PROJECT UPDATE – WESTCHESTER GIRDER INSTALLATION

update

For immediate release: Nov. 19, 2015

WESTCHESTER GIRDER INSTALLATION OVER METRO-NORTH RAILROAD TRACKS CONTINUES THIS FRIDAY EVENING
Overnight Closures of the I-87/I-287 Exit 10 On-Ramp Scheduled for Nov. 19 and Nov. 20

Next week, Tappan Zee Constructors, LLC (TZC) will continue installing structural steel girder assemblies from the new bridge’s Westchester landing in Tarrytown. The assemblies will connect the future westbound span’s on-land abutment to the first offshore support pier in the Hudson River. TZC is installing the girders by literally pushing them west over the Metro-North Railroad Hudson Line’s tracks toward the first pier in the river, as seen in this animation. As the operation progresses, additional girders are being connected to the assembly and pushed farther westward. TZC is closely coordinating the effort with Metro-North Railroad, ensuring that the operation maximizes safety for both workers and the public and minimizes impacts to rail service.

With the entire operation anticipated to conclude by the end of the year, the remaining work over the Metro-North tracks will occur during two Friday overnights, with the next scheduled for this Friday evening, Nov. 20. Metro-North has adjusted its schedule slightly to allow the work to be completed. TZC will suspend construction activities when commuter trains pass through the area, resuming when given the “all clear” instruction by Metro-North.

Across the river, TZC has completed steel girder installation near the Rockland shoreline, connecting the new bridge’s abutment to already-installed support structures in the Hudson River.

The I Lift NY super crane will continue placing larger girders across the river, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

All-Electronic Toll Collection Gantry Work
Construction of the project’s temporary all-electronic toll collection (AETC) system in Rockland will continue near the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to southbound New York State Thruway (I-87/I-287). The work will necessitate closing the on-ramp during the overnights of Thursday, Nov. 19 and Friday, Nov. 20. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the graphic below. No lane closures are planned for this work next week.

Ramp Closures Near the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Thu., 11/19 9 p.m. – Ramp Closure 5 a.m., Fri., 11/20 Southbound I-87/I-287
exit 10 on-ramp
Fri., 11/20 9 p.m. – Ramp Closure 5 a.m., Sat., 11/21 Southbound
exit 10 on-ramp

Tower Construction
Construction will continue on the new bridge’s iconic towers, which will eventually rise 419 feet above the river. Innovative self-climbing jump forms enable TZC workers to build the towers in segments that progressively “jump” up from the foundations to their full height. Within the jump forms, workers assemble steel reinforcement cages that are then encased in concrete, one segment atop the previous one and so on. Eight towers will be constructed on the project’s football-field-long main span pile caps over the coming year, as seen in this animation.

Deck Panel Installation
TZC is continuing to install nearly 6,000 high-strength concrete deck segments for the new crossing’s approach spans. Project cranes are lifting the prefabricated deck panels into place atop previously-installed structural steel girders. The deck segments are prefabricated at an off-site location and barged down river from the project’s Port of Coeymans facility in Albany County. TZC will continue installing the approach span deck sections over the coming year.

Installation of Noise Barriers in South Nyack
Next week will see continued removal of the noise walls located along the northbound Thruway and the construction of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road in South Nyack. The work involves drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
Westchester and Rockland Marine Units are continuing extensive patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

###

The New NY Bridge November 2015 Newsletter

November 2015
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

As more and more piers are connected by steel-blue girder assemblies, the New NY Bridge project’s iconic towers continue to advance skyward.

As the summer turns to fall in the Lower Hudson Valley, progress continues to march forward on the New NY Bridge project. More and more of the high strength structural steel-blue girder assemblies are being placed across the Hudson River by Tappan Zee Constructors, LLC (TZC), largely with the help of the massive I Lift NY super crane. At both shorelines, however-where shallow waters prevent the use of the super crane-alternate methods were necessary, including the use of construction platforms. The Westchester landing posed a further shoreline challenge: how to safely install the girders over the Metro-North Railroad Hudson Line tracks?

