with identifying bands by the New York State Department of Environmental Conservation (DEC). The bands, placed on the fledglings’ ankles, will allow the project team and DEC to identify them and track their health and migration habits.

The Name-the-Falcons poll will remain open until 6 p.m., Wednesday, May 27. Names that garner the most votes will be announced shortly thereafter and the schools that suggested the winning names will be recognized.

Watch this spring and summer as the chicks become flying adult falcons via the 24/7 FalconCam on our website NewNYBridge.com.

The Tappan Zee Bridge falcon nest box is maintained by the New York State Thruway Authority. The New NY Bridge will include a new peregrine falcon nest box high atop its towers.

Please note: The falcons are wild birds and their behaviors reflect what happens in nature. Some of their actions may be unpleasant to watch and it is possible that some of the fledglings may not survive into adulthood.

Learn more about the Tappan Zee falcons.

 

NEW NY Bridge 2015 Annual Public Meetings

The new NY bridge

You are invited to attend the New NY Bridge 2015 Annual Public Meetings, hosted by Brian Conybeare, Special Advisor to the Governor for the project. Members of the project team will discuss the remarkable progress being made, preview upcoming construction activities, and unveil some exciting new design features. Attendees will also be able to participate in a Q&A session with project leaders from the New York State Thruway Authority and Tappan Zee Constructors

Please attend one of the annual meetings listed below for more information:

 

Westchester County

 

Tuesday, May 12, 2015

6:30 pm – 8:00 pm

 

Washington Irving Middle School  

103 S. Broadway

Tarrytown, NY 10591

 

Rockland County

 

Thursday, May 14, 2015

6:30 pm – 8:00 pm

 

Nyack High School 

360 Christian Herald Rd.

Nyack, NY 10960

Thruway Authority Discussions with South Nyack Making Progress on Bike/Pedestrian Path Parking

For immediate release: April 6, 2015
Contact: Brian Conybeare 845-705-3302

Thruway Authority Discussions with South Nyack Making Progress on Bike/Pedestrian Path Parking

New York State Thruway Authority Acting Executive Director Robert Megna today announced that renewed discussions with the Village of South Nyack on parking options for the New NY Bridge project’s shared-use bike/pedestrian path (SUP) in Rockland County are progressing.

The Thruway Authority and Federal Highway Administration are undertaking an Environmental Assessment to study the parking options generated by the public and other stakeholders.  Formal public hearings will be held as part of the process, once a draft Environmental Assessment is complete.

“The renewed talks with South Nyack are making substantial progress,” said Acting Thruway Authority Executive Director Robert Megna. “We want to continue working proactively with Mayor Bonnie Christian and the South Nyack Tappan Zee Bridge Task Force to find solutions for the shared-use pathparking areas and connectivity to the community that will work for all the parties involved while protecting New York taxpayers and tollpayers at the same time.”

“We continue working together on the location of the shared-use path and hopefully we will be able to come to an agreement that benefits the residents of South Nyack, the Thruway Authority and the people who will use the path in the future,” said South Nyack Mayor Bonnie Christian.

The New NY Bridge Community Benefits Program has approved a $250,000 grant for the Village of S. Nyack to study the feasibility of redesigning and redeveloping interchange 10 on I-87/287.  The village is now considering several proposals from engineering firms to design and recommend economically sustainable redevelopment concepts.

The Thruway Authority and the village have agreed to continue working on these issues together as the New NY Bridge project moves forward.

For more information on the SUP parking options currently being studied in both S. Nyack and Tarrytown: http://www.newnybridge.com/documents/sup/index.html

The New NY Bridge April 2015 Newsletter

April 2015
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

Springing into Action:

Remobilizing on the Hudson River


As the Lower Hudson Valley thaws out from a particularly punishing winter, the hardworking men and women of the New NY Bridge project are remobilizing on the river.

READ MORE

While frigid weather conditions have limited river work in recent weeks, Tappan Zee Constructors, LLC (TZC) has been forging ahead with the parts of the bridge that anchor it to the land: the abutments. Located at each end of the crossing, the stout abutments will serve as solid foundations for the bridge and the land-side highway.

 

READ MORE

On Feb. 28, the New NY Bridge (NNYB) project educational outreach team met with Girl Scout troops from Greenburgh and Elmsford to promote careers in science, technology, engineering and mathematics (STEM).

 

 READ MORE

The construction of river crossings present an engineering challenge: how to build in the water?.

 

 READ MORE

Frequently Asked Questions
Q:
Who is the Project Director, and what are his responsibilities?
A:
Peter Sanderson was hired by the Thruway Authority to serve as project director for the New NY Bridge. Sanderson leads a team of state employees, and private-sector design and construction experts, with the goal of completing the new bridge on budget and on time. Among his past accomplishments, Mr. Sanderson was the lead for the I-35 bridge replacement project in Minnesota in 2007. Under his guidance, the I-35 project, projected to take 14 months, was completed in just 11 months.

 

Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates

TZ Bridge Project Update and Lane Closures for the Week of March 23, 2015

FLOATING BATCH PLANTS RETURN TO WORK ON THE NEW NY BRIDGE PROJECT
Triple-Lane Closure on Northbound New York State Thruway (I-87/I-287) During Overnight of Wednesday, Mar. 25

Tappan Zee Constructors, LLC’s (TZC) two floating concrete batch plants recently returned to the work site, passed the required testing and soon will begin pumping concrete. The batch plants were taken out of service in December after a silo failed.

The concrete plants move from location to location on the river, providing high-quality concrete where it is needed to build the New NY Bridge project. Their resumption of service will reduce the number of concrete trucks using local roads.

The following lane and exit closures are planned for next week:

Three left lanes of the northbound Thruway (I-87/I-287) will be closed from exit 9 (Tarrytown – Sleepy Hollow – NY Route 9) to exit 10 (Nyack – South Nyack – Route 9W), and including the Tappan Zee Bridge, from 9 p.m., Wednesday, Mar. 25 to 4:30 a.m., Thursday, Mar. 26. One lane will remain open during the closure. The closures are necessary to accommodate road-striping work.

Additionally, road striping will require the closure of the two left (35 mph) E-ZPass lanes at the southbound Thruway toll plaza in Tarrytown from 10 p.m. Friday, Mar. 27 to 5 a.m., Saturday, Mar. 28. The work also will necessitate the closure of the southbound exit 9 off-ramp to Route 9 from 10 p.m., Friday, Mar. 28 to 5 a.m., Saturday, Mar. 28. Traffic that would otherwise use exit 9 will be detoured to exit 8A, as shown below:

map

Turn-by-turn directions for southbound exit 9 closure detour:

  1. Exit onto the exit 8A off-ramp;
  2. At the end of the long ramp, turn right on westbound Route 119/White Plains Road;
  3. Enter westbound I-287, which merges with northbound I-87;
  4. Exit onto the exit 9 off-ramp;
  5. Turn left onto westbound Route 119/White Plains Road; and
  6. Turn left or right on Route 9, depending on your destination. 

Preparations for the Temporary All Electronic Toll Collection system in South Nyack near exit 10 will require a single right-lane closure from 10 a.m. to 3 p.m. on Monday, March 23 and Tuesday, March 24.

Marine operations continue to gear up following the winter shutdown, with crews installing reinforcing steel (rebar) in the main span pile caps and the precast approach span pile caps.

With only a small percentage of piles left to install, pile driving operations will continue next week. The periodic pile driving is restricted to 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.

Crews also will continue working on the bridge’s landings at the Rockland and Westchester shorelines. The abutments, comprised of steel and concrete, will serve as strong bases where the new crossing meets the landside roadway.

TZC will continue limited concrete placement for foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and delivered by truck to the Rockland trestle located off the New York State Thruway’s (I-87/I-287) southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.

Additional work includes:

  • Pile cap foundation construction
  • Main span foundation construction
  • Landing abutment concrete work
  • River Road utility work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge

Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.

March 2015 New NY Bridge Project Monthly Newsletter

March 2015
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

Falcons Swoop In:

See Tappan Zee Peregrines Live Via Webcam


Coming to you live from high above the Hudson River are the fastest members of the animal kingdom! The Tappan Zee Bridge’s peregrine falcons have returned to their man-made nest box to prepare for the nesting season and can be viewed on the project’s “FalconCam.”

READ MORE

Long before the first foundations of the New NY Bridge project were installed, Tappan Zee Constructors, LLC (TZC) engaged experts at HDR Inc., an architectural and engineering firm with offices in Pearl River, NY, to build the new crossing in a virtual world.

 

READ MORE

Members of the New NY Bridge outreach team recently met with students at Anne M. Dorner Middle School in Ossining on the eve of the students’ entry in the 2015 Engineering Encounters Bridge Design Contest, a national competition that provides students with a realistic and engaging introduction to engineering.

 

 READ MORE

Located at the intersection of the active Hudson River and the busy New York State Thruway, the New NY Bridge project is passed by more than 138,000 vehicles every day. Building America’s largest bridge project in this bustling area compelled the project team to make security one of its top priorities. To keep the public and project safe, Tappan Zee Constructors, LLC (TZC) engaged one of the nation’s leading private security organizations, AlliedBarton Security Services and its White Plains office.

 

 READ MORE

As support columns for the New NY Bridge rise across the Hudson River, workers at an upstate facility are hard at work preparing critical elements for the project’s next stage of construction. A few miles south of Albany, a major Tappan Zee Constructors, LLC (TZC) staging yard at the Port of Coeymans (pronounced KWEE-mans) will be the assembly site for hundreds of enormous steel girders that will connect the columns and support the new crossing’s road deck.

 

 READ MORE

Frequently Asked Questions
Q:
What does “design-build” mean?
A:
Design-build is an alternative to the traditional construction method of “design-bid-build.” In a design-bid-build arrangement, the state would issue one contract to design the bridge and all of its components. Then, bids for the construction would be solicited. Under a design-build contract, the contractor that builds the structure is also responsible for the development and integrity of the design. If construction cost overruns arise relating to the design, they are the responsibility of the contactor, not taxpayers or toll payers. Design changes under the old design-bid-build system often led to past project delays and cost overruns that had to be borne by taxpayers and toll payers. Design-build shifts most of the risk to the contractor.
Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates
HOW TO GET INVOLVED
Follow Us on Twitter

@NewNYBridge

Call the Project Hotline

1-855-TZBRIDGE

(1-855-892-7434)

Community Outreach Centers

Westchester: 2 N. Broadway, Tarrytown, NY

Rockland: 142 Main Street, Nyack, NY

Mon-Fri: 11am-7pm | Sat-Sun: 11am-4pm

Visit the Project Website
Email Us
Construction Viewing Platform

Scenic Hudson RiverWalk Park, Tarrytown, NY

Next to the Tarrytown Senior Center at
240 West Main St.

©2015 New York State Thruway Authority

Falcons Swoop In See Tappan Zee Peregrines Live Via Webcam

Falcons021815

 

Coming to you live from high above the Hudson River are the fastest members of the animal kingdom! The Tappan Zee Bridge’s peregrine falcons have returned to their man-made nest box to prepare for the nesting season and can be viewed on the project’s “FalconCam.”

Installed in the steel super structure of the existing bridge, the nest box is equipped with a live, 24/7 FalconCam, accessible here.

The remote FalconCam, located outside the nest box, provides close-up views of the lives of these amazing migratory raptors, which recently came back to reproduce. Peregrine eggs typically are laid in February and March and chicks hatch approximately one month later. Viewers may be able to watch as the chicks peck their way out of their eggs and are then fed and cared for by their parents.

As construction on the New NY Bridge project continues, a 100-foot buffer area is in place to help protect the falcons during their nesting period.

Maintained and monitored by the New York State Thruway Authority, the nest box evetappan zeentually will be relocated to a new perch in the towers of the new bridge.

Learn more about the Tappan Zee falcons.

Project Update: Winter Weather Limits Operations

WINTER WEATHER CONTINUES TO LIMIT OPERATIONS AT NEW NY BRIDGE PROJECT SITE DURING THE WEEK OF FEBRUARY 9

Freezing temperatures and winter weather in the Hudson Valley continue to limit operations at the New NY Bridge project site. Tappan Zee Constructors, LLC (TZC) has included a two-month winter shutdown in its schedule to account for winter weather conditions.

During the week of February 9, TZC will continue limited operations.

TZC’s inclement weather preparation protocols include having tug boats on the water at all times, inspecting and adjusting all mooring lines, inspecting crane barges and securing all equipment, moving the large majority of cranes to shallow water moorings and taking all smaller crew boats out of the water. Additionally throughout every storm, TZC uses video and GPS to monitor the entire fleet of project vessels from its security operations center.

As weather permits, landside crews are working to assemble formwork that will shape the bridge’s landings on the Rockland and Westchester shorelines. The abutments, which will be made of steel, concrete, will serve as strong bases where the new crossing meets the landside roadways.

Pile Driving and Other Construction Activity

As much as allowed by weather conditions, construction will continue in the Hudson River, where crews are placing the foundations of the new bridge. The work includes pile driving from 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.

TZC also will continue limited concrete placement for foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and delivered by truck to the Rockland trestle located off the New York State Thruway (I-87/I-287) southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp.  The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.

Westchester landing foundation operations continue as crews work to construct the land based piers and abutment for the new bridge.

Additional work includes:

  • Pile cap foundation construction
  • Main span foundation construction
  • River Road utility work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge

Boater Safety

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.

Building a Landmark

NYS Thruway Lane Closures for Jan 28-29,2015

For immediate release: January 23, 2015 

TWO LANES OF SOUTHBOUND NEW YORK STATE THRUWAY (I-87/I-287) CLOSED OVERNIGHT WEDNESDAY JAN. 28 AND THURSDAY JAN. 29

Two lanes of the southbound New York State Thruway (I-87/I-287) will be closed between The Tappan Zee Bridge Toll Plaza in Tarrytown and exit 8A (Elmsford – NY Route 119 – Saw Mill River Parkway North) during the overnights of Tuesday, January 27 and Wednesday, January 28. The two overnight closures will occur between 7 p.m. and 5 a.m. and are necessary to accommodate work on an electronic message sign facility.

Bridge Abutment Work Continues

Tappan Zee Constructors, LLC (TZC) will continue assembling formwork that will shape the bridge’s landing on the Rockland and Westchester shorelines. The abutments, which will be made of steel, concrete and earth, will serve as strong bases for where the new crossing meets the landside roadway.

Pile Driving and Other Construction Activity
Construction will continue in the Hudson River as crews place the foundations of the new bridge. Work will include pile driving from 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.

TZC will continue limited concrete placement for foundations near the South Nyack shoreline. In the absence of the project’s floating batch plants, which were temporarily taken out of service last month after a silo failed, the concrete for this work will be acquired from local concrete suppliers and will be delivered by truck to the Rockland trestle located off of the New York State Thruway (I-87/I-287) southbound access ramp. Trucks will exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.

