SUPER CRANE SUCCESSFULLY COMPLETES FIRST LIFT ON

update

NEW NY BRIDGE PROJECT
I LIFT NY hoists massive 600-ton foundation element into place today

One of the world’s largest floating cranes this morning successfully completed the first of many enormous lifts for the New NY Bridge project, following months of planning and preparation.

In a carefully coordinated three-and-a-half hour operation on the Hudson River between Westchester and Rockland counties, the I Lift NY super crane hoisted and set one of the project’s largest precast concrete pile caps weighing in at 600 tons.

Video and photos from today’s lift will be posted here.

“We brought in the I Lift NY super crane to reduce construction time and cost, and this first lift is another symbol that the New NY Bridge is officially on the way,” Thruway Acting Executive Director Robert L. Megna. “The crane is a key tool to building the bridge in a safer, more cost-effective, environmentally-friendly way. With savings of more than a billion dollars for tollpayers, this super crane will continue to do great work.”

Owned by Tappan Zee Constructors, LLC, the design-build contractor for the New York State Thruway Authority, the super crane’s extraordinary capabilities save time and money while enhancing quality and safety by allowing large sections of the bridge to be pre-fabricated off-site and shipped by barge to the construction zone.

I Lift NY will continue to lift and place sections of the new twin-span bridge — some weighing from 900 to 1,100 tons — and will assist with the dismantling of the existing 60-year-old Tappan Zee Bridge, reducing costs and shortening the deconstruction process.

The super crane’s boom is 328 feet tall, which is taller than a 30-story building, and can lift up to 1,900 tons, or the equivalent of 12 Statues of Liberty, at once. Despite its enormity, the barge-mounted crane sits high in the water, thereby reducing the need for dredging on the project by 50 percent.

The I Lift NY super crane made a 6,000-mile journey from the San Francisco Bay area in 2014, passing through the Panama Canal.

Since its arrival here in New York, the crane has gone through months of testing, modifications and upgrades including a new high-tech computer operating system and complete replacement of its rigging cables. The most experienced operating engineers in the area also spent months of specialized training to carefully handle this massive machine. Now that the ice has cleared on the Hudson River, the I Lift NY crane is getting to work on the pile caps and later this year will begin placing the even heavier structural steel beams that will carry the road deck across the new spans.

New NY Bridge Progress
Under Governor Cuomo’s leadership and with the support of President Barack Obama and the Federal government, the New NY Bridge project has progressed dramatically since construction began in October 2013 following many years of delay. Since October 2011, steps forward include: enactment of new design-build legislation; review and completion of concurrent environmental review and procurement processes; negotiation of a project labor agreement with construction unions; and recommendation from a panel of local leaders and transportation experts for a comprehensive plan for mass transit options for the region – all with an unprecedented level of transparency and community involvement.

About the New NY Bridge
The New NY Bridge’s eight traffic lanes, four breakdown and emergency lanes, and state-of-the-art traffic monitoring systems will mean less congestion for motorists. Designed and constructed to be mass-transit-ready, the new crossing will be able to accommodate bus rapid transit, as well as light rail or commuter rail. The bridge will also include a bike and pedestrian shared-use path. Extensive measures are in place throughout the duration of the project to protect the environment and to monitor the impact of construction on surrounding communities.

I LIFT NY SUPER CRANE SPECIFICATIONS

Type of vessel: Floating Sheerleg Crane
Propulsion: None
Hull material: Steel
Lifting capacity: 1,929 tons
Length: 384 feet
Breadth: 99.8 feet
Depth: 22 feet
Boom length: 328.08 feet
Boom width: 65.7 feet
Min. boom angle for transport: 4 degrees
Min. boom angle for lifting: 19 degrees
Max. boom angle for lifting: 67 degrees
For more information or for photos and video of the I Lift NY super crane’s first lift, go to www.NewNYBridge.com

NYS Thruway Lane Closures for Jan 28-29,2015

For immediate release: January 23, 2015 

TWO LANES OF SOUTHBOUND NEW YORK STATE THRUWAY (I-87/I-287) CLOSED OVERNIGHT WEDNESDAY JAN. 28 AND THURSDAY JAN. 29

Two lanes of the southbound New York State Thruway (I-87/I-287) will be closed between The Tappan Zee Bridge Toll Plaza in Tarrytown and exit 8A (Elmsford – NY Route 119 – Saw Mill River Parkway North) during the overnights of Tuesday, January 27 and Wednesday, January 28. The two overnight closures will occur between 7 p.m. and 5 a.m. and are necessary to accommodate work on an electronic message sign facility.