While most of the new bridge’s steel-blue girder assemblies are being placed across the Hudson River with the barge-based I Lift NY super crane, the location from the Westchester landing to the first pier in the river is inaccessible to the monumental machine. Tappan Zee Constructors, LLC is using an innovative yet simple alternative method to install the girders in this area, as detailed in this video.

New NY Bridge fans looking for a firsthand view of construction from the Rockland shoreline now have a “front row seat” to the action. Nyack’s new fishing pier at Memorial Park is now open and offers spectators a sweeping view of the Hudson River and the bustling project site.

After successfully installing structural steel girders between the Westchester abutment and a nearby pier, Tappan Zee Constructors, LLC (TZC) moved forward with the next stage of operations this week. In a remarkable feat of engineering, crews carefully pushed the massive steel-blue materials further west, over the Metro-North Railroad Hudson Line and toward the next pier in the Hudson River.
Frequently Asked Questions
Q:
Why does the current Tappan Zee Bridge need to be replaced? 
A:
The Governor Malcolm Wilson Tappan Zee Bridge opened to traffic in 1955 and is a vital artery for residents, commuters, travelers, and commercial traffic. The bridge, which was designed to carry up to 100,000 vehicles per day, currently handles an average of 138,000 daily, and traffic congestion and delays are regular occurrences. Heavy traffic, narrow lanes and the lack of emergency shoulders contribute to congestion and frustration for motorists and can create unsafe driving conditions. As a result, the bridge has twice the average accident rate per mile as the rest of the 574-mile Thruway system. In recent years, hundreds of millions of dollars have been spent to maintain and repair the bridge. If the current bridge were not being replaced, the state would need to spend an additional $3 to $4 billion over the next 20 years to ensure its structural integrity.

Steel Girder Installation Continues

For immediate release: August 20, 2015

STEEL GIRDER INSTALLATION CONTINUES NEAR THE ROCKLAND LANDING

Tappan Zee Constructors, LLC (TZC) will continue installing structural steel girders for the New NY Bridge project next week. Smaller girder sections will be lifted into place by cranes from the Rockland trestle near the South Nyack shoreline. Local ironworkers will then bolt together the steel blue girders and cross beams that will support the new bridge’s concrete road deck.

In addition, the I Lift NY super crane will continue placing larger girder assemblies next week and beyond, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.

Two northbound lanes of the New York State Thruway (I-87/I-287) will be closed during the overnights of Monday, August 24 and Tuesday, August 25 across the existing Tappan Zee Bridge to facilitate surveying efforts.

I-287/I-87 Lane and Ramp Closures on the Tappan Zee Bridge

DATE: CLOSURES BEGIN: CLOSURES END: LOCATION:
Mon., 8/24 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Tue., 8/25 Northbound Across the
Tappan Zee Bridge
Tue., 8/25 8 p.m. – One right lane
9 p.m. – Two right lanes
5 a.m., Wed., 8/26 Northbound Across the
Tappan Zee Bridge

Dredging Operations Continue
TZC will continue the second stage of dredging operations near the Westchester shoreline as part of the preparation for removing the existing bridge and completing the landing of the new southern span. Dredging is allowed during a three-month period from August 1 to October 31 in specified locations and will be conducted 24/7 to complete the required dredging during the short window of time. The window was established to avoid impacting migration and spawning patterns of endangered sturgeon and other fish species.

Installation of Noise Barriers in South Nyack
Next week also will see continued installation of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road in S. Nyack. The work will involve drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.

Additional work includes:

  • Pile cap foundation construction
  • Placement of Steel Girder assemblies
  • Dredging
  • Main span foundation construction
  • Landing abutment concrete work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge
  • Westchester landings utility work

Boater Safety
During the summer months, Westchester and Rockland Marine Units will add extra patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.

The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

 

The New NY Bridge July Newsletter

July 2015
New NY Bridge Project Monthly Newsletter
Forward   |    Home   |    Archives 

Heavy Metal:

Bridge Starts Taking Shape with Installation of First Section of Structural Steel


Following months of careful planning and with the use of the project’s king of cranes, the New NY Bridge team installed the span’s first section of structural steel on June 17: a 410-foot segment of welded girders that will support the road deck.