Westchester landing foundation operations continue as crews work to construct the land based piers and abutment for the new bridge.

  • Additional work includes:
  • Pile cap foundation construction
  • Main span foundation construction
  • River Road utility work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on existing bridge

Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.

New Year of Construction Looking Ahead to 2015

New Year of Construction
Looking Ahead to 2015

December 31, 2014 |

With a fleet of approximately 130 floating cranes, barges, tugboats and other vessels working on the New NY Bridge, construction continues to move forward. The coming year will see the completion of the new crossing’s foundations and an increasing number of bridge piers across the Hudson River.

Early in 2015, the I Lift NY super crane will make the first of what will be hundreds of heavy lifts by installing a 600-ton approach span pile cap, a task that no other crane on the job can handle. Next year will also bring the completion of phase one of pile driving (phase two is scheduled for 2017, after the landings of existing bridge are removed); the installation of numerous precast approach-span pile capsby the project’s floating cranes; and the completion of the main-span pile caps, which will support the soaring 419-foot main span towers. The bridge also will begin to take its finished form, as segments of the road deck are mounted on the steel girders that connect the approach span piers. With the placement of thousands of tons of concrete and steel in the coming year, the project is steadily progressing towards completion in 2018.

Individuals keen on observing progress of the New NY Bridge project firsthand are invited to visit the recently opened Westchester viewing platform in Tarrytown’s Scenic Hudson RiverWalk Park. The platform is equipped with telescopes and a spotter’s guide, which describes the wide array of equipment on the river. The Rockland viewing platform, which will be situated in Nyack’s Memorial Park, is under development and is slated to open in early 2015. The project’s day-by-day progress also can be tracked from the comfort of home, thanks to construction cameras situated at various vantage points on and around the project site and accessible from the project website.

Here’s to another year of progress on this historic project in 2015!

http://www.newnybridgegallery.com/updates/new-year-of-constructionlooking-ahead-to-2015/

 

 

 

 

Traffic Updates for the Thanksgiving Holiday!

THREE LANES OF NORTHBOUND NEW YORK STATE THRUWAY (I-87/I-287) TO BE CLOSED OVERNIGHT MONDAY
All Lanes Remain Open from Wednesday, Nov. 25 to Monday, Dec. 1
for Thanksgiving Travel

During the overnight of Monday, Nov. 24, three lanes of the northbound New York State Thruway (I-87/ I-287) will be closed to accommodate restriping (i.e., applying lane markers) and a minor shifting of lanes. The triple-lane closure will be in effect from 11 p.m., Monday, Nov. 24 to 4:30 a.m., Tuesday, Nov. 25 and will extend nearly five miles between exit 9 (Tarrytown – Sleepy Hollow – US Route 9) and exit 10 (Nyack – South Nyack – US Route 9W). One northbound travel lane will remain open throughout this period. The operation also will require the closure of the exit 10 off ramp from 10 p.m., Monday, Nov. 24 to 4:30 a.m., Tuesday, Nov. 25. Exiting motorists will be directed to use exit 11 and follow signs to Route 9W and Route 59. In the event of rain or snow on Monday the above closures will move to Tuesday, Nov. 25.

No Thruway lane closures will occur from Wednesday, Nov. 26 to Monday, Dec. 1 in observance of the busy Thanksgiving holiday travel season as part of Governor Cuomo’s Drivers First Initiative, which focuses on the convenience of motorists to ensure that disruptions are as minimal as possible for drivers at highway and bridge construction projects across the state.

Work Continues on Stormwater Management Pond South of Thruway in Tarrytown
Tappan Zee Constructors, LLC (TZC) has begun clearing a work zone immediately south of the Thruway in Tarrytown to prepare for the construction of a stormwater management pond. The pond will help control the flow of stormwater by collecting and retaining runoff. Excavation will follow the clearing and a retaining wall will be installed next spring. TZC will employ noise, dust and other mitigation techniques to minimize impacts to local residents.

Continued Demolition of Westchester Landing of Existing Tappan Zee Bridge
A small section of the existing Tappan Zee Bridge’s Westchester landing will be removed during overnight hours next Monday and Tuesday to make room for the new bridge. The work will require the closure of the northbound Thruway’s two right traffic lanes approaching the bridge to construct the abutment and the first foundation pier for the new northbound bridge, which is due to be completed late 2016. The two lanes will be closed between 8 p.m., Monday, Nov. 24 and 4:30 a.m., Tuesday, Nov. 25 and 8 p.m. to 11 p.m., Tuesday, Nov. 25.

Pile Driving and Other Construction Activity
Construction will continue in the Hudson River as crews place the foundations of the new bridge. Work will include pile driving between 7 a.m. and 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.

A second shift of workers also will continue pile welding, pile cleanout and concrete placement operations associated with foundations.

Related to the Westchester landing work referenced above, work is continuing on the new bridge’s landings on both sides of the river.  In Westchester, work includes drilling holes into the bedrock for the foundation of the landing. In Rockland, a similar operation is improving the strength of the soil by using aggregate piers, which are constructed with a drill that mixes soil and aggregate (i.e., crushed stone) to form a strong base for the new bridge’s abutment and foundation. The drilling process is less audible than impact pile driving and noise-reducing measures are being implemented to further minimize sound levels. The eight-week operation is anticipated to conclude in late November.

Additional work includes:

  • Pile cap foundation construction
  • Main span foundation construction
  • River Road utility work
  • Rockland trestle construction, including pile driving
  • Support for river-based work from the Rockland trestle
  • Survey inspections on existing bridge

Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.

New NY Bridge Project Monthly Newsletter_ November 2014

November 2014
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

Enter the Super Crane:

I Lift NY Arrives at the New NY Bridge Project 


 Following a 6,000 mile journey that included transit through the Panama Canal, the New NY Bridge project’s I Lift NY super crane arrived at the Hudson River construction site on October 6.

READ MORE

October 16, 2014 marked the first anniversary of permanent construction operations on the New NY Bridge project, and the past year has seen exceptional progress on the foundations of the new crossing. Looking ahead, the project is poised to make even greater and more visible strides in the coming year.

 

 READ MORE 

I Lift NY Completes Journey
I Lift NY Completes Journey
 

The I Lift NY super crane arrived at the New NY Bridge site on October 6. Here is a video of the powerful lifter completing the last leg of its 6,000-mile journey.

 

 READ MORE 

Led by the recently-arrived I Lift NY super crane, an armada of more than 30 floating cranes – each capable of raising immense structural elements with great precision – is hard at work lifting and placing many millions of pounds of components and materials to help build the New NY Bridge. These workhorse machines are critical to keeping the project on schedule for completion in 2018.

 

 READ MORE

Now in its second year, the New NY Bridge Educational Outreach Program continues to engage students of all ages in Westchester, Rockland and beyond. The program reflects Governor Andrew Cuomo’s goal of using the state’s largest infrastructure project to educate tomorrow’s professionals. This year, the team is focusing on the ‘how-it-works’ engineering behind the new bridge’s foundations.

 

 READ MORE 

Those keen on observing firsthand the progress of the New NY Bridge project are invited to the recently-opened Westchester viewing platform in Tarrytown’s Scenic Hudson RiverWalk Park. Located near the Tarrytown Senior Center at 240 West Main Street, the easy-to-access platform provides an unobstructed view of the project site.

 

READ MORE

Frequently Asked Questions
Q: What will happen to the current bridge?
A: The current Tappan Zee Bridge will be carefully dismantled and the structural steel will be recycled. The concrete deck panels, which have been replaced in recent years, will be reused where possible on other Thruway and state Department of Transportation projects.

 

http://campaign.r20.constantcontact.com/render?ca=d87df910-023c-4eb5-b9f6-bcac7d294151&c=4897cfb0-a650-11e3-bc68-d4ae5292c426&ch=49f6ea80-a650-11e3-bcd8-d4ae5292c426

Going Vertical First Columns Rise out of the Hudson

 

Following extensive pile installation and other foundation work in the Hudson River over the past year, the first permanent, vertical elements of the New NY Bridge are beginning to take shape: Two 40-foot steel cage towers now stand near the Westchester shore. Soon—with the addition of high-strength concrete—the first pier for the westbound span will be created.

“Everything we’ve been doing to date has been below the surface. This new work is giving people the first opportunity to see the bridge rising above the water,” noted Thruway Authority Construction Compliance Engineer Tom McGuinness.

The columns—over 130 in total—eventually will support the steel girders and deck of the new bridge. The girders and decking will be lifted in place by the soon-to-arrive I Lift NY super crane.

The steel cage frameworks for the piers are pre-assembled at a site several miles upriver. The rebar cages are transported to the project site by barge and lifted into place by floating cranes.

After the steel cages are carefully inspected, they are filled with concrete produced by the project’sfloating batch plants. Enclosing forms are erected around the frameworks to enable the concrete to set in the shape of the piers that will hold up the new twin-span structure.

The floating concrete batch plants maneuver around the river, mixing the precise amount of concrete required and using an extending arm to apply the material directly into the frameworks. The concrete flows around the steel cages and eventually hardens to form steel-reinforced concrete. The composite material is remarkably strong and capable of supporting the new bridge for the next century or more.

The New NY Bridge project remains on schedule and on budget as it approaches the one-year anniversary of new bridge construction that began with permanent pile installation in October 2013. Local residents can expect to see more and more vertical pier structures rise out of the river in the coming months as construction progress continues.

September 26, 2014 |

2014 New NY Bridge Project Monthly Newsletter

 

Art Show Bridges the Hudson:  

Exhibits on Display this Month


Dozens of art works interpreting the Tappan Zee Bridge and marking the construction of the New NY Bridge will be on display this fall at the new bridge project Community Outreach Centers in Rockland and Westchester. The art was created for the New York State Thruway Authority’s 2014 Bridge Art Show, a juried exhibition that invited local painters, sculptors and photographers to showcase their interpretations of the new bridge design or the existing Tappan Zee Bridge.

READ MORE

The New NY Bridge team’s high standards of quality and precision are crucial to the day-to-day operations of the project. To ensure that the bridge’s foundation piles are welded with consistent accuracy, skilled operators are utilizing advanced mechanical welding machines.

READ MORE

The Hudson Valley is a unique geological formation, created by receding glaciers tens of thousands of years ago. As the colossal sheets of ice melted and formed the Great Lakes, the melt-water rushed down the Palisades and filled the Hudson Valley with enough sediment to bury the Statue of Liberty. This torrential force of nature created the striking Hudson Valley landscape and more recently, a number of geotechnical hurdles for the New NY Bridge project.

READ MORE

 

The New York State Thruway Authority, Tappan Zee Constructors, LLC (TZC) and the U.S. Coast Guard have worked together to establish a safe channel for recreational boaters looking to access Piermont’s popular waterfront. The newly-marked channel is part of the New NY Bridge project team’s ongoing efforts to enhance boater safety in and around the construction area.

RED MOR

Frequently Asked Questions
Q: How long will it take to build the bridge?
A: The northern span of the new twin-span bridge is scheduled to open in December 2016. The completed twin-span bridge, with westbound traffic on the new northern span and eastbound traffic on the new southern span, is scheduled to open in April 2018.
Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates

PROJECT UPDATE FOR BOATERS

update

NEW NY BRIDGE PROJECT ESTABLISHES SAFE CHANNEL FOR PIERMONT BOATERS

Following collaboration with the U.S. Coast Guard, the New NY Bridge project team has installed channel markers near Piermont to help guide recreational boaters to and from the Hudson River Main Channel.

Soil borings will begin in South Nyack near the intersection of S. Broadway and Cornelison Ave. during the week of August 11 to inform preliminary design options. The samples of material will be taken in different areas to help designers understand subsurface conditions that may be experienced during construction. Some survey activities are also being performed to support these design investigations. These operations require temporary lane closures and traffic control measures including flaggers to maintain safety and movement of local traffic.

Construction will continue in the Hudson River as crews place the foundation for the New NY Bridge. Work will include pile driving between 7 a.m. and 7 p.m., Monday through Friday and 12 noon to 7 p.m. on Saturday.

A second shift of workers will also continue pile welding, pile cleanout and concrete placement operations associated with permanent foundations.

Sheet pile driving at locations on land and near the Rockland landing is temporarily on hold due to high noise levels from the operation. Tappan Zee Constructors, LLC (TZC) continues to implement additional noise-reducing measures at sheet pile driving operations at the Rockland Landing and in the river at one of the closest piers to the shoreline. Sheet pile driving operations will continue as soon as noise is at an allowable level.

Work will continue on the Rockland work trestle near the shoreline, including pile driving. The trestle will support equipment used for the construction of the western-most section of the new bridge.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of five knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

Lane Closures for New York State Thruway (I-87/I-287):

Monday Aug 11 Northbound, Left Lane near Exit 9 10 a.m. to 3 p.m.
Monday Aug 11 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.
Tuesday Aug 12 Southbound, Left Lane approaching the Toll Plaza and Left hand EZ-Pass Lanes. 10 a.m. to 3 p.m.
Tuesday Aug 12 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.
Wednesday Aug 13 Northbound, Left Lane near Exit 9 10 a.m. to 3 p.m.
Wednesday Aug 13 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.
Thursday Aug 14 Southbound, Right Lane near Exit 9 10 a.m. to 3 p.m.
Thursday Aug 14 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.
Friday Aug 15 Southbound, Right Lane near exit 9 10 a.m. to 1 p.m.
Friday Aug 15 Northbound, Right Lane approaching the Tappan Zee Bridge 9 p.m. to 5 a.m.

Ongoing Operations:

  • Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays
  • Pile Cap foundation construction
  • Main Span foundation construction
  • Rockland Landing construction
  • Westchester Landing construction
  • River Road utility work
  • Rockland trestle construction, including pile driving
  • Survey inspections on existing bridge

Support for river-based work from the Rockland trestle

Building the Backbone of the New NY Bridge


Main Span Bases Rise out of the Hudson

August 7, 2014

Two enormous structures with bases the size of football fields are rising out of the Hudson River at the New NY Bridge project site. These concrete monoliths are the pile caps that will act as the structural backbone for New York’s largest bridge and highway infrastructure project, distributing the weight of the bridge onto dozens of steel foundation piles.

The main span pile caps will support the bridge’s 400-foot towers, and require months of preparation to complete.

To construct these main span pile caps, steel pilings are first driven deep into the riverbed, reaching bedrock hundreds of feet below the surface. Once all the piles are in place, a series of concrete floor panels is pieced together around them, outlining the footprint of the pile cap as the supporting base for its concrete pour. The team then positions heavy steel panels precisely around the edge of this footprint to form a massive tub, which is sealed to be watertight and carefully lowered into the river to bring its base to the proper final level for the concrete pile cap.

Next, workers build the pile cap’s reinforcement system inside this lowered tub. The team installs high-strength steel reinforcement bars, called rebar, to closely-engineered dimensions within the form.