Bridge Abutment Work Continues

Tappan Zee Constructors, LLC (TZC) will continue assembling formwork that will shape the bridge’s landing on the Rockland and Westchester shorelines. The abutments, which will be made of steel, concrete and earth, will serve as strong bases for where the new crossing meets the landside roadway.

Pile Driving and Other Construction Activity
Construction will continue in the Hudson River as crews place the foundations of the new bridge. Work will include pile driving from 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.

TZC will continue limited concrete placement for foundations near the South Nyack shoreline. In the absence of the project’s floating batch plants, which were temporarily taken out of service last month after a silo failed, the concrete for this work will be acquired from local concrete suppliers and will be delivered by truck to the Rockland trestle located off of the New York State Thruway (I-87/I-287) southbound access ramp. Trucks will exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.

Westchester landing foundation operations continue as crews work to construct the land based piers and abutment for the new bridge.

  • Additional work includes:
  • Pile cap foundation construction
  • Main span foundation construction
  • River Road utility work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on existing bridge

Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.

New Tappan Zee expected to become top tourism destination

The new bridge’s 3-mile walking and biking path could prove to be a major tourist draw.

Will tourists flock to see the new Tappan Zee Bridge?

The answer is years away but it’s conceivable the world’s widest crossing could one day rank alongside New York’s many treasured landmarks, which include Grand Central Terminal, the Brooklyn Bridge and most recently, the Walkway Over the Hudson.

People walking or biking over the Hudson River between Westchester and Rockland will enjoy six scenic overlooks along the 3-mile path. The northerly view would offer stunning vistas of the water, Hook Mountain and the Sleepy Hollow lighthouse.

“That really is a big draw,” said Larry Oakner, senior partner of strategy and engagement with CoreBrand, a marketing consultant firm in Manhattan.

“It may fall into those hidden gem kind of ideas of what New York state has to offer,” he added.

Although the first of the Tappan Zee’s two spans will open in late 2016, the path won’t be ready until 2018 when it will become part of the northern span that carries traffic into Rockland.

A tourism director’s dream scenario would envision thousands of people arriving on weekends to descend upon the path, while pumping money into shops and restaurants in Tarrytown and the Nyacks. Bicycle clubs from New York City and the region would add it to their routes; out-of-state visitors would opt to stay overnight to take in local attractions, including the first major new bridge to be built in the metropolitan area in half a century.

“Just to simply build the bridge won’t deliver the greatest return for you from a tourism perspective,” said Bill Baker, chief strategist of Total Destination Marketing, an Oregon-based firm that helps communities with branding. “They want reasonable experiences, not to just take a photo of it.”

Baker said the landmark offered a unique opportunity for local businesses.

“The parties need to start talking and planning for it,” he said. “There may be some need to commit some funds and perhaps re-purpose some plans.”

Michael Yanko, whose company is constructing a 132-room hotel in Nyack, is banking on the new bridge and walkway drawing visitors from all over. Located off Exit 11 on the Thruway, Nylo Nyack is expected to open in June 2015, targeting both corporate clients and tourists.

“We will have packages for couples to come from the city and to stay in Nyack for the weekend,” said Yanko, a developer and co-owner of WY Management. “Certainly the bike and pedestrian lane and a beautiful bridge is helping.”

In Tarrytown, plans call for putting up a visitors center with parking for about 100 cars near the bridge on South Broadway. The path will connect to South Nyack but exactly where is far from settled. The village is almost entirely residential, further complicating the parking issue.