READ MORE

With the 2015 recreational boating season hitting full stride this weekend as boaters celebrate Independence Day on the water, the New NY Bridge project team and local law enforcement officials remain committed to helping all boaters navigate safely near the work area. Boaters are reminded to be extra vigilant around commercial vessels and the construction zone, especially the no-wake low-speed zone at the Tappan Zee Bridge.

 

READ MORE

Oyster reefs were once a predominant feature of the Hudson River, supporting vast and diverse communities of aquatic life. But past decades of pollution and overharvesting led to a decline in oyster populations in the area to near-extinction. In recent years, however, there have been promising signs of recovery.

 

 READ MORE

The addition of a third floating concrete batch plant this week enables the New NY Bridge project to shift into an even higher gear. Capable of delivering 180 cubic yards of concrete per hour – more than twice as much as the initial two batch plants combined – the new mixing platform will supply concrete for the new bridge’s remaining foundations and piers as well as its 419-foot towers, which will begin later this summer.

 

READ MORE

After a stunningly beautiful trip down the Hudson River, the first 12′ tall, 400′ long section of structural steel arrived at the New NY Bridge construction site on Thursday June 10, 2015. The girder sections, weighing up to 1,100 tons are assembled at the Port of Coeymans in Albany County and then barged to the project site. The trip can take from 12 to 20 hours depending on weather, tides and other conditions. The individual steel girders, totaling 31 miles in length before assembly, are all made in the USA and will support the road deck of the new twin span bridge. The girders will be set in place by the I Lift NY crane in the coming days.

 

 READ MORE

Frequently Asked Questions
Q:
How can my company apply for subcontracting work on the project?
A:
Businesses interested in obtaining contracts for the New NY Bridge project should reach out to Tappan Zee Constructors, LLC through the TZC website, TappanZeeConstructors.com.
Get Your E-ZPass® “On-the-Go”at the New NY Bridge Community Outreach Centers
View the latest issues of the New NY Bridge Quarterly Magazine
Visit NewNYBridge.com to subscribe for periodic email updates
HOW TO GET INVOLVED
Follow Us on Twitter

@NewNYBridge

Call the Project Hotline

1-855-TZBRIDGE

(1-855-892-7434)

Community Outreach Centers

Westchester: 2 N. Broadway, Tarrytown, NY

Rockland: 142 Main Street, Nyack, NY

Mon-Fri: 11am-7pm | Sat-Sun: 11am-4pm

Visit the Project Website
Email Us
Construction Viewing Platform

Scenic Hudson RiverWalk Park, Tarrytown, NY

Next to the Tarrytown Senior Center at
240 West Main St.

©2015 New York State Thruway Authority

WORK CONTINUES ON TEMPORARY ALL-ELECTRONIC TOLL COLLECTION SYSTEM

update
Several Weeks of Weekday Overnight Triple-Lane Closures
on New York State Thruway (I-87/I-287) Start May 4

Several weeks of weekday overnight triple-lane closures of southbound New York State Thruway (I-87/ I-287) will begin Monday, May 4. The Monday-through-Friday closures will start as early as 7 p.m. with the closure of one lane near exit 11 (Nyack – South Nyack – US Route 9W) to the Tappan Zee Bridge, followed by a second lane closed at 9 p.m. and a third at 10:30 p.m. All lanes will reopen 6 a.m., Tuesday through Friday and 8 a.m., Saturday. At least one lane will remain open at all times, except during the periodic traffic holds described below.

The lane closures are necessary to allow Tappan Zee Constructors, LLC (TZC) to modify the highway for a temporary all-electronic toll collection system that will be employed until a permanent system is constructed in the location of the current toll plaza in Tarrytown.

In addition, periodic closures of all four lanes of the southbound Thruway in the vicinity of exit 11 (Nyack – South Nyack – US Route 9W) will occur between 8 p.m. and 4 a.m. during the overnights of Wednesday, May 6 and Thursday, May 7. To ensure the public’s safety, the New York State Police will stop and hold all traffic approaching the area immediately before the closures go into effect. Motorists will be permitted to enter the Thruway from all ramps during the closures. The complete closures are necessary to move equipment from the right shoulder to the left shoulder.