The project’s floating batch plantsare then moved adjacent to the pile cap, and each form is filled with concrete specially formulated for long-term durability. The process continues over many hours until the entire footprint is covered with concrete to the specified depth. Once this steel-reinforced concrete hardens, the backbone of the new structure will have taken shape.

Learn more about how steel piles are transported to the project site, or installed with the well-being of local wildlife in mind.

 

 

Read complete Monthly Newsletter here:

http://www.newnybridgegallery.com/updates/august-2014-new-ny-bridge-monthly-newsletter/

NEW NY BRIDGE PROJECT MONTHLY NEWSLETTER

President Obama and Governor Cuomo

 Visit New NY Bridge Project Site


With the Tappan Zee Bridge and the New NY Bridge project site in the background, President Obama stood by the Hudson River to make a push for funding transportation infrastructure. The Highway Trust Fund is projected to be insolvent by the fall, and the President is calling on Congress to […]

READ MORE

07-08-2014

The New NY Bridge team is reaching out to New York firms, suppliers and subcontractors – particularly disadvantaged business enterprises (DBEs) – to aid construction efforts. DBEs are defined by the U.S Department of Transportation as small businesses that are owned and controlled by socially and economically disadvantaged individuals such as women, minorities, veterans or disabled persons.

 

READ MORE

07-01-2014 
 

Road work along highways and ramps presents safety challenges to both motorists and construction crews. The New York State Thruway Authority keeps the public informed and up to date on the latest construction activities to help ensure the safety of motorists as well as Thruway and Tappan Zee Constructors, LLC (TZC) workers.

 

READ MORE

06-17-2014 
 

Native to the Hudson River and once plentiful here, the shortnose and Atlantic sturgeon were identified as endangered species and fishing of them was halted in 1996. Since then, the sturgeon population has been growing steadily in the Hudson, one of the species’ most important habitats.…»

 

READ MORE

06-24-2014 
 

The New NY Bridge team is reducing the project’s impact to the environment through the use of construction platforms-known as trestles on either side of the Hudson River. The trestles, which extend 1,000 feet from each shoreline and run parallel to the existing bridge, enable heavy duty machinery to work over shallow water and reduce the […]…»

 

READ MORE

The New NY Bridge project is now accepting submissions for its 2014 Bridge Art Show. The juried exhibit is an opportunity for local artists to showcase their interpretations of the new bridge design or the existing Tappan Zee Bridge.The project’s Visual Quality Panel – which includes Rockland and Westchester representatives involved in the arts, architecture, […]

 

READ MORE

People Behind the New NY Bridge

  

 

Minelly De Coo

Design Production Team Area Manager

Minelly De Coo is an area manager for the design production team, who coordinates efforts between the office and the field. As an environmental specialist, she analyzed sound data and worked with the project’s visual quality panel to help design the project’s noise barriers. Minelly is also involved in the environmental monitoring for the project, overseeing sound monitoring stations and directing crew members in the field. She is notified of any environmental concerns that may arise, and works to see that they are resolved in a timely manner. An invaluable member of the project team, Minelly is proud to see progress on the bridge as it rises out of the Hudson River.  

Frequently Asked Questions 

Q:
A:
The existing bridge has only seven lanes, some of which are narrower than the current standard width of 12 feet. The new bridge will have eight 12-foot-wide lanes. The wide shoulders of the new crossing will greatly reduce the impact of disabled vehicles and accidents, which can cause massive tie-ups on the existing bridge. The incline over the main span will not be as steep, allowing large trucks to maintain consistent speed and reduce engine and braking noise. There will also be gently banked curves to help smooth traffic flow and reduce accidents. The new bridge will also include all-electronic toll collection technology, which allows motorists to pay tolls without slowing down from highway speeds. Motorists without E-ZPass will be automatically billed by mail.
Get Your E-ZPass® “On-the-Go”at the 

View the latest issues of theNew NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates

 

Tappan Zee could be pathway to tourism in Rockland

Tourism experts say the new crossing and an enhanced bus system could lure tourists and their money to Rockland but officials need to start planning now.

Khurram Saeed, ksaeed@lohud.com11:25 a.m. EDT July 1, 2014

1402940492000-nnyb-rend-15

Most of the talk about the Tappan Zee Bridge project so far has been about construction, noise and how the state will pay for the crossing.

But on Monday, the conversation took a new direction: the bridge as a money generator.

“You’re in a good place here right now, particularly with some of the development at the Tappan Zee Bridge and what’s going to happen,” Mary Kay Vrba, tourism director for Dutchess County, told 50 people at “Destination Rockland: Blazing New Trails in Tourism” at Nyack College.

A group of marketing experts, business leaders and elected officials saw visions of cash registers being filled up by tourists walking or bicycling over the bridge’s dedicated path into Rockland County. A revitalized bus system slated to be ready when the $3.9 billion span opens in 2018 could bring more.

Rockland Legislative Chair Alden Wolfe organized the three-hour conference, stating that it marked the “launching point” for further discussion.

Vrba drew parallels between the upcoming Tappan Zee path and the Walkway Over the Hudson, a 1.2-mile-long pedestrian walkway connecting Highland and Poughkeepsie that draws 700,000 visitors a year. Rockland has most of the ingredients to became a destination with its access to the Hudson River, a bevy of hiking trails and parks, and quaint river villages filled with stores and restaurants.

Downtown Poughkeepsie, on the other hand, lacks popular tourist draws like art galleries, she said.

“They walk the bridge and they say, ‘What next?’ ” Vrba said. “So you’ve got the what next, I think, with Nyack and Piermont and a lot of the shops and everything. You’ve got a product that you can work with. I think you have some real opportunities.”

Officials have the luxury of time to take a look at their towns and villages, address their needs and invest in a tourism plan, she said.

South Nyack and Tappan Zee project officials are still struggling to figure out where people who want to use the path will park in the village. The project team is expected to hold a meeting soon with several concepts proposed by the community, Mayor Bonnie Christian said.

Asked how they addressed parking for the Walkway Over the Hudson, Vrba said the land on both sides was municipally owned and purchased by the state parks department so they could be converted into paid lots. They also had the benefit in Poughkeepsie of parking garages six blocks away.

Veronica Vanterpool, executive director of Tri-State Transportation Campaign and a member of the task force that recently came up with transit recommendations for the bridge, said it was seeking a “transformation” of the existing Tappan ZEExpress service to entice more riders. There would be modern buses, traveling more frequently, utilizing technology like off-board fare collection, but some have said the plan didn’t work.

The system, known as bus rapid transit, is still in the conceptual stage. There are no cost estimates, and only $20 million in state seed money to date.

Twitter: @ksaeed1

CONSTRUCTION SCHEDULE FOR THE WEEK OF 6/23

update

CONSTRUCTION CONTINUES ON THE NEW NY BRIDGE

Tappan Zee Constructors, LLC (TZC) will continue work on the Rockland County landing of the new bridge.  The work will last several weeks and includes the installation of sheet piles, some measuring over 50 feet long.  These interlocking steel sheets will support the existing roadway during the excavation and construction process.  A large crane with a vibratory pile hammer will install the sheets, and be positioned behind a temporary concrete barrier in South Nyack.

In Westchester County, crews will conduct directional boring for future utility relocations under I-87/I-287 west of the toll plazas from 9 p.m. to 4:30 a.m. the week of June 23.  The overnight operation requires the closing of various toll lanes.  Different tolls lanes will be affected as the work progresses.  The Thruway will remain open at all times.

Construction of the New NY Bridge will continue with pile driving between 7 a.m. and 7 p.m., Monday through Friday and 12 noon to 7 p.m. on Saturday.

A second shift of workers will also continue pile welding operations associated with permanent foundations.

Work will also continue on the Rockland temporary work trestle near the county shorelines, including pile driving to install the temporary foundations needed to support the platform. The trestles will support cranes for the construction of the western-most section of the new bridge.

Lane Closures for New York State Thruway (I-87/I-287):

Monday June 23 Northbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Monday June 23 Southbound, Toll Plaza Lanes 6-7-8 9 p.m. to 4:30 a.m.
Tuesday June 24 Northbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Tuesday June 24 Southbound, Toll Plaza Lanes 6-7-8 9 p.m. to 4:30 a.m.
Wednesday June 25 Northbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Wednesday June 25 Southbound, Toll Plaza Lanes 8-9-10 9 p.m. to 4:30 a.m.
Thursday June 26 Northbound, Right Lane near Exit 10 10 a.m. to 3 p.m.
Thursday June 26 Southbound, Toll Plaza Lanes 8-9-10 9 p.m. to 4:30 a.m.
Friday June 27 Northbound, Right Lane near Exit 10 10 a.m. to 1 p.m.

Mariners should be aware that TZC will continue installing permanent piles in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night. An interactive map showing vessel locations on the Hudson River is now available on the project website, NewNYBridge.com, for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.  More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here.

Ongoing Operations:

  • Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays
  • Rockland Landing construction
  • Westchester Landing utility relocations
  • River Road utility work
  • Rockland trestle construction, including pile driving
  • Survey inspections on existing bridge
  • Support for river-based work from the Rockland shoreline
  • Armoring of Dredge channel
  • Relocation/Moving to the Temporary Joint Facility at exit 12

Pile work for Tappan Zee Bridge starting in South Nyack

Khurram Saeed, ksaeed@lohud.com

Sheet piles will be installed just off River Road to create a temporary support wall for the Rockland landing of the new bridge.

Work is starting later this week to install 60-foot-long flat sheet piles along the northbound Thruway near River Road. The work will last about three weeks and take place only during the day, said Carla Julian, spokeswoman for bridge builder Tappan Zee Constructors. The sheet piles, which are different from the round pipe piles being used in the Hudson, will create a temporary continuous wall that will support the Thruway during the excavation and construction for the Rockland landing of the new bridge, Julian said in an email.

About 45 to 50 sheets are needed to cover approximately 100 feet, and crews typically average three piles per day, Julian saidThe site formerly housed a state Thruway Authority maintenance building; it was demolished a few weeks ago. A 165-foot tall crane positioned just off River Road will install the piles into the ground using a vibratory hammer, an alternative to louder pile driving.

The interlocking sheets are installed in sequence. Julian said crews first install a 25-foot-high template, lift and swing a sheet into the template, position it and drive enough of the pile to stand in the template, drive additional sheets, move the template and drive the piles the remaining depth.”The actual pile driving is the fastest part of the process and is not done in one shot,” she said.Tappan Zee Constructors crews are expected to be on the site Wednesday to mobilize and plan to begin work on Thursday or Friday.The pile work will require the closure of the right lane on the northbound Thruway for some of the operation, Julian said.

The lane will be closed this week from 10 a.m. to 3 p.m. Wednesday and Thursday, and from 10 a.m. to 1 p.m. on Friday. The project team has a video on YouTube providing an animated look at the construction of the new bridge’s main span foundation and towers.

http://www.lohud.com/story/news/local/tappan-zee-bridge/2014/06/10/pile-work-tappan-zee-bridge-starting-south-nyack/10280581/

Obama, at Tappan Zee Bridge, pushes transportation funding

The president will seek to rally support for more federal dollars for highway and bridge improvements.

TARRYTOWN – With the new Tappan Zee Bridge taking shape behind him, President Barack Obama on Wednesday urged Congress to inject billions of dollars in the nation’s transportation infrastructure to keep Americans working and encourage businesses to stay.

During his first visit to Westchester as president, Obama praised the progress on the new $3.9 billion crossing, which is replacing the 58-year-old crumbling structure.

“It carries a lot more traffic than when it was built back in 1955,” Obama said under sunny skies at Sunset Cove, a restaurant at the Washington Irving Boat Club. “At times, you can see the river through the cracks in the pavement. Now, I’m not an engineer, but I figure that’s not good.”

Highlights from President Obama’s speech on the country’s infrastructure at near the Tappan Zee Bridge in Tarrytown. (Video by Peter Carr/The Journal News)

He noted the new Tappan Zee will be the first new bridge in New York in 50 years and announced the federal government plans to apply the same “fast track” process to 11 other infrastructure projects, including Boston’s South Station and light rail around Seattle.

“Normally it would have taken three to five years to permit this bridge,” Obama said during his 10-minute speech. “We did it in a year and a half.”

With the Tappan Zee Bridge as a backdrop, President Barack Obama speaks from the Washington Irving Boat Club in Tarrytown May 14, 2014. The President spoke about the need for Congress to fund road and bridge improvements across the nation.

With the Tappan Zee Bridge as a backdrop, President Barack Obama speaks from the Washington Irving Boat Club in Tarrytown May 14, 2014. The President spoke about the need for Congress to fund road and bridge improvements across the nation.  (Photo: Seth Harrison/The Journal News)

He also called out congressional Republicans for blocking funding that would pay for modern highways, bridges and seaports.”We’ve got more than 100,000 bridges that are old enough to qualify for Medicare,” Obama said.Officials have warned that funding in the federal Highway Trust Fund is set to run out by the fall, which would put 112,000 active road and bridge projects and 5,600 transit projects at risk, along with nearly 700,000 jobs.”That’s like the population of Tampa and St. Louis combined,” the president said, citing the jobs figure.

“So far at least Republicans who run this Congress seem to have a different priority,” Obama said. “Rebuilding America — that shouldn’t be a partisan issue.”

Obama emphasized that “there is work to be done.”

“So the bottom line, Tarrytown, is America doesn’t stand still. … So I’m going to keep on fighting alongside all of you to make sure that we’re doing everything we can to rebuild America – not just rebuild one bridge, but I want us to rebuild every bridge. I don’t want us to just rebuild one school, I want us to rebuild every school that needs help.”

 His administration in late 2011 named replacing the Tappan Zee Bridge, which carries 138,000 vehicles a day, a top infrastructure priority. The process moved quickly from there, with environmental reviews fast-tracked and in 2013, the New York State Thruway Authority received a record $1.6 billion federal loan.

Under New York Gov. Andrew Cuomo, the state approved a process that allows infrastructure project to be designed while construction begins.

Cuomo, who introduced the president, has been praised for reviving the project, which had been stagnating for nearly a decade. It’s now in its second year of construction with completion projected for 2018.

With preparations in place for President Obama’s visit to the TZ Bridge construction site, minority construction workers protest about being shut out of major construction projects. (Video by Joe Larese/ The Journal News)

“We are the state of the bold. We are the state of the daring,” Cuomo said. “We are the state of performance. We are the state of skyscrapers, intricate transit systems. We are the state of public works that challenge the imagination.”

Also in attendance, seated to the back, was Westchester County Executive Rob Astorino, the Republican who is planning to challenge Cuomo this fall. He criticized the governor before the speech for not discussing the cost of future tolls.

“The public has a right to know before the election,” Astorino said. “They know what it’s going to be. They promised last year we would have answers.”