Rockland County Legislator Nancy Low-Hogan lives in South Nyack and represents several river villages near the bridge.

“In my mind, the (path) is going to be a tourist attraction. Period. End of story. That means opportunity. It also means challenges and that requires planning,” said Low-Hogan, who has taken up the tourism torch with fellow Legislators Alden Wolfe and Harriet Cornell.

They plan to host a meeting next month with officials from South Nyack, Nyack, Grand View, Piermont and Orangetown to talk about next steps. They later hope to expand the sessions to include other local and regional representatives, business leaders and tourism experts.

“Eventually all of these people have to be in this conversation,” Low-Hogan said.

The state Thruway Authority, which owns the Tappan Zee and its replacement, has not released estimates on how many visitors the path could attract.

Some are looking to learn from the experiences of other elevated pedestrian paths, including the High Line in Manhattan and Walkway Over the Hudson, a mile-long converted railroad bridge connecting Poughkeepsie and Highland that has attracted nearly 3 million visitors since opening in 2009.

David Rocco, a Yorktown Heights resident who served on the Walkway’s board of directors from 2005 to 2010, predicted the Tappan Zee path would become a major tourist destination. He visited San Francisco last summer and took a stroll on the 2-mile walkway on the new San Francisco-Oakland Bay Bridge. He thought of home as he saw people jogging and cycling while taking in spectacular views of San Francisco Bay and Candlestick Point.

“I think it’s going to be magnificent,” Rocco said of the new Tappan Zee. “It’s going to be such a draw for both sides of the river.”

However, he said there was the matter of the traffic noise — “It was loud” — but it didn’t take away from his overall enjoyment.

Tappan Zee officials may want to keep an eye on the Bay Bridge to see if its path ends up giving the Golden Gate Bridge a little friendly competition.

More than 5,500 people showed up to use the Bay Bridge Trail on the first Sunday it opened on Sept. 8, 2013.

John Goodwin, a spokesman for the Bay Area Toll Authority, said while there aren’t updated hard figures, he estimated thousands use the path on a good weather weekend, even though it won’t be completed until June. And driving there requires walking a mile from a parking lot just to reach its entrance.

“We weren’t sure how big of an attraction it would be,” Goodwin said. “It proved to be a major attraction indeed.”

Twitter: @ksaeed1

Ask us about the Tappan Zee

Journal News/lohud transportation reporters Theresa Juva-Brown and Khurram Saeed will answer questions and listen to concerns about the Tappan Zee Bridge project from 11 a.m. to noon on Nov. 1 at Pierson Park in Tarrytown. Join them for the informal one-on-one talk over coffee and snacks.

Tappan Zee fast facts

Bridge type: Cable-stayed

Project cost: $3.9 billion

Construction schedule: 5 years, 2.5 months

Project completed to date: 25 percent

Numbers of spans: 2

Traffic lanes: 4 on each span

Breakdown lanes: 1 on each span

Express bus lane/emergency access lanes: 1 on each span

First span opens: December 2016

Second span opens: November 2017

Project physical completion: April 2018

 

http://www.lohud.com/story/news/local/tappan-zee-bridge/2014/10/17/new-tappan-zee-expected-become-top-tourism-destination/17432371/

Tappan Zee could be pathway to tourism in Rockland

Tourism experts say the new crossing and an enhanced bus system could lure tourists and their money to Rockland but officials need to start planning now.

Khurram Saeed, ksaeed@lohud.com11:25 a.m. EDT July 1, 2014

1402940492000-nnyb-rend-15

Most of the talk about the Tappan Zee Bridge project so far has been about construction, noise and how the state will pay for the crossing.

But on Monday, the conversation took a new direction: the bridge as a money generator.

“You’re in a good place here right now, particularly with some of the development at the Tappan Zee Bridge and what’s going to happen,” Mary Kay Vrba, tourism director for Dutchess County, told 50 people at “Destination Rockland: Blazing New Trails in Tourism” at Nyack College.