Finally, the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to the southbound Thruway will be closed from 10 p.m., Tuesday, May 5 to 5 a.m., Wednesday, May 6. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown on the following graphic. The closure will allow TZC to mobilize a crane that will place concrete slabs for the all-electronic toll collection system.

All planned work is subject to postponement due to weather conditions.

River Road in South Nyack
River Road utility work will continue the week of May 4. The work may require reducing River Road to one lane at times. TZC flag persons will direct traffic as needed and additional signage as well as other safety measures will be in place.

Foundation Work on the New Bridge
Marine crews will continue working on the foundations for the new bridge next week by placing reinforcing steel and concrete in the piles, main span pile caps and approach span pile caps. The high-strength concrete is made on site by the project’s two floating batch plants. Teams also will erect formwork for the cast-in-place pier columns, which eventually will support the new bridge’s road deck. With only a small percentage of piles left to install, pile driving operations will continue next week. Pile driving is restricted to 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.

Crews also will continue working on the bridge’s landings at the Rockland and Westchester shorelines. The abutments, comprised of steel and concrete, will serve as strong bases where the new crossing meets the landside roadway.

TZC will continue concrete placement for foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and is delivered by truck to the Rockland trestle located off the Thruway’s southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.

Additional work includes:

  • Pile cap foundation construction
  • Main span foundation construction
  • Concrete placement for foundations
  • Landing abutment concrete work
  • River Road utility work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on the existing bridge

Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.

Massive crane arrives at site of new Tappan Zee Bridge

TZ Under construction

By Judy Rife; Times Herald-Record

Posted Oct. 6, 2014 @ 7:33 pm

NYACK – One of the world’s largest floating cranes, in the wings in Jersey City since January, finally took center stage at the construction site of the new Tappan Zee Bridge on Monday. The crane, known as the I Lift NY, got the kind of gushing welcome that celebrities are accustomed to – including a declaration of love from Gov. Andrew Cuomo.

“I truly love this crane,’’ said Cuomo, surrounded by dozens of crane-ogling journalists and officials on a 149-passenger ferry off Piermont. “Every New Yorker should love this crane because it’s saving us a lot of money – as much as a billion dollars.”

The crane was a factor in the ability of Tappan Zee Constructors to win the $3.1 billion contract to design and build the new TZB, underbidding its two competitors by almost $1 billion in the process. Its superior lifting ability will allow much of the new bridge’s superstructure to be assembled off site and hoisted into place, slicing time and expense off the construction bill.

Darrell Waters, TZC’s president, said the crane will start work this week, and construction, concentrated in the river until now, will become more vertical and visible by the end of the year.

“We are 24 percent complete and we are on time and on budget,’’ said Waters, adding that 65 percent of the piles that will ultimately support the new bridge’s piers have been installed.

What surprised the welcoming party on the ferry was how ordinary the partially collapsed crane looked as it glided toward the TZB at four knots – despite sitting on a barge the size of a football field.

Its jaw-dropping size only became apparent when the ferry swung around it and the crane could be viewed against the bridge – and then it towered over the bridge and the 130 other pieces of construction equipment, including 31 cranes, in the water.

TZC will fill the barge with water and further collapse portions of the crane Tuesday in preparation for moving the I Lift NY beneath the bridge, 139 feet above the Hudson at low tide, Wednesday. Waters said he expects to have three feet of clearance.

As the ferry returned to Piermont, Cuomo was peppered with questions about what the tolls will be when the new bridge opens in 2018, a subject he has avoided in this election year.

The governor said that the state needs “a little more information” before it can speculate about the tolls. He pointed out incentives and penalties in the construction contract, as well as additional state or federal aid, could ultimately affect the project’s cost and the amount to be raised through tolls.