Astorino accused the governor’s staff of refusing to allow him to sit in the front. Cuomo’s office, however, denied it meddled with the seating chart. An official who attended the speech said Astorino spent more than an hour talking with reporters and that by the time he tried to claim a seat, the choice ones were taken.

But all eyes were on the president who wore a crisp dark suit and dark blue tie against a background of construction equipment and steel piles. Obama joked and shook hands with many of the 250 people who were invited to attend, including elected officials, construction workers and residents.

Chris Junge of Tarrytown brought his two children, Tucker, 8, and Cassie, 6. The family walked from home to the event.

“It was exciting to be that close. It was personal,” Junge said. “It was a long day for them but I think they will remember it.”

Arriving at John F. Kennedy International, Obama flew aboard Marine One to Tarrytown. He traveled by motorcade the short distance to the marina. Less than 30 minutes after he arrived, Obama was back off to New York City to attend two Democratic party fundraisers in the evening.

Reporter Brian Tumulty contributed to this story.

Twitter: @ksaeed1

http://www.lohud.com/story/news/local/tappan-zee-bridge/2014/05/14/obamas-tappan-zee-bridge-speech-set-mid-afternoon/9080115/

Tappan Zee viewing areas coming to Nyack, Tarrytown

Memorial Park in Nyack and RiverWalk Park in Tarrytown will offer close vantage points to check out what’s happening on the river or the perfect background for selfies.

SHARE 4CONNECTTWEETCOMMENTEMAILMORE

Love it or hate it, construction of the new Tappan Zee Bridge is sure to draw huge crowds over the coming months and years.

Not only are two spans going up, but how many of us have had a chance to see a mega-project like this rise before our collective eyes?

While both Rockland and Westchester offer numerous lovely vantage points from their shores, the official go-to viewing sites will be in Nyack’s Memorial Park and RiverWalk Park in Tarrytown. Platforms with binoculars, signs and seating are expected to open sometime this summer.

“People are going to come so we might as well plan for it,” Tarrytown Village Administrator Mike Blau said. Both villages will receive $50,000 through the project’s $20 million community benefits programs, which is equally funded by the state Thruway Authority and Tappan Zee Constructors, the team designing and building the $3.9 billion crossing.

The Tarrytown viewing area will be set up at the end of West Main Street, adjacent to Pierson Park. There’s already a round deck there, surrounded by a stone wall. It can comfortably fit 15 people, Blau said.

At least two binoculars on stands will be in place, along with signs about local history and information about the construction equipment in the water.

“When you see something come out of the river, I think a lot of people will be curious and will want to go look at it,” Blau said.

Both character-rich villages also are in line to cash in from the visitors through 2018, when the project is expected to wrap up.

“We see it as a unique economic opportunity,” Nyack mayor Jen Laird-White said. “The more people that come to look at the bridge, the more they’ll stop in Nyack and eat lunch or have a cocktail or buy something in our stores.”

The village was already planning a major renovation of its fishing pier, with $150,000 already in hand from New York’s state department.

Measuring 90 feet long by 30 feet wide, the current pier, lined with gravel and bordered by large boulders, will be transformed into a destination with a wood surface, decorative lighting, wood rails, fixed and moveable benches and tables and a curved end resembling a boat.

The project still has to be bid and construction could start as early as June, Nyack Village Administrator Jim Politi said.

The mayor said there’s some talk of a having a temporary stop-gap measure until then so people have someplace to look out on the Hudson, especially with the expected arrival of the humongous floating crane known as the Left Coast Lifter during the next several weeks.

“People love to watch things getting built,” Laird-White said.

Twitter: @ksaeed1

Building a New Bridge Video!

Building a New Bridge!

Building a New Bridge!

 

Building a New Bridge

NY Times BY ROOPA VASUDEVAN AND STEPHEN FARRELLMarch 25th, 2014

This video graphic illustrates how a new cable-stayed bridge across the Hudson River north of New York City will replace the 60-year-old Tappan Zee Bridge between Rockland and Westchester Counties.

February New NY Bridge Newsletter

newsletter

The New York State Thruway Authority and the New NY Bridge team are proud to present the February issue of the New NY Bridge Newslettera monthly publication designed to keep everyone abreast of the latest news about the project.

 In this issue:

American Made: New York Businesses Benefit From New NY Bridge Project

High Steel Structures, LLC: A Brief Look at One of The Nation’s Pre-Eminent Steel Producer

Reaching the Next Generation: New NY Bridge Project Presents for Science Week

Safety: Personal Protection Equipment (PPE)

Please enjoy the February New NY Bridge Newsletter.

 

Port Expected in Newburgh NY

By James Walshbilde (1)
Times Herald-Record
Published: 2:00 AM – 01/31/14

CITY OF NEWBURGH — A riverfront company aims to build a port on the Hudson from which it can transport decking for the new Tappan Zee Bridge.

Officials of Steelways Inc. and the city will join federal and state officials Friday morning to announce the effort, which Steelways spokeswoman Susan Sullivan said could bring 150 jobs over three years.

Mayor Judy Kennedy and Councilwoman Genie Abrams declined to discuss details of the plan in advance of Friday’s announcement, though both spoke glowingly — in general terms, anyway — of its potential. Among the expected attendees are Rep. Sean Patrick Maloney, D-Cold Spring, state Sen. William Larkin, R-C-Cornwall-on-Hudson, and Assemblyman Frank Skartados, D-Milton.

“This project has such potential,” Kennedy said. “It can truly change the economics of Newburgh.: Abrams said: “It will be very good news for the people of Newburgh, the kind of news we haven’t heard in 50 years.”

Sullivan said the company will bid on Friday to supply precast concrete decking for the new Tappan Zee Bridge. The contract will likely be awarded within a few weeks. Steelways can begin work on the port in April and complete the project by late summer. The company’s website says its 60 waterfront acres already include a shipyard with three sheltered harbors.

It has concrete marine launchways capable of accommodating vessels up to 300 feet long and 125 feet wide, and a marine railway capable of hauling 500-ton vessels. The main shipping channel runs adjacent to Steelways’ main pier, according to the site.

A resolution adopted Monday by the City Council expressed its “conceptual support of the Port of Newburgh project,” saying it will boost Newburgh’s economy by creating high-paying jobs and providing job-training opportunities for city residents.

Thomas Wright, a co-owner of Atlas Industries, a furniture designer and maker in the city, said who gets the potential jobs is important. “Jobs are great, but where do the people eat and live?” Wright said. “Are they people from Middletown driving to a parking lot, or people in Newburgh walking from their home in the city?”

Newburgh was once such a busy port that it had its own U.S. Customs office. Sailing ships were built at the waterfront in the 18th century. Navy ships were docked in Newburgh for repairs and reconstruction during World War II, said Mary McTamaney, the city’s historian. The Newburgh waterfront was where farmers brought their produce for shipping to New York City and beyond. “We were a transportation city,” McTamaney said. “We brought the goods of Orange County and the region to market, mostly downriver.”

jwalsh@th-record.com

http://www.recordonline.com/apps/pbcs.dll/article?AID=/20140131/NEWS/401310366

Tappan Zee Crane Arrives by Boat

NY Times BY STEPHEN FARRELL January 30th, 2014

TAPPENZEE2-articleLarge

A huge crane arrived in New York Harbor Thursday, after a 6,000-mile ocean journey from San Francisco. It will be used to build the new Tappan Zee Bridge across the Hudson River.

Watch Video here:  http://www.nytimes.com/video/nyregion/100000002680602/tappan-zee-crane-arrives-by-boat.html?smid=pl-share

 

Muscular West Coast Worker is on way to Build New Tappan Zee Bridge

NY Times January 27,2014 , Joseph Berger

Read complete NY Times article here:  http://nyti.ms/1jZ4Pm9

A 6,000 mile journey from San Francisco to NY; this might crane will rise to build the New NY Bridge!

TAPPANZEE4-articleLarge

 

Watch Time Lapse Video here: Passing thru the Panama Canal

tappanzee-videoSixteenByNine540

 

 

 

A Colossal Bridge Will Rise Across The Hudson

 

TZ Under construction

Expected to last 50 years, the Tappan Zee Bridge also known a “The Longest Bridge in New York” is rebuilding what might be the “Widest Bridge in the World”.

Read the complete article here:  http://www.nytimes.com/2014/01/20/nyregion/a-colossal-bridge-will-rise-across-the-hudson.html?hp&_r=0

 

GIANT FLOATING CRANE PREPARES FOR PASSAGE THROUGH THE PANAMA CANAL, EN ROUTE TO NEW NY BRIDGE PROJECT

bilde

The new NY bridge

For immediate release: January 10, 2014

GIANT FLOATING CRANE PREPARES FOR PASSAGE THROUGH THE PANAMA CANAL, EN ROUTE TO NEW NY BRIDGE PROJECT

The journey that began late last month for one of the world’s largest floating cranes continues as it prepares to pass through the Panama Canal this weekend.

The crane, known as the Left Coast Lifter, is expected to begin its passage through the Panama Canal as soon as Saturday, Jan. 11, and updated information on its journey will be available at NewNYBridge.com. It departed from Oakland, California, on Dec. 22, escorted by tug boats, and is expected to arrive in New York at the end of the January.

A fourth construction camera is now live and is also available on the project website. The public can stay up-to-date on the progress of the New NY Bridge project with views from this camera, which captures construction as viewed from Tarrytown, as well as through those already live from Rockland County, Westchester County and on the bridge. An interactive archive calendar also allows viewers to take a look back at progress already made.

As weather permits, Tappan Zee Constructors, LLC (TZC) will continue construction of the foundation of the New NY Bridge with ongoing installation of permanent piles. TZC plans to begin full production again on Monday, Jan. 13, assuming temperatures rise and ice clears the river.

On Monday, Jan. 13 and Tuesday, Jan. 14, the southbound, right-hand lane and shoulder of the New York State Thruway (I-87/I-287) near exit 10 in Nyack will be closed from 10 a.m. to 3 p.m. On Wednesday, Jan. 15 and Thursday, Jan. 16, the northbound, right-hand lane and shoulder of the Thruway (I-87/I-287) near exit 10 in Nyack will be closed from 10 a.m. to 3 p.m., to allow for work on the northbound maintenance ramp.

Mariners should be aware that TZC will be installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) – 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website at NewNYbridge.com under the “Boater Safety” icon.

Ongoing Operations:

• Rockland access ramp modifications
• Armoring of dredge channel
• River Road utility work
• Test pile program
• Permanent pile installation
• Temporary Rockland trestle construction, including pile driving on weekdays 7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline
• Reinforcement steel pre-assembly at bridge yard

Giant crane Left Coast Lifter on way to build new Tappan Zee Bridge

 Ocean voyage expected to take 6 to 8 weeks

LoHud December 31, 2013 Theresa Juva Brown

http://www.lohud.com/videonetwork/2968321291001/Left-Coast-Lifter-heads-for-Tappan-Zee-Bridge-project

The gargantuan crane that will help build the new Tappan Zee Bridge is on its way.

New video released by bridge builder Tappan Zee Constructors shows the Left Coast Lifter passing under the Golden Gate Bridge in San Francisco this week as it begins its 6,000-mile voyage to the Hudson River. The journey is expected to take six to eight weeks. The 400-foot-long floating crane — one of the world’s largest — will travel down the West Coast, through the Panama Canal, across the Gulf of Mexico, up the East Coast and through New York Harbor.

The Left Coast Lifter, previously used on the San Francisco-Oakland Bay Bridge project, can lift 1,750 metric tons, or 12 times the weight of the Statue of Liberty. It will help install the huge deck panels on the new Tappan Zee and demolish the existing Tappan Zee in 2017.

The crane is owned by Fluor Corp. and American Bridge Co., two of the companies that make up Tappan Zee Constructors.

bilde

 

Read complete article here: http://www.lohud.com/article/20131231/NEWS02/312310014/Giant-crane-Left-Coast-Lifter-on-way-to-build-new-Tappan-Zee-Bridge-(video)?nclick_check=1

Construction Continues From US9 to TZ Bridge

new

For immediate release: December 6, 2013

INSTALLATION OF PERMANENT PILES CONTINUES,
TARRYTOWN RAMP FROM US9 SOUTH TO TAPPAN ZEE BRIDGE CLOSES

Construction activities continue on the foundations for the New NY Bridge with the ongoing installation of permanent piles.

The entrance ramp to the Tappan Zee Bridge (I-87 northbound/I-287 westbound) from South Broadway (Route 9) in Tarrytown is now closed to traffic for the duration of the New NY Bridge project. Signs are in place to direct motorists to the entrance ramp located nearby on White Plains Road (Route 119.)

As a result of the closure, motorists who wish to travel northbound/ westbound on the Thruway are directed to bear right immediately after the closed ramp, onto what is referred to as the “jughandle” for Route 119. Motorists will proceed approximately 0.2 miles east on Route 119, turning right onto the I-87 northbound/I-287 westbound entrance ramp.
Walkways along South Broadway will be maintained for pedestrian use.

Tappan Zee Constructors, LLC (TZC) will utilize the area surrounding the ramp for storage and staging, which will in turn reduce the amount of construction traffic on local roadways. Complete closure is required for the construction of the New NY Bridge in order to ensure safety for motorists and project workers.

Excavation and preparation work for installation of permanent sound barriers continues along I-87 northbound /I-287 westbound in the area south of exit 10 in Rockland County. From Monday, Dec. 9 to Thursday, Dec. 12, one northbound right-hand lane and shoulder on I-87/I-287 near exit 10 in Nyack will be closed from 10 a.m. to 3 p.m. and Friday, Dec. 13 from 10 a.m. to 1 p.m.

Mariners should be aware that TZC will be installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard in the future may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website under the “Boating Safety” icon.

Ongoing operations:
• Rockland access ramp modifications
• Armoring of dredge channel
• River Road utility work
• Test pile program
• Rockland Dock Extension – finishing work under existing bridge
• Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline
• Reinforcement steel pre-assembly at bridge yard

 

###

West Nyack buildings demolished to clear way for ‘Palisades Plaza’

LoHud By Akiko Matsuda November 27, 2013

http://m.lohud.com/RocklandNews/article?a=2013311260048&f=1168

Demolition work in West Nyack has made the way for a strip mall, to be known as Palisades Plaza.

Demolition work in West Nyack has made the way for a strip mall, to be known as Palisades Plaza. – Akiko Matsuda/The Journal News

WEST NYACK — A triangular lot with three buildings that was an eyesore for years will soon become a strip mall with a restaurant.

The 2.36-acre site is east of Route 303 and south of the New York State Thruway. The lot originally consisted of three separate properties: a single-story mixed-use office and light manufacturing building, a former state police barracks, and a former Texaco station.

Those buildings were all demolished recently. On Tuesday, heavy machinery was crushing chunks of concrete left behind.

The development is the latest sign of life to spring out of disused lots in the Tappan Zee Bridge corridor.