A group of marketing experts, business leaders and elected officials saw visions of cash registers being filled up by tourists walking or bicycling over the bridge’s dedicated path into Rockland County. A revitalized bus system slated to be ready when the $3.9 billion span opens in 2018 could bring more.

Rockland Legislative Chair Alden Wolfe organized the three-hour conference, stating that it marked the “launching point” for further discussion.

Vrba drew parallels between the upcoming Tappan Zee path and the Walkway Over the Hudson, a 1.2-mile-long pedestrian walkway connecting Highland and Poughkeepsie that draws 700,000 visitors a year. Rockland has most of the ingredients to became a destination with its access to the Hudson River, a bevy of hiking trails and parks, and quaint river villages filled with stores and restaurants.

Downtown Poughkeepsie, on the other hand, lacks popular tourist draws like art galleries, she said.

“They walk the bridge and they say, ‘What next?’ ” Vrba said. “So you’ve got the what next, I think, with Nyack and Piermont and a lot of the shops and everything. You’ve got a product that you can work with. I think you have some real opportunities.”

Officials have the luxury of time to take a look at their towns and villages, address their needs and invest in a tourism plan, she said.

South Nyack and Tappan Zee project officials are still struggling to figure out where people who want to use the path will park in the village. The project team is expected to hold a meeting soon with several concepts proposed by the community, Mayor Bonnie Christian said.

Asked how they addressed parking for the Walkway Over the Hudson, Vrba said the land on both sides was municipally owned and purchased by the state parks department so they could be converted into paid lots. They also had the benefit in Poughkeepsie of parking garages six blocks away.

Veronica Vanterpool, executive director of Tri-State Transportation Campaign and a member of the task force that recently came up with transit recommendations for the bridge, said it was seeking a “transformation” of the existing Tappan ZEExpress service to entice more riders. There would be modern buses, traveling more frequently, utilizing technology like off-board fare collection, but some have said the plan didn’t work.

The system, known as bus rapid transit, is still in the conceptual stage. There are no cost estimates, and only $20 million in state seed money to date.

Twitter: @ksaeed1

Tappan Zee: Artists prepare for Bridge Art Show

LoHud By Theresa Juva-BrownTjuva@lohud.com11:07 p.m. EDT June 23, 2014

For Kenneth Burns, the Tappan Zee Bridge is a crossing between his bustling city past and his quieter suburban life.

“I love my life up here,” he said. “The bridge gave me that.” After working and living in New York City for decades, the 70-year-old is now retired in New City, where he has spent the past eight years developing himself as a painter. He dabbles in watercolor and acrylics. “I mainly do landscapes, abstract landscapes,” he said. “I’m not ever going to make money out of it — it’s just a joy. It’s fun.”

The 2014 Bridge Art Show

Burns is working on a Tappan Zee painting to submit to the 2014 Bridge Art Show, sponsored by the Tappan Zee project team, along with ArtsWestchester, Rockland Center for the Arts, Rivertown Artists Workshop and Nyack Art Collective.The show, which is accepting entries from the public, has already drawn six submissions since it was announced earlier this month, officials say. “You will recognize the bridge, but it will be kind of a cloudy situation,” Burns said of his piece. “Moody is the the proper word. Not much color involved.” Photographers, painters and sculptors have until July 31 to submit their interpretations of the old and new Tappan Zee.

The project’s visual quality panel will select one winner and two runners-up. All the pieces will be displayed at the project’s community centers in Nyack and Tarrytown. For more show guidelines, see newnybridge.com. Mary Louise Allen, Burns’ wife, said she is excited about the exhibit. “I would love to see what my husband comes up with and see how he stacks up against the other local artists,” she said. “It will help him in his pursuit as an artist. He is always inspired by seeing the work of other artists.”