“It’s four years down the road,’’ he said.

judyrife@gmail.com

http://www.recordonline.com/article/20141006/NEWS/141009636/101008/NEWSLETTER100

Super Crane to Travel up the Hudson 10/6/2014

update

For immediate release: October 5, 2014

I LIFT NEW YORK SUPER CRANE SCHEDULED TO TRAVEL TO
NEW NY BRIDGE PROJECT SITE ON MONDAY, OCTOBER 6

The I Lift NY super crane, one of the world’s largest floating cranes, is scheduled to travel from New York harbor up the Hudson River to the New NY Bridge project site on Monday morning October 6.

The giant crane, which will help build the new bridge and remove the old bridge more quickly and economically, is expected to leave its berth early Monday morning and arrive at the project site between 11 am and noon. However, the trip is subject to schedule changes or cancellation due to weather conditions or other safety factors.

You can track the crane’s transit up the Hudson using the New NY Bridge GPS tracking system here.

I Lift NY
has a height of 328 feet and a 1,900-ton lift capacity. Built on a 384-foot barge, it has no navigational power of its own, and will be guided to the project site by two tugboats. You can find more information here.

The crane was christened the “Left Coast Lifter” for its role in a major bridge construction project in the San Francisco Bay area. It made the 6,000-mile journey to New York via the Panama Canal in January, 2014.

 

A Visit from the Past Original Tappan Zee Engineer Visits New NY Bridge Project

September 16, 2014

The New NY Bridge Rockland Community Outreach Center welcomed a surprising visitor earlier this month: an engineer from the original Tappan Zee Bridge construction team. Jerry Sondack was in his late 20s when he helped build the existing bridge more than half a century ago. Now, as the replacement bridge rises out of the Hudson River, the 90-year-old World War II veteran stopped by to learn how the new structure is being engineered to meet the needs of the growing region.

As a young man living in New York City in the 1950s, Sondack heard about the Thruway’s plans for a new bridge and was eager to contribute. He approached engineers from Madigan-Hyland, the engineering firm that built the Tappan Zee Bridge, asking how he could get involved.

Eventually, Sondack was engaged full time on the project. One of the many former military men who worked on construction of the Tappan Zee, he says their experience in America’s armed forces helped foster a safe and efficient working environment amid the immense construction equipment and materials.

Sondack’s day-to-day activities included surveying the Tappan Zee Bridge’s caissons, which are hollow concrete bases that support much of the bridge.

Now, as the region’s growing population increases demands on the aging Tappan Zee Bridge, Sondack told project officials, “[Rockland] county needs a bridge of greater capacity; the old bridge won’t be able to handle this in the future. We need a new bridge that will sustain the flow of people into Rockland in the years ahead.”

Sondack observed the scale of the New NY Bridge project evokes the project he worked on all those years ago. “When you take on a project this grand, the amount of coordination and tight-knit supervision is extraordinary,” he noted.

Sondack’s work on the landmark Tappan Zee Bridge project boosted his career, helping him land future jobs and pursue other business opportunities. After the project’s completion, he settled in the Spring Valley area of Rockland County for over a decade. Now as a retiree, he looks forward to crossing the new bridge when the first span opens in 2016.

The New NY Bridge Community Outreach Centers in Westchester and Rockland counties are open seven days a week. For locations and hours, visit NewNYBridge.com/contac

No Construction For Christmas Day!

The new NY bridge

For immediate release: December 20, 2013

NO CONSTRUCTION ACTIVITIES PLANNED FOR CHRISTMAS DAY, RAMP RE-OPENS TO ACCOMMODATE HOLIDAY TRAVELERS

No construction activities are scheduled for the New NY Bridge project on Christmas Day, Wednesday, Dec. 25, and the Tarrytown entrance ramp from South Broadway to the Tappan Zee Bridge has been temporarily re-opened to traffic to accommodate holiday travelers.

Referred to as “Ramp E” by the New York State Thruway Authority, the ramp from Route 9 southbound to I-87/I-287 was closed earlier this month to allow Tappan Zee Constructors, LLC (TZC) to utilize the area surrounding the ramp for construction access to keep construction vehicles off local streets, perform underground utility work and shift Thruway traffic headed toward the Tappan Zee Bridge onto the ramp area in 2014.