Developer Lawrence Adler of East Syracuse has gone before the Clarkstown Planning Board for his plans to build a 13,900-square-foot strip mall at the site, combining the three lots into one.

“Palisades Plaza” will include four retail stores and a restaurant with drive-thru service. Names of the future occupants are not mentioned in the application.

Adler and Ira Emanuel, an attorney representing the developer, did not return phone and email messages seeking comment.

Clarkstown Principal Town Planner Joe Simoes said the developer has taken all the necessary steps with regulatory jurisdictions.

At its meeting last month, the Clarkstown Planning Board granted final approval for the project, and the developer is in the process of getting Planning Board Chairwoman Shirley Thormann’s signoff.

The Tappan Zee Bridge replacement project has been stimulating the local real estate scene, as bridge builder Tappan Zee Constructors is leasing properties for temporary construction staging areas.

The former Journal News printing plant at 160 N. Route 303 — just north of the proposed Palisades Plaza — is slated to become a temporary home for state police and the New York state Thruway Authority.

Simoes said he didn’t believe the strip mall project was prompted by the bridge construction because the developer has been unsuccessfully trying to bring new businesses to the site for some time.

Because it’s an oddly shaped property that was partly zoned “residential,” it has been difficult to develop, Simoes said. Most recently, a mini-storage project was proposed, but the plan didn’t work out, he said.

The zoning issue has been resolved, making a way for the strip mall.

Simoes said the new development would be good for the community.

“It’s been such an eyesore for years that it’s an improvement,” he said.

Twitter: @LohudAkiko

Inaugural Newsletter of the New NY Bridge

 

MonthlyNewsletter_Nov_2013 (3) Page 001

 

The New York State Thruway Authority and the New NY Bridge team are proud to launch the first issue of the New NY Bridge Newsletter, a monthly publication designed to keep everyone abreast of the latest news about the project.

The newsletter, produced in partnership with Tappan Zee Constructors, LLC (TZC), is one of many outreach tools employed to keep residents of Rockland and Westchester counties and the entire region informed about the New NY Bridge Project — the largest transportation infrastructure project in North America. Please enjoy the inaugural issue of the New NY Bridge Newsletter.

 

Read the complete Newsletter document here: MonthlyNewsletter_Nov_2013 (3)

As New Bridge Construction Begins, Boaters Must Practice Defensive Driving

New City Patch , Posted by  (Editor) , 

New City Patch Article Here

6430fd382faebe6b4396d23c2321c533

With permanent piles for the New Tappan Zee Bridge now going in, navigating the Hudson is getting increasingly more challenging.

There’s a very necessary and informative forum on Hudson River Boating Safety Wednesday at 7 p.m. in Tarrytown Village Hall at One Depot Plaza.

Bridge officials in their latest weekly press release advised mariners to exercise extreme caution where the new piles are going in – “in the vicinity of the side channels under the existing bridge.”

“New temporary navigational lights have been installed to further define the 600’ navigation channel under the main span. Both temporary and permanent piles are illuminated at night.”

The U.S. Coast Guard recently issued revised safety information, establishing a “Regulated Navigation Area” from 300 yards north of the bridge to 200 yards south:

“All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard in the future may temporarily prohibit all vessel traffic in the RNA for safety purposes.”

More boating safety information can be found on theNewNYBridge website here, including exact lighting regulations and approved mooring locations.

And for a previous Patch article on the difficulties of navigating the waters at night, click here.

 

 

 

 

 

 

 

 

 

The first permanent piles for the New Tappan Zee Bridge are going in this week.

Tarrytown-Sleepy Hollow Patch; Posted by (Editor) , 

349fd2e38bd6114054c0c042a06a4d90

The big news on today’s media boat tour of the work surrounding the Tappan Zee Bridge was that construction is now officially underway for the new bridge.

All the action we’ve been seeing for months in the river has been preconstruction work – test piling, geotechnical investigations, dredging. Just this week, permanent piles are being vibrated, and then pounded, in place to begin forming the bridge’s foundation.

“This week, we are putting shovels in the ground and starting formal construction on a new bridge to replace the Tappan Zee, the largest infrastructure project New York State has undertaken in decades,” Governor Andrew Cuomo said in a press release following the tour, which was cut a little short due to the threat of rain.

“After more than a decade of delay, New York State has moved this project forward at a dramatic pace while working with the community, involving the public and protecting the local environment,” Cuomo said. “Once completed, drivers in Rockland, Westchester and surrounding areas will finally have a safer, less congested bridge that will include a walkway for pedestrians and bikers and accommodates future mass transit.”

The project, said Thruway Authority Chairman Howard Milstein, is on track with a projected build timeline in place of just under five years.

Bridge cam anyone? You can watch the progress up close as it happens on a new ‘Construction Camera’ section of the New NY bridge website.

The specifics of the five-year timeline to date:

· Dredging to prepare for bridge construction is ongoing until November 1, and will also take place during August, September and October, 2014.
· October 2013: Main span permanent pile installation begins
· November 2013: Permanent pile installation begins for approaches
· March 2014: Work begins on approach substructure
· June 2014: Work begins on main span substructure
· September 2014: Work begins for erection of superstructure
· Late 2014 / early 2015: Work begins on cable stay installation
· Late 2016: Complete north span
· December 2016: Relocate westbound traffic to new north span
· February 2017: Relocate existing eastbound traffic to new north span
· February 2017: Start demolition of existing bridge
· Late 2017: Both spans complete
· November 2017: Relocate eastbound traffic from new north span to new south span
· April 2018: Physical completion of project
· July 2018: Final acceptance of project

There are reports that one of the world’s largest floating cranes, the Left Coast Lifter, is in Virginia now, ever so slowly making its way upriver for the biggest show we’ll see yet.

Read complete article here:

http://tarrytown.patch.com/groups/tappan-zee-bridge/p/construction-for-new-tappan-zee-bridge-begins-now

New Tappan Zee Bridge spurs interest in nearby commercial parcels; Vacant commercial sites now sold, leased

bilde

LoHud October 15, 2013 Written by Theresa Juva-Brown

The Tappan Zee Bridge replacement project is giving new life to vacant commercial properties that have languished since the Great Recession.

The site of the former Lovett power plant in Stony Point, for instance, sat unused for years before bridge builder Tappan Zee Constructors recently signed a lease with NRG Energy to assemble bridge pieces there. As part of the deal, Stony Point could collect up to $500,000 in permit fees over the next five years.

It’s been a similar situation in West Nyack, where the former Journal News printing plant at 160 N. Route 303 hasn’t had a tenant in three years, said Timothy Hauser of the Hauser Bros., the real estate investment company that owns the site.

That will change this spring, when state police and the New York State Thruway Authority temporarily move from Tarrytown to the 42,000-square foot warehouse that is currently being renovated.

Tappan Zee Constructors is relocating those operations because it plans to tear down the current barracks/Thruway offices on North Broadway and use the area for bridge construction equipment.

“We’re giving them a piece of property at a fair market value rate, and they are taking the expenses off my lap that I have to struggle to pay,” Hauser said of the parcel on Route 303 near Thruway Exit 12. Just before the deal was reached in April, the asking price for the warehouse was $6.25 per square foot, according to the website of Rand Commercial Services, which was involved with the agreement.

Hauser said the five-year lease could be extended, but for now the site’s future remains wide open.

“It’s one of the best locations in the entire county for any type of business — a car dealer, hotel. It’s a discussion already,” he said.

The recent deals, even if they are for just five years, help the local real estate industry but also the region’s optimism about the overall economy, said Paul Adler, vice president of Rand Commercial.

“People are understanding that this is the beginning of the growth,” he said. “What we’re seeing is just enough to nudge us out of this recession.”

“There is income, and there is enough time to plan what to do after five years now that the landlord has cash flow,” he added. “These 5-year injections of confidence in the market are going to spur smart growth.”

The new bridge, especially the thousands of workers the project will bring, helped convince Howard Josephs to purchase a commercial parcel in Nyack last month.

Josephs, a partner with Josephs Group, bought slightly less than an acre near Route 59 and Waldron Avenue.

A gas station and fast food joint once operated there, but the site has been dormant for years, he said.

After the land is remediated this winter, he plans to build a 5,000-square foot restaurant and retail center.

He declined to disclose how much he paid for the site.

“It’s a very busy corner, and we see it as the gateway to Nyack,” he told The Journal News. “I think the bridge (project) will definitely bring a lot of people for a number of years.”

The project is also giving a lift to property owners in Westchester.

Tappan Zee Constructors moved into its main office on White Plains Road in Tarrytown this spring and is leasing a satellite office on the grounds of Hudson Harbor, a residential complex on the Tarrytown waterfront.

Farrokh Hormozi, an economics professor at Pace University in Pleasantville, said property owners who are leasing instead of selling is a sign that they expect their assets to gain significant value after the new bridge is completed. He said more businesses and people will want to live and work near the future Tappan Zee. “It’s all facilitated by a more comfortable ride across the bridge,” he said.

Read complete article here:http://www.lohud.com/apps/pbcs.dll/article?AID=/201310142341/NEWS/310140063

 

TZ Bridge Pre-Construction Activities Continue

The new NY bridge

For immediate release: October 11, 2013

NEW NY BRIDGE PROJECT
PRE-CONSTRUCTION ACTIVITIES CONTINUE

 

Second shift operations will continue on the river from 3:30 p.m. to 12 midnight on weekdays in preparation for permanent construction activities.

This work is primarily to support activities for the daytime pile driving operations and is limited by the project’s noise level restrictions. Pile driving will be limited to the hours of 7 a.m. to 7 p.m. on weekdays and, occasionally, from 12 noon to 7 p.m. on Saturdays.

Construction of the Rockland County trestle will continue. This work will include daytime pile driving to install the temporary foundation piles needed to support the platform. The trestle is a work platform that will support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required.

From Tuesday, October 15 to Friday, October 18, one southbound right hand lane and shoulder on I-87/I-287 between exit 9 and exit 11 will be closed from 9 a.m. to 3 p.m. for shoulder work.

Additionally, utility work will continue on River Road in South Nyack. This work will be performed from 6:30 a.m. to approximately 6 p.m. for the next three weeks and has been coordinated with and approved by the Village of South Nyack. The work will reduce the roadway to one lane during daytime hours and flaggers will be onsite to safely direct motorists on River Road. During non-work hours, the road will have temporary coverings in place that may create uneven surfaces. Motorists and bicyclists should slow down and use extreme caution in the area.

Mariners should be aware that TZC will be installing piles in the vicinity of the side channels. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area.

If necessary, the Coast Guard in the future may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website, NewNYBridge.com, under the boating safety icon.

E-ZPass tags are now available for purchase at the New NY Bridge Community Outreach Centers in Tarrytown and Nyack.

The pre-packaged E-ZPass tags can be purchased for $25 and are ready for immediate use. E-ZPass users avoid delays when traveling through toll plazas, receive a discount on every Thruway toll they pay, and enjoy the convenience of using E-ZPass in fifteen states: Delaware, Illinois, Indiana, Maine, Maryland, Massachusetts, New Hampshire, New Jersey, New York, North Carolina, Ohio, Pennsylvania, Rhode Island, Virginia, and West Virginia.

E-ZPass tags have a $25 value and are active upon purchase. The first $15 is immediately available for toll usage, and the remaining $10 becomes available once the tag is registered online or by phone. E-ZPass provides a five percent savings on Thruway tolls and offers toll discounts on many other roadways.

The Community Outreach Centers for the new bridge project were established last year as a gathering place and source of information for the community regarding the New NY Bridge. They are located at:

• 303 South Broadway in Tarrytown, and
• 142 Main Street in Nyack.

The centers are open Monday through Friday, 11 a.m. to 7 p.m.; Saturday and Sunday, 11 a.m. to 4 p.m.

Ongoing operations:

• Dredging operations will continue 24/7

• Test pile program

• Rockland Dock Extension under existing bridge

• Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.

• Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.

• Survey inspections on existing bridge

• Support for river-based work from the Rockland shoreline

TZC CREWS SAVES UNMOORED BOATS

update

For immediate release: October 4, 2013

TZC CREWS SAVES UNMOORED BOATS

Tappan Zee Constructors, LLC (TZC) crews helped rescue two boats that became unmoored near the Tappan Zee Bridge this past week.

On September 25, crews spotted a sail boat approaching the dredging area surrounding the Tappan Zee Bridge. After attempting communications and determining that no one was onboard, TZC’s safety team secured the boat and towed it to a tugboat. TZC then contacted the Rockland County Sheriff’s Office and the Coast Guard to track down the owner of the vessel. Later in the week, another unmoored vessel was secured by TZC and safely returned to its owners.

TZC crews will begin second shift operations on the river from 3:30 p.m. to 12 midnight on weekdays in preparation for permanent construction activities. This work is primarily support activities for the daytime pile driving operations and is limited by the project’s noise level restrictions. Pile driving will be limited to the hours of 7 a.m. to 7 p.m. on weekdays and, occasionally, from 12 noon to 7 p.m. on Saturdays.

Construction of the Rockland County trestle will continue. This work will include daytime pile driving to install the temporary foundation piles needed to support the platform. The trestle is a work platform that will support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required.
From Monday, October 7 to Wednesday, October 9, one southbound right hand lane and shoulder on I-87/I-287 between exit 12 and the Tappan Zee Bridge will be closed from 10 a.m. to 3 p.m. for shoulder work.

Additionally, utility work will continue on River Road in South Nyack. This work will continue through November and will involve reducing the roadway to one lane during daytime hours. During non-work hours, the road will have temporary coverings in place that may create uneven driving surfaces. Motorists and bicyclists should slow down and use extreme caution in the area.

Mariners should be aware that TZC will be installing piles in the vicinity of the side channels. Both temporary and permanent pile are illuminated at night. Boaters should use extreme caution and only use the main channel for transiting the area.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are required to use the main channel, reduce wake and use extreme caution while transiting the area.

If necessary, the Coast Guard in the future may temporarily prohibit all vessel traffic in the RNA for safety purposes.

The Coast Guard boating safety information can be found on the project website, NewNYBridge.com, under the boating safety icon.

Ongoing operations:
• Dredging operations will continue 24/7
• Test pile program
• Rockland Dock Extension under existing bridge
• Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
• Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline

The New York Bridge Quarterly Newsletter

The New NY Bridge Newsletter

 

Quarterly Marketing Report

The NewNYBridge releases it quarterly Newsletter.

Check out the construction progress and what the future holds for the TappanZee Bridge project.

Visit: www.TheNewNyBridge.com

 

Bridge Construction Continues

new

For immediate release: September 27, 2013

NEW NY BRIDGE PROJECT CONSTRUCTION ACTIVITIES CONTINUE

Tappan Zee Constructors, LLC will continue the construction of the Rockland County trestle.
This work will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to the hours of 7 a.m. to 7 p.m. on weekdays and, occasionally, from 12 noon to 7 p.m. on Saturdays. The trestle is a work platform that will support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required.