 

Read Complete article on line here: http://www.lohud.com/story/news/local/tappan-zee-bridge/2014/06/23/tappan-zee-artists-prepare-bridge-art-show/11108353/

 

State to loan $511M for new TZ Bridge

LoHud; Joseph Spector, TJN3:03 p.m. EDT June 16, 2014

1402940492000-nnyb-rend-15

The state’s Environmental Facilities Corp. said today it will loan up to $511 million to the new Tappan Zee Bridge project, a move that will help with the financing of the $3.9 billion project.It’s the latest effort by the state to fund the bridge and limit toll increases when the new 3-mile span across the Hudson River is completed in 2018.“As we continue to see progress on the New NY Bridge, it is essential that actions are taken to protect wildlife and address the project’s environmental impacts – but in a way that doesn’t overburden taxpayers and drivers,” Gov. Andrew Cuomo said in a statement obtained by Gannett.

The loan, which is financed through federal aid, will be used for environmental protection and Hudson River restoration projects related to the bridge’s construction. The projects include protecting water quality and marine life in the Hudson River estuary, including endangered sturgeon, oyster beds and other habitats.The loan comes through the EFC’s Clean Water State Revolving Fund. State officials said it won’t impact other projects.It’s the newest loan for the project. The largest loan, $1.6 billion, was announced last year by the federal Department of Transportation.

With the low-interest loans, state officials said it will help keep tolls down on the new bridge, which is being financed through the state Thruway Authority. The round-trip toll on the current bridge is $5, but there have been concerns that it could go as high as $14 on the new bridge.The Thruway Authority will need to approve the loan and is expected to start using it in August, state officials said.The Environmental Facilities Corp. is the financing arm for the state to provide low-interest loans to local governments and agencies for drinking water, wastewater infrastructure and other clean-water projects.Last year, EFC financed close to $2 billion in clean-water investments statewide, a news release from Cuomo’s office said.

http://www.lohud.com/story/news/politics/politics-on-the-hudson/2014/06/16/state-loan-511m-new-tz-bridge/10627953/

 

TZ Task Force Nears Final Meeting

Top Photo

For the past year, the Tappan Zee Bridge Mass Transit Task Force has been
developing recommendations for services on the new bridge.
Times Herald-Record
Published: 2:00 AM – 02/26/14

TARRYTOWN — The Tappan Zee Bridge Mass Transit Task Force will hold its final meeting Friday and release the short-, mid- and long-term recommendations that its 31 members have developed over the past year.

The recommendations, contained in a 26-page executive summary, offer no surprises and no guarantees that any of them will ever be implemented. The summary will be followed next month with a report that details the actions that Rockland and Westchester counties could take to advance the short-term recommendations for new express bus routes as well as estimates of potential costs.

The task force has never identified a source of funding for transit improvements, and Gov. Andrew Cuomo’s staff has forcefully steered members away from any suggestions with hefty price tags on the grounds that it can’t afford a new bus rapid transit or commuter rail system and a new $3.9 billion bridge.

Recommendations

The Tappan Zee Bridge Mass Transit Task Force will formally present the recommendations that have been developed over the past year Friday. They include:

Short-term (between now and the new bridge’s completion in 2018)

• Modify existing bus service in Rockland and Westchester to create seven express routes between Suffern and Nanuet and Tarrytown, White Plains and Yonkers, and between White Plains and Tarrytown, Port Chester, Valhalla and The Bronx.

• Install technology that manages traffic flow through ramp metering, signal prioritization and queue jumping, as well as a bus-only lane on the new bridge, to improve travel times.

• Use specially designed buses to differentiate the new service from existing services, and adopt a common fare structure.

• Advance studies of a transit hub in White Plains, reconstruction of the Thruway’s Interchange 10 in South Nyack and construction of a new Thruway interchange at Route 59 in Monsey. Mid-term (up to 15 years after the new bridge’s completion)

• Create a White Plains transit hub around the train station.

• Reconstruct Interchange 11.

• Construct a bus station in the Thruway median and a pedestrian bridge from the Palisades Center.

• Make improvements to Rockland train service on the Pascack Valley and Port Jervis lines. Long-term (more than 15 years after the new bridge’s completion)

• Pursue revival of passenger rail service on the now freight-only West Shore line in Rockland.