The ramp, which has routinely closed for bridge-related maintenance projects, will close again in January and will remain closed for the duration of the project. Its complete closure is required for the construction of the New NY Bridge, and to ensure safety for the traveling public and construction workers.

Excavation and preparation for the installation of permanent sound barriers continues along I-87 northbound/I-287 westbound in the area south of exit 10 in Rockland County.

This weekend, one of the country’s most famous floating cranes will weigh anchor and begin its journey, traveling from Oakland Harbor, near San Francisco, to the site of the New NY Bridge project. Named “The Left Coast Lifter” for its use in the replacement of the eastern span of the San Francisco—Oakland Bay Bridge, the floating crane will be used in the construction of the New NY Bridge.

A highly experienced crew of mariners will guide the 400-foot-long crane along the West Coast, through the Panama Canal and the Gulf of Mexico, and then up the East Coast before arriving in the Hudson River. The trip is approximately 6,000-miles long and will take between six and eight weeks to complete.

Mariners should be aware that TZC will be installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website at NewNYbridge.com under the “Boater Safety” icon.

Ongoing Operations:
• Rockland access ramp modifications
• Armoring of dredge channel
• River Road utility work
• Test pile program
• Permanent pile installation
• Temporary Rockland trestle construction, including pile driving on weekdays7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Support for river-based work from the Rockland shoreline
• Reinforcement steel pre-assembly at bridge yard

As New Bridge Construction Begins, Boaters Must Practice Defensive Driving

New City Patch , Posted by  (Editor) , 

New City Patch Article Here

6430fd382faebe6b4396d23c2321c533

With permanent piles for the New Tappan Zee Bridge now going in, navigating the Hudson is getting increasingly more challenging.

There’s a very necessary and informative forum on Hudson River Boating Safety Wednesday at 7 p.m. in Tarrytown Village Hall at One Depot Plaza.

Bridge officials in their latest weekly press release advised mariners to exercise extreme caution where the new piles are going in – “in the vicinity of the side channels under the existing bridge.”

“New temporary navigational lights have been installed to further define the 600’ navigation channel under the main span. Both temporary and permanent piles are illuminated at night.”

The U.S. Coast Guard recently issued revised safety information, establishing a “Regulated Navigation Area” from 300 yards north of the bridge to 200 yards south:

“All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard in the future may temporarily prohibit all vessel traffic in the RNA for safety purposes.”

More boating safety information can be found on theNewNYBridge website here, including exact lighting regulations and approved mooring locations.

And for a previous Patch article on the difficulties of navigating the waters at night, click here.

 

 

 

 

 

 

 

 

 

TZ Construction to Begin On River Road, S Nyack

new

For immediate release: September 6, 2013

UTILITY WORK BEGINS ON RIVER ROAD

Tappan Zee Constructors, LLC will begin utility work on River Road in South Nyack the week of Sept. 9. This work will continue through November and will involve reducing the roadway to one lane during daytime hours. During off hours the road will have temporary coverings in place that may create uneven driving surfaces. Motorists and bicyclists should slow down and use caution in the area.

Construction of the Rockland County trestle will continue and include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to a maximum of 7 a.m. to 7 p.m. on weekdays and, occasionally, from 12 noon to 7 p.m. on Saturdays. The trestle is a work platform that will support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required.

Impact pile driving will continue as part of the ongoing test pile program and will continue through October at various locations for future pile foundations during the same timeframe as above. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.

The Coast Guard boating safety information can be found on the project website, NewNYBridge.com, under the boating safety icon.

On Monday, Sept. 9, and Tuesday, Sept. 10, one southbound right hand lane and shoulder on I-87/I-287 between exit 11 and the Tappan Zee Bridge will be closed from 10 a.m. to 3 p.m. for shoulder work. On Wednesday, Sept. 11, and Thursday, Sept. 12, one northbound right hand lane and shoulder on I-87/I-287 between exit 8 and exit 9 will be closed from 10 a.m. to 3p.m. for shoulder work.