Impact pile driving will also continue as part of the ongoing test pile program and will continue through October at various locations for future pile foundations during the same timeframe as above.

>From Tuesday, October 1 to Thursday, October 3, one northbound right hand lane and shoulder on I-87/I-287 between exit 9 and the Tappan Zee Bridge will be closed from 10 a.m. to 3 p.m. for utility location testing. One northbound right hand lane and shoulder on I-87/I-287 in the vicinity of exit 10 will be closed on Wednesday, October 2, from 10 a.m. to 3 p.m. for catch basin repair.

Additionally, utility work will continue on River Road in South Nyack. This work will continue through November and will involve reducing the roadway to one lane during daytime hours. During non-work hours, the road will have temporary coverings in place that may create uneven driving surfaces. Motorists and bicyclists should slow down and use extreme caution in the area.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are required to use the main channel, reduce wake and use extreme caution while transiting the area.

If necessary, the Coast Guard in the future may temporarily prohibit all vessel traffic in the RNA for safety purposes.

The Coast Guard boating safety information can be found on the project website, NewNYBridge.com, under the boating safety icon.

Ongoing operations:
•Dredging operations will continue 24/7
•Test pile program
•Rockland Dock Extension under existing bridge
•Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
•Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
•Survey inspections on existing bridge
•Support for river-based work from the Rockland shoreline

Tappan Zee Bridge Labor Day Holiday Schedule 2013

update

For immediate release: August 30, 2013

NO IMPACT PILE DRIVING OR LANE CLOSURES SCHEDULED FOR LABOR DAY HOLIDAY WEEKEND, ROCKLAND BULKHEAD CONCRETE PLACEMENT TO COMMENCE

Tappan Zee Constructors, LLC (TZC) will not engage in any pre-construction activities that affect traffic through Monday, Sept. 2 in observance of Labor Day. No lane closures will be allowed until Tuesday Sept. 3 at 10am in order to avoid impacts on motorists during the busy Labor Day holiday travel weekend. In addition, no impact pile driving is scheduled until Tuesday September 3.

Dredging will continue 24/7 through Oct. 31. As outlined in the Final Environmental Impact Statement for the New NY Bridge project, the dredging window is designed to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.

Rockland bulkhead construction continues next week with concrete placement. Frequent concrete truck traffic is expected on certain designated roads in the villages of Nyack and South Nyack from 9 a.m. to 4 p.m. on Tuesday, Wednesday and possibly Thursday. TZC and the Thruway Authority have coordinated extensively with village leaders and local police to ensure safety and minimize impacts on traffic, the villages and their residents. Anyone with questions can call the New NY Bridge 24-hour Toll-Free Hotline: 1-855-TZ-BRIDGE.

Construction of the Rockland County trestle will continue and include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to a maximum of 7 a.m. to 7 p.m. on weekdays and, occasionally, on Saturdays from noon to 7 p.m. The trestle is a work platform that will support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required.

Impact pile driving will continue as part of the ongoing test pile program and will continue through October at various locations for future pile foundations during the same timeframe as above. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.

On Tuesday, Sept. 3, one northbound right hand lane and shoulder on I-87/I-287 near Exit 10 will be closed from 10 a.m. to 3 p.m. for shoulder work. The northbound right hand and shoulder lane will be closed at the same location from 10 a.m. to 12 noon on Wednesday, Sept. 4. On Friday, Sept. 6, one southbound right hand lane and shoulder on I-87/I-287 between the foot of the existing Tappan Zee Bridge and Exit 11 will be closed from 10 a.m. to 1 p.m. for shoulder work.

Ongoing operations:

Test pile program
Rockland bulkhead construction and Dock Extension at Rockland under existing bridge
Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
Survey inspections on existing bridge
Mobilization at the exit 10 staging area
Support for river-based work from the Rockland shoreline

DREDGING OPERATIONS BEGIN, TEST PILE PROGRAM IMPACT PILE DRIVING ONGOING

new

Project Update

For immediate release: August 2, 2013

Tappan Zee Constructors, LLC (TZC) began 24 hour a day dredging operations today in the Hudson River as part of the New NY Bridge Project.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use extreme caution within 1,000 feet of all construction barges as a safety precaution.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com.

Dredging will occur over a three-month period from August 1 through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.

Dredging crews will work 24 hours a day, seven days a week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being processed and properly disposed at offsite locations.

Impact Pile driving began this week as part of the ongoing test pile program and will continue over the next three months at various locations for future pile foundations. This work will be performed 7 a.m. to 7 p.m. on weekdays and at times on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

Ongoing operations:
· Test pile program
· Rockland bulkhead construction (including fence & gates)
· Dock Extension at Rockland (under existing bridge)
· Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Rockland and Westchester environmental monitor installations
· Geotechnical land borings
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline

Westchester:
Limited test-boring operations will continue on Thruway property near the Irving Neighborhood in Tarrytown. The work is scheduled to be conducted between the hours of 7 a.m. and 5 p.m. Monday, August 5 through Wednesday, August 6.

Rockland:
TZC, LLC will reconstruct the sidewalk along River Road in S. Nyack north of the existing bridge. This is part of the Bulkhead construction area and will be performed between 7 a.m. and 3 p.m. Monday, August 5 and Tuesday, August 6. River Road will be limited to one lane with flag persons in place to control traffic safely.

Survey activity will occur in the southbound lanes of I-87/I-287 and will require a temporary lane closure between exit 10 and the existing bridge from 10 a.m. to 3 p.m. Monday, August 5 and Tuesday, August 6.

NEW NY BRIDGE TEST PILE PROGRAM STARTS NEXT WEEK

The new NY bridge

 

For immediate release: July 12, 2013

NEW NY BRIDGE TEST PILE PROGRAM STARTS NEXT WEEK

Beginning the week of July 15, Tappan Zee Constructors, LLC will install the first test piles for the New NY Bridge.

The test pile operations will be conducted over the next three months at proposed locations for pile foundations. Work will start at the main span footings. Piles will be placed by utilizing both vibratory and impact installation techniques. The test pile program will verify subsurface conditions in preparation for the construction of the bridge’s permanent foundation.

Multiple crews will conduct night time boring operations along I-87/I-287 in both Westchester and Rockland Counties. The night time operations are necessary due to lane closure restrictions during day time hours that are in place to keep traffic flowing over the current bridge. Boring operations will begin at exit 10 in Rockland County and move west into Westchester County.

Ongoing operations

– Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
– Survey inspections on existing bridge
– Rockland environmental monitor installations continue
– Geotechnical land borings
– Mobilization at the exit 10 staging area
– Support for river-based work from the Rockland shoreline

Westchester:
Night time boring operations to investigate subsurface soil conditions will be conducted in the southbound shoulder of I-87/I-287 and will require a temporary right lane closure between the existing bridge and exit 9 on Friday, July 19 from 9 p.m. to 6 a.m.

Rockland:
Night time boring operations to investigate subsurface soil conditions will be conducted in the southbound shoulder of I-87/I-287 and will require a temporary right lane closure between exit 10 and the existing bridge from 9 p.m. to 6 a.m. beginning Monday, July 15 through Thursday, July 18.

ONGOING PRECONSTRUCTION ACTIVITIES CONTINUE ON THE NEW NY BRIDGE PROJECT

The new NY bridge

For immediate release: July 5, 2013

ONGOING PRECONSTRUCTION ACTIVITIES CONTINUE ON THE NEW NY BRIDGE PROJECT

Tappan Zee Constructors, LLC (TZC, LLC) will continue preconstruction activities the week of July 8 in Westchester and Rockland Counties.

Ongoing operations:

– Cleaning and preparation for future construction of the Thruway’s Rockland Bulkhead
– Construction of the temporary Westchester work trestle which includes pile driving operations that will occur between 7 a.m. and 7 p.m.
– Survey inspections on existing bridge
– Rockland environmental monitor installations continue
– Geotechnical land borings
– Mobilization at the Exit 10 staging area
– Support for river-based work from the Rockland shoreline

Lane closures will be in place on the right lane of northbound I-87/I-287 on Monday, Tuesday and Friday from 10 a.m. to 3 p.m. for installation of instrumentation to monitor the existing bridge during construction. Lane closures will also be in place on the southbound right lane of I-87/I-287 Wednesday and Thursday from 10 a.m. to 3 p.m. for the same activity.

LARGE CRANES START TO ARRIVE ON THE HUDSON RIVER THIS WEEK

update

Two large barge-mounted cranes that will be used to place permanent piles for the substructure of the New NY Bridge Project will arrive throughout the next two weeks. Upon arrival, crews will start to assemble each crane and moor them until the test pile operations begin in mid-July. The cranes will be moored on the north side of the bridge closer to the Rockland County side of the Hudson River.


Neither of these cranes are the Left Coast Lifter, which is set to arrive late this year.

Work will also begin next week on the New York State Thruway Authority’s Rockland bulkhead area located on River Road in South Nyack. Work includes clearing of the site and construction of a larger bulkhead that will be used for staging of equipment.

Ongoing operations:
– Construction of the temporary Westchester work trestle which includes pile driving operations occurring weekdays between 7 a.m. and 7 p.m.
– Survey inspections on existing bridge
– Environmental monitoring activities
– Geotechnical land borings
– Mobilization at the Exit 10 staging area
– Support for river-based work from the Rockland shoreline

Westchester:

Limited geotechnical analysis boring operations continue this week on Thruway property and will not require lane closures. Work activities will be conducted between 7 a.m. and 3:30 p.m. Monday through Friday.

Rockland:

Limited geotechnical analysis boring operations continue this week on Thruway property and will not require lane closures due to work being performed behind barriers. Crews will also inspect and clean the 72-foot storm sewer line that services the existing Thruway property. Work is scheduled between the hours of 7 a.m. and 3:30 p.m. Monday through Friday. 

Tappan Zee Bridge: Webcams to stream construction

bilde

LoHud  By Khurram Saeed  June 7, 2013

The public will soon be able to watch the new Tappan Zee Bridge rise before their wired eyes.

Tappan Zee Constructors has hired EarthCam, a webcam technology company, to stream the five-year construction of one of the largest bridge projects in the nation. The images will be delivered in high definition over the Internet using multiple cameras.

“Everyone is interested in this project and it will help people better understand what we’re doing,” Tappan Zee Constructors spokeswoman Carla Julian told The Journal News on Thursday.

Over the years, EarthCam, based in Hackensack, N.J., has documented major construction projects for governments nationwide, including the rebuilding of the World Trade Center.

Initial plans call for placing three cameras around the project site. Julian said the locations are still to be determined as the Tappan Zee Constructors works out access issues.

She expected ultimately there would be more cameras offering detailed views. She pegged the figure at fewer than 10.

The webcams are expected to go online in the coming months to document all aspects of the $3.9 billion project.

Tappan Zee Constructors and EarthCam are still in the early stages of negotiating costs since the level of service hasn’t been determined, Julian said.

People will be able to see real-time streaming video on the project’s website, www.newnybridge.com, and share their favorite images via social media, including Facebook and Twitter. EarthCam also will edit the images into a time-lapse movie.

“It’s going to capture everything,” Julian said. “It’s going to be really cool.”

There is already some construction activity taking place in the Hudson, but it will intensify in the coming months and years, starting with the installation of the first piles that will support the new parallel spans.

Some 100 construction barges will dot the river by next year and by 2016, after the first new span opens, people will get a chance to see the existing Tappan Zee Bridge demolished.

EarthCam said project teams will keep a close eye on activities since the cameras will have robotic capabilities allowing them to remotely pan the job site and zoom in for a detailed view.

“Our team is thrilled to be the construction camera provider for the Tappan Zee Bridge replacement project,” Lisa Kelly, EarthCam’s strategic sales manager, said in a statement. “The new state-of-the-art bridge will drive economic growth to the area and we’re excited to share views of the progress with the public.”

This isn’t the first major bridge project of which EarthCam has been a part. It documented the construction of the Lake Champlain Bridge in upstate New York a few years ago and is still chronicling the San Francisco-Oakland Bay Bridge project.

The company’s website, www.earthcam.com, also offers links to a network of live webcams around the U.S. and the world.

http://m.lohud.com/localheadlines/article?a=2013306060068&f=1166

 

New Tappan Zee work site bustles with activity

LoHud June 5, 2013 Written by Theresa Juva-Brown

From a giant crane hoisting steel beams to workers tightening bolts on an emerging platform in the river, the site of the new Tappan Zee Bridge was bustling with activity on Tuesday.

To promote the $3.9 billion bridge replacement, project officials took about a dozen members of the media on the river to see construction preparations. Leaders from Tappan Zee Constructors — the team designing and building the new bridge — and the Thruway Authority led the tour on a tugboat suitably named Tappan Zee II.

“This project is progressing and you’re going to see it ramp up over the next several months to the next year,” said Brian Conybeare, a special adviser to Gov. Andrew Cuomo. “More and more equipment arrives almost daily for this pre-construction work.”

The twin span is set to be completed by April 2018. Crews have just wrapped up test borings of the river’s soil and plan to start test pile-driving next month. Pile-driving tests are necessary to ensure that when permanent supports are installed, they are strong enough to hold the new span.

By the middle of next year, close to 100 work barges will fill the river, with about 30 of them being used to hold giant cranes, officials said.

There are about a dozen barges in the river now, with each dedicated to specific tasks. For example, one team is currently setting up vibration monitoring equipment on the existing bridge, while another is focused on building a 1,000-foot platform off the Tarrytown shore. When completed, the temporary trestle, which won’t be attached to the shore, will house a crane for construction.

“The new northern span will be right over our heads,” Conybeare shouted as the tugboat chugged parallel to the existing bridge on its way to the trestle location.

At the site, a 300-ton crane on a barge slowly lifted a hydraulic power unit that operates a vibratory hammer.

The hammer vibrates piles into the river bed, a technique that is less noisy than pounding them in, officials said.

In addition to the Westchester trestle, crews plan to build a similar one off the Rockland shore, though that one will stretch about 1,300 feet, Conybeare said.

37861007001_2434745098001_vs-51ae778ee4b0c77bd45a17cf-1464912386001

Click here to watch the progress on The New NY Bridge:

http://www.lohud.com/apps/pbcs.dll/article?AID=2013306040075

 

 

A New Week of Tappan Zee Bridge Repair Work Coming

Nyack-Piermont Patch  Posted by William Demarest (Editor), 

http://nyack.patch.com/groups/politics-and-elections/p/a-new-week-of-tappan-zee-bridge-repair-work-coming?ncid=newsltuspatc00000001&evar4=picks-2-post

Contruction delays on Tappan Zee Bridge

Work on the Tappan Zee Bridge will continue May 20 through May 24, according to the New York State Thruway Authority.

In case of inclement weather, the work may be postponed.

Monday, May 20 through Friday, May 24

During the daytime hours, the contractor will be working within designated maintenance lane closures and/or underneath the bridge.

Nighttime lane closures scheduled for Monday, May 20 through Friday, May 24

Monday, May 20 and Tuesday, May 21

Work will begin at 8 p.m. resulting in the closure of one left southbound lane and an additional left southbound lane at 10:30 p.m. until 6 a.m. on the Tappan ZeeBridge. In addition, this will result in the closure of two left northbound lanes at 9 p.m. and an additional left northbound lane at 10:30 p.m. until 6 a.m., also on theTappan Zee Bridge.  At least one lane southbound and one lane northbound will be opened to traffic from 8 p.m. to 6 a.m.

During Monday and Tuesday night operations, due to the southbound lane closures, the southbound entrance to the Thruway at Exit 10 (South Nyack) will be closed from 8 p.m. to 6 a.m. and southbound detour signs will be posted through Nyack for the entrance at Route 59 near Exit 11 (Nyack).

During Monday and Tuesday night operations, due to the northbound lane closures, the entrance ramp to the Thruway from Broadway in Tarrytown will also be closed from 9 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Wednesday, May 22

Work will begin at 8 p.m. resulting in the closure of two left southbound lanes and an additional left southbound lane at 10:30 p.m. until 6 a.m. on the Tappan ZeeBridge. In addition, this will result in the closure of one left northbound lane at 9 p.m. and an additional left northbound lane at 11 p.m. until 6 a.m., also on theTappan Zee Bridge.  At least one lane southbound and one lane northbound will be opened to traffic from 8 p.m. to 6 a.m.

During Wednesday night operations, due to the southbound lane closures, the southbound entrance to the Thruway at Exit 10 (South Nyack) will be closed from 8 p.m. to 6 a.m. and southbound detour signs will be posted through Nyack for the entrance at Route 59 near Exit 11 (Nyack).

During Wednesday night operations, due to the northbound lane closures, the entrance ramp to the Thruway from Broadway in Tarrytown will also be closed from 9 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Thursday, May 23

Work will begin at 9 p.m. resulting in the closure of two left southbound lanes and an additional left southbound lane at 11 p.m. until 6 a.m. on the Tappan ZeeBridge. In addition, this will result in the closure of one left northbound lane at 10 p.m. and an additional left northbound lane at 11:30 p.m. until 6 a.m., also on theTappan Zee Bridge.  At least one lane southbound and one lane northbound will be opened to traffic from 8 p.m. to 6 a.m.

During Thursday night operations, due to the southbound lane closures, the southbound entrance to the Thruway at Exit 10 (South Nyack) will be closed from 9 p.m. to 6 a.m. and southbound detour signs will be posted through Nyack for the entrance at Route 59 near Exit 11 (Nyack).

During Thursday night operations, due to the northbound lane closures, the entrance ramp to the Thruway from Broadway in Tarrytown will also be closed from 10 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Friday, May 24

No nighttime work scheduled.

Saturday, May 25 and Sunday, May 26

No work scheduled.

The nighttime lane closures on Monday through Friday are required in order for the contractor to continue with miscellaneous work on the Tappan Zee Bridge.

For the safety of the public and construction workers, motorists are urged to proceed with caution and obey posted work-zone speed limits.

Traffic updates will be broadcast to motorists via Variable Message Signs along the highway and by Highway Advisory Radio 530 AM in the Tappan Zee Bridgecorridor, as well as 1610 AM in the Newburgh area. To see real-time webcam views of the bridge and approaches, go to http://www.thruway.ny.gov/travelers/map/index.html?layer=cameras.

STATE-OF-THE-ART ENVIRONMENTAL MONITORING SYSTEM ONLINE FOR TZ BRIDGE

For immediate release: May 10, 2013
Contact: Dan Weiller (518) 471-5300

Residents kept informed by noise, vibration and air quality monitors
as first pile driving begins on a temporary work platform

As work begins on a temporary Westchester work platform for the New NY Bridge, residents will be kept informed by a first-of-its kind environmental monitoring system with results publicly posted on the internet.

“We are empowering people with information and keeping them up to date on what’s happening with this vital project,” said Thruway Authority Executive Director Thomas Madison. “We are taking unprecedented measures to mitigate noise, vibration and air quality issues and the monitoring system that is now on our website is a major part of that effort.”

As soon as Friday, May 10, Tappan Zee Constructors, LLC (TZC) will begin daytime pile driving work to install the temporary foundation needed to support a trestle in the Hudson River on Thruway Authority property just north of the current bridge in Tarrytown.   The trestle is a work platform that will support a crane for the construction of the easternmost 1000 feet of the new bridge.  The 1000-foot long platform, which will be dismantled when the bridge is complete, helps reduce the amount of dredging required in the Hudson and allows the crews to work from the water and not from the Westchester shoreline.

TZC has installed highly sophisticated monitoring devices at locations near the project site in Westchester. These devices will record the level of sound, vibration and air quality and the data will be available to the public online at www.newnybridge.com as part of the New York State Thruway Authority’s commitment to openness and transparency.

Environmental requirements limit pile driving and other loud construction activities to a maximum of 7 a.m. to 7 p.m. Monday through Friday. There will be no pile driving done on the weekends.

Because the soil under the river is so soft, the pilings will be installed using the vibration technique for the most part.  Vibratory pile driving is much quieter than impact pile driving and will be less intrusive for nearby residents.  Short duration impact pile driving will be used to set the piles into bedrock.  TZC will also use sound mitigating shrouds and other techniques to reduce the noise levels involved.

The EPCs are intended to monitor, minimize and mitigate potential adverse effects related to construction noise, vibration and air quality associated with the project.  In addition to the monitoring systems and specialized pile driving techniques, the Thruway Authority is requiring many other mitigation measures including state-of-the-art controls to limit dust and emissions and receiving deliveries of equipment and supplies mostly by barge, rather than truck.

Construction of the temporary Westchester trestle is expected to last several months.  Construction of a similar work platform on Thruway property near the Rockland County shoreline is expected to begin in July.

For a direct link to the data from the monitors go to: http://newnybridgegallery.com/noise/

###

WESTCHESTER TEMPORARY TRESTLE WORK CONTINUES

For immediate release: May 10, 2013
Contact: Dan Weiller (518)471-5300

WESTCHESTER TEMPORARY TRESTLE WORK CONTINUES

During the week of May 13, work is expected to continue on the Westchester trestle, which is the first of the temporary work platforms to be constructed as part of the New NY Bridge project.

The work will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to the hours of 7 am to 7 pm Monday through Friday. The trestle is a work platform that will support a crane for the construction of the easternmost 1000 feet of the new bridge. The 1000-foot long platform helps reduce the amount of dredging required and allows the crews to work from the water and not from the Westchester shoreline. Noise, vibration and air quality monitors are in place in Westchester and data can be viewed at www.newnybridge.com.

Arborists will be evaluating trees near the project, recording the types, size and health of the trees. This information will help with TZC’s project planning and conservation efforts.

Surveying work and soil sampling for the New NY Bridge Project will continue during the week of May 13 as engineering crews conduct more design surveys at various locations in Rockland, and Westchester in the vicinity of the project, including the Westchester access road location on New York State Thruway property in Tarrytown.

Preconstruction geotechnical investigations will continue as small barge-based drilling equipment will work at various locations throughout the project footprint in the Hudson River. The crews are conducting preconstruction geotechnical surveys to determine soil conditions where future piles will be installed for the new span. Noise levels from the equipment will be at a minimum. The river-based operations will run continuously 24 hours a day Monday through Friday and possibly Saturday.

Westchester:
Limited test-boring operations will continue on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between 7 am and 5 pm Monday through Friday.

Rockland:
At times, traffic on River Road near the South Nyack-Grand View border will be restricted to one lane during weekday daytime hours for utility investigations. Signs and flaggers will be in place to help keep traffic flowing safely.

Limited test-boring operations may start on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 am and 5 pm Monday through Friday.

Soil sampling will be conducted in the westbound shoulder area of NY State Thruway during daytime hours; this operation will not cause lane closures and should not affect traffic

Tappan Zee builders eye private, public parcels as staging areas

LoHud May 8, 2013

Written by Theresa Juva-Brown and Khurram Saeed

Tappan Zee Constructors is eyeing several riverfront locations for construction staging areas, including land owned by Haverstraw where parts of the new bridge could assembled and floated to work sites, officials said.

The bridge project team has shown interest in the 10-acre, former site of the Empire State Chair Factory, but no “hard offers” have been made, Haverstraw village attorney Jay Hood Jr. said.

“We’d love to see the site go to use because it’s sitting there vacant,” he said. “The village is very interested in that because it would bring in very significant revenue.”

About 20 trucks using village streets would deliver bridge parts to the site likely every few weeks. After the parts were put together, they would be shipped downriver, Hood said.

Paul Adler, vice president of Rand Commercial Services, said TZC is also interested in the former Lovett plant property in Tomkins Cove. He said the riverfront property owned by NRG Energy also could be a good staging area for the project, but it remains unclear what NRG wants to do with it.

An NRG Energy spokesman told The Journal News in April the company was considering building a new, gas-fired generating station on the site, which has been vacant since the coal-fired generating station was demolished in 2008. A company spokesman did not return a call seeking comment on Tuesday.

On the other side of the river, project officials are looking for areas where they can load crews onto boats to take them to work sites. Tarrytown officials said TZC had proposed using a public section of RiverWalk Park in Tarrytown, but the plan would have required approval from state legislators and Scenic Hudson, which has rights to the walk.

TZC spokeswoman Carla Julian said that “at this point TZC has no plans to pursue the use of public parkland for staging operations.”

She said she could not discuss possible staging locations until agreements are finalized.

Sleepy Hollow administrator Anthony Giaccio said the River’s Edge property is being considered as place for staging workers. National Resources is currently developing the site as a condominium complex. It also owns Hudson Harbor, the neighboring riverfront condo complex in Tarrytown.

The company did not return requests seeking comment.

Long-term agreements for staging areas won’t be the first deals TZC makes with local property owners. Project crews are already using Petersen’s Boat Yard & Marina in Upper Nyack and the Tarrytown Boat and Yacht Club Marina, officials said.

Thousands of jobs, $2 billion in income forecast for region

LoHud May 7, 2013

Written by, Khurram Saeed and Theresa Juva-Brown

New Bridge Design

Construction of the new Tappan Zee Bridge will create the equivalent of 7,700 full-time jobs and pour $2 billion in disposable personal income into the region in the next five years, according to a new state-commissioned economic study.

“The timing is just incredible — you are talking about putting money into the pockets of working people who for the past three or four years, as a group, had major difficulties,” said Al Samuels, president of the Rockland Business Association. “This is a tremendous asset for folks to come out of the recession.”

Samuels added that when people have more money to spend, local governments also benefit.

“The sales-tax revenue that will accrue to the county and local municipalities is also a big plus,” he said. “It’s good on so many fronts.”

The project is expected to create 38,644 direct and indirect jobs as reported in “job-years,” a standard employment measure used by government on projects. A job-year is one job held for one year. So a trucck driver who works on this project for the next five years will have worked five job-years.

Each year, the project will generate roughly 2,600 construction jobs, 500 office and administrative positions, and some 700 sales and transportation-related jobs, according to the analysis conducted by the state Department of Labor and Empire State Development.

The study predicted employment spikes in management, food services and finance. Additionally, it found that a large construction project like the Tappan Zee “will spur secondary labor demand in retail trade, leisure and hospitality, and population-dependent industries such as health care.”

The study noted that additional analysis was required to figure out specific occupations, when they will be created, and how long they will be needed.

Farrokh Hormozi, an economics professor at Pace University in White Plains, predicted the actual economic impacts of the $3.9 billion five-year project will begin to be felt within a year or so.

“It’s going to boost the economy of the region,” Hormozi said. “This is the type of (project) that cannot be outsourced. … You have to hire local people. Wages and salaries will be made locally. And the impact will be felt locally.”

He said there would be a multiplier effect as workers spend their earnings in their communities. Also, local businesses may directly benefit by providing materials and services for the project or indirectly by seeing their sales increase due to increased demand. That will create income for others, he said.

“These workers, they have to eat, they have to relax and they have go shopping,” Hormozi said.

The job figures were based on $3.9 billion of spending.

“This project is one of the biggest opportunities for us to work collaboratively with local business and contractors on placing New Yorkers in new and exciting jobs,” state Labor Commissioner Peter Rivera said in a statement, adding the agency was prepared to match workers to openings and businesses.

The overwhelming majority of construction and trade jobs will go to local unions, which are covered by a project labor agreement.

But Tappan Zee Constructors, the joint venture that will design and build the new bridge, has already begun accepting résumés from job seekers on its website, http://www.tappanzeeconstructors.com/. The state Labor Department will continue to host career fairs and training to recruit workers.

“The information developed by the state Department of Labor and Empire State Development maps out in new, greater details the jobs that building this new bridge will create throughout the region,” said Thomas Madison, executive director of the New York State Thruway Authority, whose agency requested the study.

Construction of the replacement bridge will generate $3.2 billion in gross domestic product, the study said. The project will create $5.6 billion in total value of all goods produced and $3.7 billion in total personal income.

Tappan Zee Bridge spectator areas may be set up during work

LoHud ; By Theresa Juva-Brown and Khurram Saeed

May 4, 2013

bridge

The massive effort to build a new Tappan Zee Bridge will create a grand spectacle on the river that likely will draw crowds of curious onlookers.

While Tarrytown has plenty of public waterfront where official viewing areas can be set up, that’s not the case across the river. Because there are no public spaces along the South Nyack shore, residents there are concerned that people will wander onto their properties to watch the $3.9 billion project take shape.

Trespassing is already a problem at South Nyack’s Salisbury Point, co-op Vice President Judy Hirschhorn said. The 120-unit riverfront complex has a front-row view of the Tappan Zee that often attracts outside visitors who make themselves at home on the complex’s sprawling lawn. Some cyclists are also notorious for urinating in Salisbury Point’s bushes, she said.

Residents worry that when heavy construction starts on the new Tappan Zee, spectators from all over will flock to their parking lots to get a glimpse of the action.

“We think it’s going to be a huge problem,” she said.

Nyack Mayor Jen Laird-White said some people might go to Nyack’s Memorial Park to get unimpeded — but distant — views of the construction.

One resident has proposed getting the project team to help overhaul Memorial Park, including moving the parking lot to Nyack Municipal Marina and building a pedestrian bridge over the inlet to connect the two areas, she said.

Meanwhile, leaders in Tarrytown are already looking at the village’s waterfront for possible viewing stations, including Losee and Pierson parks and the River Walk.

David Aukland, Tarrytown’s liaison to the project, said he envisions an area where people could not only watch construction but also learn about the project.

“We know the public is interested, and we’d rather them have clear information than have them guess,” he said.