Ongoing operations:
• Dredging operations will continue 24/7
• Test pile program
• Rockland bulkhead construction and Dock Extension at Rockland under existing bridge
• Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
• Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
• Survey inspections on existing bridge
• Mobilization at the exit 10 staging area
• Support for river-based work from the Rockland shoreline

Pile Driving Set To Begin This Week

The New Tappan Zee Bridge

For immediate release: July 26, 2013

TEST PILE PROGRAM IMPACT PILE DRIVING SET TO BEGIN,
ROCKLAND THRUWAY DOCK CONSTRUCTION GETTING UNDERWAY

Tappan Zee Constructors, LLC (TZC) is scheduled to begin impact pile driving as part of the ongoing test pile operation this week. The test pile installation will continue over the next two to three months at the proposed locations of the foundations for the New NY Bridge. The test pile program will verify subsurface conditions in the river and the structural capacity of the pilings.

Under the Final Environmental Impact Statement, the hours of impact pile driving are restricted to 7 a.m. to 7 p.m., Monday through Friday and 12:00 noon to 7 p.m. on Saturday. There is no impact pile driving allowed at night or on Sundays. Noise monitors are in place along the Rockland and Westchester shorelines and the data is available at www.NewNYBridge.com.

Construction of the New York State Thruway’s temporary dock at the Rockland Maintenance facility on River Road in South Nyack will begin the week of July 29. TZC will reconstruct a maintenance dock that was damaged during Superstorm Sandy. This new dock will allow the Thruway to continue its normal maintenance work on the existing Tappan Zee as the construction activities for the New NY Bridge get underway.

Orange and Rockland Utilities will install new utility poles near River Road in South Nyack to support utility relocations which are needed for the New NY Bridge project. These operations may require temporary lane closures and will be performed by the utility.

Ongoing operations:
· Test pile program
· Rockland bulkhead construction
· Temporary Westchester trestle construction including pile driving on weekdays from
7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Rockland and Westchester environmental monitor installations
· Geotechnical land borings
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline

Westchester:
Survey crews will be conducting surveys in the toll plaza area in Tarrytown on Wednesday, July 31 requiring temporary closures of toll lanes conducted one at a time.

Rockland:
Geotechnical boring operations to investigate subsurface soil conditions will be conducted in the northbound lanes of I-87/I-287 and will require a temporary lane closure between the existing bridge to Interchange 10 in South Nyack from 10 a.m. to 3 p.m. on Monday, July 29 through Wednesday, July 31. Southbound lane closures will be required from Interchange 10 to the existing bridge between 10 a.m. and 3 p.m. on Thursday, August 1 and from 10 a.m. to 2 p.m. Friday, August 2.

Holiday Construction Schedule for TZ Bridge

The new NY bridge

For immediate release: June 28, 2013

NO WORK SCHEDULED JULY 4–NEW NY BRIDGE CELEBRATES INDEPENDENCE DAY

Tappan Zee Constructors, LLC (TZC) will not work on July 4 in observance of Independence Day.

Preconstruction activities will continue throughout the week; however, TZC will have no lane closures in order to keep traffic moving on the Thruway.

Ongoing operations:

– Cleaning and preparation for future construction of the Thruway’s Rockland Bulkhead
– Construction of the temporary Westchester work trestle which includes pile driving operations that will occur weekdays from 7 a.m. to 7 p.m. (except for July 4)
– Survey inspections on existing bridge
– Rockland environmental monitor installations continue
– Geotechnical land borings
– Mobilization at the Exit 10 staging area
– Support for river-based work from the Rockland shoreline

Westchester:

Limited geotechnical analysis boring operations continue this week on Thruway property and will not require lane closures as work will be performed behind barriers. Work may be scheduled between the hours of 7 a.m. and 3:30 p.m.

Rockland:

Limited geotechnical analysis boring operations continue this week on Thruway property and will not require lane closures as work will be performed behind barriers. Work may be scheduled between the hours of 7 a.m. and 3:30 p.m.