The area, which he said would likely be created by the Thruway Authority and Tappan Zee Constructors, could include binoculars and signs that explain the work. The signs could also feature tags people scan with their smartphones to get information about local wildlife and history, he said.

That would be similar to the approach taken by another huge public works project, the reconstruction of the San Francisco-Oakland Bay Bridge, which has a designated viewing area. The location offers information on the bridge’s history and great views of the self-anchored suspension portion of the new Bay Bridge East Span, said John Goodwin, spokesman for the Metropolitan Transportation Commission.

Brian Conybeare, Gov. Andrew Cuomo’s special adviser on the Tappan Zee Bridge project, said the project team is discussing possible viewing sites with officials on both sides of the river.

“The goal is to find safe, accessible, public areas where people can view the project and take pictures once construction gets going, but no final determination on locations has been made,” he said in an email.

In addition to asking the project team for security fencing and cameras, Salisbury officials plan to post more trespassing signs and work with South Nyack-Grand View police to keep an eye out for unwelcome visitors.

Hirschhorn said measures need to be in place soon. Dredging of the river bottom is set to start in August and will likely attract attention, she said.

“We can’t have people walking all over our property,” she said.

www.NewNYBridge.com

For immediate release: May 3, 2013

The new NY bridge

WESTCHESTER TEMPORARY TRESTLE CONSTRUCTION SCHEDULED TO BEGIN

Work is expected to begin during the week of May 6 on the Westchester trestle, which is the first of the temporary work trestles to be constructed as part of the New NY Bridge project.

The work will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to a maximum of 7:00am to 7:00pm Monday through Friday and is expected begin on Friday May 10. The trestle is a work platform that will support a crane for the construction of the easternmost 1000 feet of the new bridge. The 1000-foot long platform helps reduce the amount of dredging required and allows the crews to work from the water and not from the Westchester shoreline.

In addition, two mooring buoys will be installed in the Hudson River on the Rockland side of the channel. These will be utilized to secure work barges and will be on site for the duration of the project.

Surveying work and soil sampling for the New NY Bridge Project will continue during the week of May 6 as engineering crews conduct more design surveys at various locations in Rockland and Westchester in the vicinity of the project, including the Westchester haul road location on New York State Thruway property in Tarrytown.

Preconstruction geotechnical investigations will continue as small barge-based drilling equipment will work at various locations throughout the project footprint in the Hudson River. The crews are conducting preconstruction geotechnical surveys to determine soil conditions where future piles will be installed for the new span. Noise levels from the equipment will be at a minimum. The river-based operations will run continuously 24 hours a day Monday through Friday and possibly Saturday.

Westchester:
Limited test-boring operations will continue on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 am and 5 pm Monday through Friday.

Rockland:
At times traffic on River Road near the South Nyack-Grand View border will be restricted to one lane during weekday daytime hours for utility investigations. Signs and flag persons will be in place to help keep traffic flowing safely.

Limited test-boring operations may start on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 am and 5 pm Monday through Friday.

 

 

https://tappanzeebridge.randcommercial.com/922/

Nyack Grants Variances For Proposed Luxury Hotel

April 30, 2013 Lohud ; Author Alex Taylor

NYACK — A proposed $19 million boutique hotel on High Avenue came one step closer to reality after the Nyack Zoning Board of Appeals on Monday issued zoning variances for the project.

The developer, WY Management LLC, had sought the village’s approval to convert a vacant manufacturing facility at 400 High Ave. into a 132-room hotel with a steakhouse, radio station and conference center.

The variance was needed to add two floors to the existing structure: a two-story, 40,000-square-foot corrugated metal building next to Oak Hill Cemetery and Exit 11 of the New York State Thruway.

Because the area is zoned as a manufacturing district, a special permit was also needed, officials said.

“Our land use board has done its usual good work,” Nyack Mayor Jen Laird-White said Tuesday. “A great idea looks like it may be coming to fruition as a great project.”

Michael Yanko and Kerry Wellington, co-owners of WY Management, declined to comment Tuesday.

Once built, the hotel will be managed by Nylo Hotels, a boutique chain with hotels in Texas and Rhode Island, with another planned for New York.

Architectural renderings of 400 High Ave. show a stylish, loft-like design, including brick and glass siding and extensive outdoor landscaping. In addition to the 184-seat restaurant, the hotel will feature a bar and fitness center.

The site was formerly occupied by Stoffel Seals Corp., a plasticsand metal manufacturer that relocated to Congers about five years ago. WY Management bought the property for a reported $4.2 million.

A Best Western — the only other hotel in the village — is a block away on Polhemus Street.

The village Planning Board will meet Monday to vote on final site approval — the last step before construction.

“Once the Planning Board gives a final they can commence the building permit process for construction,” Nyack Village Attorney Walter Sevastian said. “They’re getting close.”

The hotel is expected to open late 2014, according to the developer’s website.

Earlier this year, the Rockland County Industrial Development Agency approved exemptions on the sales and mortgage recording tax to help the project. Developers are also negotiating a payment in lieu of taxes on the site.

WY Management recently opened an office at 79 Main St. in Nyack. The developer also is converting the former MetLifeFinancial Services Building in Broxville into multifamily apartments.

SOIL SAMPLING AND SUBSURFACE UTILITY INVESTIGATIONS BEGIN

The New NY Bridge; For Immediate Release: April 26, 2013

Contact: Dan Weiller: (518) 471-5300

Soil sampling and subsurface utility explorations operations will be conducted within the Thruway’s right of ways.  Soil sampling is a requirement of any project that includes excavation work, in order to verify the soil content for proper disposal or reuse. These operations will be conducted between 7 a.m. and 5 p.m.

Surveying work for the New NY Bridge Project will continue during the week of April 29 as engineering crews conduct more design surveys at various locations in Rockland and Westchester in the vicinity of the project, including the Westchester Haul Road location on New York State Thruway property in Tarrytown.

Installation of construction monitoring devices is planned at several locations this week. These devices, which monitor vibration, noise, and air quality, will be in place for the duration of the project to record construction activity impacts.

Preconstruction surveys of properties located near the construction will continue next week. These operations will be conducted by engineering teams and will involve photographing the exterior and interior of structures. Tappan Zee Constructors is coordinating with the property owners for access.

Preconstruction geotechnical investigations will continue as small barge-based drilling equipment will work at various locations throughout the project footprint in the Hudson River. The crews are conducting preconstruction geotechnical surveys to determine soil conditions where future piles will be installed for the new span. Noise levels from the equipment will be at a minimum. The river-based operations will run continuously 24 hours a day Monday through Friday and possibly Saturday.

Westchester:
Soil Sampling will begin on Thruway Authority right-of-ways. Limited test-boring operations will continue on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 a.m. and 5 p.m. Monday through Friday.

Rockland:
There are no land-based boring operations scheduled for the Rockland area for the week of April 29.

 

Environmental sensors to be installed near Tappan Zee construction

Lohud.com; By Khurram Saeed and Theresa Juva-Brown

April 30, 2013  TARRYTOWN — As the Tappan Zee Bridge project continues to ramp up, crews this week will begin installing environmental monitors that will allow residents to track noise, dust and vibration levels during the five years of construction.

The sophisticated shoebox-sizes devices with special sensors will be placed on top of poles at eight locations — four in Tarrytown and four in South Nyack. Losee Park in Tarrytown is set to get the first one by Wednesday.

Devices also will be installed at the Quay, an 89-unit condo complex in Tarrytown, south of the bridge in the neighborhood of Irving, and on New York State Thruway Authority property near South Broadway, state officials said.

Tappan Zee Constructors, the team engineering and constructing the $3.9 billion bridge, the Thruway Authority and community leaders are working to pin down specific locations for the devices in Rockland County, said Brian Conybeare, a special adviser on the project.

“The installation process is just getting under way, but once construction starts the public will be able to view the data from the monitoring stations 24 hours a day on our website, www.newnybridge.com,” he said.

Sensors devoted just to measuring construction vibrations have already been installed on the piers of the existing Tappan Zee Bridge, officials said.

Among the likely Rockland locations to receive a monitor is the 120-unit Salisbury Point Cooperative in South Nyack. TZC also wants to add a device at South Nyack Village Hall, but a village representative said officials had not been consulted about it.

Jerry Ilowite, head of South Nyack’s Tappan Zee Bridge task force, said TZC was supposed to present a monitoring and mitigation plan that would let the village weigh in on the best locations for the devices.

“I have no idea what they’re going to monitor or where or why they’re choosing the locations that they are,” Ilowite told The Journal News on Monday. “We have had no opportunity to contribute at all.”

After The Journal News inquired about the situation, a TZC representative called Ilowite on Monday afternoon to schedule a meeting.

The project team also plans to start taking photos and reports of property conditions before construction starts. This is done in case property owners later claim vibrations from the work damaged their homes.

Tori Weisel, president of the Irving Neighborhood Preservation Association, said about a dozen Irving residents plan to meet with TZC officials Wednesday to discuss which homes will be eligible for preconstruction surveys.

Meanwhile, the state has started to install new fencing along Van Wart Avenue to shield homes from traffic on the Thruway maintenance road. Weisel said more steps are needed.

“There is progress … but the true issue is not that fencing — it’s sound barriers and making sure our foundations are not rocked and cracked,” she said

Rand Commercial Services Weekly Real Estate Report- A Bridge To The Future

 

 

 

 

Watch The New NY Bridge Animation

Tappan Zee Constructors recommended to build new Tappan Zee Bridge

Tappan Zee Bridge Presentation: The state Thruway Authority on Dec. 5, 2012 released three designs to build a new Tappan Zee Bridge. The $3.1 billion bid from Tappan Zee Constructors has apparently won the state’s recommendation. Video by WGRZ/wgrz.com

Tappan Zee Constructors has won the state’s advisory committee recommendation to build the new Tappan Zee Bridge for $3.1 billion, a source close to the selection process told The Journal News on Wednesday.

The consortium, which includes the company that built the existing 3-mile Tappan Zee 57 years ago, offered the least expensive bridge plan among the three teams competing for one of the largest public works projects in the country.

The suggested design for the Tappan Zee replacement, a cable-stayed bridge, has oddly angled towers on each span, a feature so unique it’s never been used in the United States, a state official said. He added that he knows of only one bridge — in Russia — with a similar element.

The twin-span bridge would also include a concrete deck on top of steel girders. Like the other two options, it would be strong enough to carry trains in the future. In addition, it would have deck connections in four places that can be used to turn traffic around in emergencies.

The crossing would have 35 piers in the river and be made up of 350-foot long spans to create the road deck. Those spans would be six times longer than the current ones. The proposal also calls for less dredging during construction than the state initially said would be required.

The Thruway Authority on Wednesday released the three proposals for the new bridge, but did not identify each team’s proposal, citing federal rules.

“To get a bridge to this point in a year was really a fantastic accomplishment,” Gov. Andrew Cuomo said at a presentation at the Capitol.

Officials also announced that the state’s 38-member review panel had chosen the $3.1 billion bid because “they determined it was the best value,” said Brian Conybeare, a special adviser on the project.

The three proposals pegged the replacement cost between $3.1 billion and $4 billion, all much less than the initial construction price tag of $5.2 billion. Still, the proposal prices are preliminary estimates and don’t include another $600 to $800 million for expenses such as financing and management, state officials said.

American Bridge Co., which built the Tappan Zee, and Fluor Enterprises are members of the recommended Tappan Zee Constructors team. Those two firms are also involved in the $6.4 billion reconstruction of the San Francisco–Oakland Bay Bridge. A joint venture involving Kiewit Infrastructure and Skanska USA and a partnership of Bechtel Infrastructure and Tutor Perini also submitted proposals.

The construction time for each proposal was more than five years. Work is expected to begin next year.

Though the state’s panel has selected Tappan Zee Constructors, the Thruway Authority board makes the final decision. The board is set to vote for a winning team on Dec. 17. Until then, officials said the public can weigh in on the proposals on the bridge project’s website: http://www.newnybridge.com.

The design review team’s recommendations will be a major factor in the final decision, said Thomas Madison, the Thruway Authority’s executive director.

The contract award will have a ripple effect for homeowners in Rockland and Westchester.

A group of six neighbors in South Nyack are waiting to learn if they’ll remain in their homes during construction or they’ll be bought out, as most of them want. The state originally planned to take the homes but reversed that decision in May. The homeowners have asked the state to reconsider.

Homeowners said state officials have told them the contract award would allow the state to finally make a decision.

“It would be good to finally come to some kind of closure because everything has been up in the air for the longest time,” said John Cameron, who has lived in his South Broadway home with his wife, Hope Elliott Cameron, for the past six years.

A state official told Cameron and his neighbors they have reason to be “optimistic,” which he believes means the state will ask the winning bidder to buy the homes, he said.

Not everyone was satisfied with Wednesday’s developments, though.

Veronica Vanterpool, executive director of Tri-State Transportation Campaign, charged that the state’s preview of the proposals was incomplete. Her group has pushed for the plan to include mass transit along the Interstate 287 corridor.

“The proposals are still unclear about what mass transit ready means,” Vanterpool said in an email to The Journal News. “We look forward to an announcement of the TZB transit task force so these details can be hammered out. The proposals came in significantly below the projected $5.2 billion price tag, creating a greater opportunity to incorporate low-cost, bus rapid transit improvements into the project.”

Riverkeeper, the Hudson River’s leading advocacy group, was also not eager to endorse any of the proposals. Riverkeeper has criticized the state’s plan for not adequately addressing how the project could harm marine life.

“Riverkeeper is not surprised that the state has identified a reduced dredging option,” president Paul Gallay said. “We and the rest of the public need more information as to how this will affect the project’s overall environmental impacts, and we will seek to have those discussions with the state as soon as possible.”

Al Samuels, president of the Rockland Bussiness Association, said he agreed with the selection committee’s recommendation, which he said “makes the most sense.”

Plans for the new bridge have moved swiftly since last year, when the Obama Administration named it one of 14 top priority infrastructure projects across the country. In September, the Federal Highway Administration gave final approval to the project’s environmental study, allowing the replacement plan to proceed

It remains unclear, however, whether the federal government will give the state a low-interest loan. In its loan application, the state had said a new bridge could cost up to $5.9 billion. Without a significant loan, state officials warned of soaring tolls. Officials had said the current $5 cash toll could rise to $14.

Rockland Legislature Chairwoman Harriet Cornell said Wednesday she wants to know what a smaller price tag means for those toll increases.

“I’ve talked for years about not putting the tolls on the backs of commuters,” Cornell said.

 

New Tappan Zee Bridge Project Update : Video

New Tappan Zee Bridge Project – Project Meeting July 25, 2012

Here is the video:

The New Tappan Zee Project :Video

Executive Director Thomas J Madison on the LoHud Editorial Spotlight discusses the new Tappan Zee Bridge and its impact on the Hudson Valley:

 

Some property information provided by CoStar, Loopnet, HGAR, Yelp, Rand Commercial Services and other public sources.