HUDSON RIVER TEST BORINGS FOR THE NEW NY BRIDGE COMPLETED

update

For Immediate Release: June 7, 2013

HUDSON RIVER TEST BORINGS FOR THE NEW NY BRIDGE COMPLETED

The New York State Thruway Authority and Tappan Zee Constructors, LLC (TZC) have announced that test boring operations in the Hudson River have been completed. The borings in the river are part of the pre-construction geotechnical work that began in late March. Crews will, however, continue test borings on land in both Rockland and Westchester and continue installing bridge monitoring devices in the Hudson River as part of the pre-construction engineering.

Work continues on the temporary Westchester trestle. The trestle is a work platform that will support a crane for the construction of the new bridge. The 1,000-foot long platform reduces the amount of dredging required and allows crews to work from the water and not from the Westchester shoreline. Work on the Westchester trestle will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to the hours between 7 a.m. and 7 p.m. Monday through Friday.

Environmental monitors continue to be installed in Rockland County as the Thruway Authority and Tappan Zee Constructors, LLC (TZC) finalize specific installation locations. The monitors continually record noise, vibration and air quality for the duration of the project. All readings can be viewed at www.NewNYbridge.com.

Westchester:
Surveying, utility exploration and test boring work continues for the New NY Bridge Project during the week of June 10 in Tarrytown. The work being performed in the shoulder area will require a temporary right lane closure on southbound I-87/I-287 between the existing Tappan Zee Bridge and the Route 9 Bridge on Monday and Tuesday from 10 a.m. to 3 p.m.

Rockland:
Mobilization work continues at Exit 10 where TZC will store materials for construction, trailers for work operations and equipment as well as use the staging area for employee parking. Support for river-based work from the Rockland shoreline will continue the week of June 10.

Surveying, utility exploration and test boring work continues for the New NY Bridge Project during the week of June 10 in South Nyack. The work being performed in the shoulder area will require a temporary right lane closure on southbound I-87/I-287 between Interchange 11 and S. Broadway Bridge on Wednesday and Thursday from 10 a.m. to 3 p.m.

New Tappan Zee work site bustles with activity

LoHud June 5, 2013 Written by Theresa Juva-Brown

From a giant crane hoisting steel beams to workers tightening bolts on an emerging platform in the river, the site of the new Tappan Zee Bridge was bustling with activity on Tuesday.

To promote the $3.9 billion bridge replacement, project officials took about a dozen members of the media on the river to see construction preparations. Leaders from Tappan Zee Constructors — the team designing and building the new bridge — and the Thruway Authority led the tour on a tugboat suitably named Tappan Zee II.

“This project is progressing and you’re going to see it ramp up over the next several months to the next year,” said Brian Conybeare, a special adviser to Gov. Andrew Cuomo. “More and more equipment arrives almost daily for this pre-construction work.”

The twin span is set to be completed by April 2018. Crews have just wrapped up test borings of the river’s soil and plan to start test pile-driving next month. Pile-driving tests are necessary to ensure that when permanent supports are installed, they are strong enough to hold the new span.

By the middle of next year, close to 100 work barges will fill the river, with about 30 of them being used to hold giant cranes, officials said.

There are about a dozen barges in the river now, with each dedicated to specific tasks. For example, one team is currently setting up vibration monitoring equipment on the existing bridge, while another is focused on building a 1,000-foot platform off the Tarrytown shore. When completed, the temporary trestle, which won’t be attached to the shore, will house a crane for construction.

“The new northern span will be right over our heads,” Conybeare shouted as the tugboat chugged parallel to the existing bridge on its way to the trestle location.

At the site, a 300-ton crane on a barge slowly lifted a hydraulic power unit that operates a vibratory hammer.

The hammer vibrates piles into the river bed, a technique that is less noisy than pounding them in, officials said.

In addition to the Westchester trestle, crews plan to build a similar one off the Rockland shore, though that one will stretch about 1,300 feet, Conybeare said.

37861007001_2434745098001_vs-51ae778ee4b0c77bd45a17cf-1464912386001

Click here to watch the progress on The New NY Bridge:

http://www.lohud.com/apps/pbcs.dll/article?AID=2013306040075

 

 