• Consider development of Rockland-to-Westchester commuter rail or light rail.

“We’re not getting a 21st century bridge if we’re not getting mass transit,” said Nancy Proyect, president of the Orange County Citizens Foundation. “We’re not really doing BRT; we’re doing express buses. It’s not a 21st century solution for a 21st century bridge or a 21st century state.”

Proyect, who has advocated for new transit services in the Tappan Zee corridor over the past decade and attended many of the task force’s meetings, predicted the state and the region will come to regret this failure to fund significant improvements in conjunction with the new bridge’s construction.

Before Gov. Cuomo took office and fast-tracked the TZB’s replacement, the state had been pursuing a true BRT system with dedicated travel lanes and stations across the two counties that buses from Orange County could have used. But Cuomo eliminated transit elements from the project, citing high costs and ample opportunity for adding services in the future to what would be a “transit-ready” bridge.

Rockland and Westchester counties then forced Cuomo to form the task force to keep the prospect of transit improvements alive in exchange for their support of the new bridge.

The meeting will be held at 9:30 a.m. Friday at the Tarrytown Senior Center at 240 W. Main St., on the village’s waterfront.

judyrife@gmail.com

 http://www.recordonline.com/apps/pbcs.dll/article?AID=/20140226/BIZ/402260341/-1/NEWSLETTER100

Tappan Zee Bridge; A Video Introduction

Click here: A Bridge to a New Era Video

 

The Tappan Zee Bridge today can be nearly synonymous with traffic, from spectacular jams on the steel superstructure to residual delays clogging streets in Tarrytown and Nyack. The bridge almost 60 years ago was heralded for linking two villages, two counties and carrying “possibly (the) most modern super highway in the world,” according to the Rockland Journal-News. As the region and its residents ready to watch Tappan Zee 2.0 cross the Hudson River, The Journal News looks at the beginnings of the first bridge and what the second one may bring.

Read more:  http://tappanzeebridge.lohud.com

 

TZ Bridge Pre-Construction Activities Continue

The new NY bridge

For immediate release: October 11, 2013

NEW NY BRIDGE PROJECT
PRE-CONSTRUCTION ACTIVITIES CONTINUE

 

Second shift operations will continue on the river from 3:30 p.m. to 12 midnight on weekdays in preparation for permanent construction activities.

This work is primarily to support activities for the daytime pile driving operations and is limited by the project’s noise level restrictions. Pile driving will be limited to the hours of 7 a.m. to 7 p.m. on weekdays and, occasionally, from 12 noon to 7 p.m. on Saturdays.

Construction of the Rockland County trestle will continue. This work will include daytime pile driving to install the temporary foundation piles needed to support the platform. The trestle is a work platform that will support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required.

From Tuesday, October 15 to Friday, October 18, one southbound right hand lane and shoulder on I-87/I-287 between exit 9 and exit 11 will be closed from 9 a.m. to 3 p.m. for shoulder work.

Additionally, utility work will continue on River Road in South Nyack. This work will be performed from 6:30 a.m. to approximately 6 p.m. for the next three weeks and has been coordinated with and approved by the Village of South Nyack. The work will reduce the roadway to one lane during daytime hours and flaggers will be onsite to safely direct motorists on River Road. During non-work hours, the road will have temporary coverings in place that may create uneven surfaces. Motorists and bicyclists should slow down and use extreme caution in the area.

Mariners should be aware that TZC will be installing piles in the vicinity of the side channels. Both temporary and permanent piles are illuminated at night.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area.

If necessary, the Coast Guard in the future may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website, NewNYBridge.com, under the boating safety icon.

E-ZPass tags are now available for purchase at the New NY Bridge Community Outreach Centers in Tarrytown and Nyack.

The pre-packaged E-ZPass tags can be purchased for $25 and are ready for immediate use. E-ZPass users avoid delays when traveling through toll plazas, receive a discount on every Thruway toll they pay, and enjoy the convenience of using E-ZPass in fifteen states: Delaware, Illinois, Indiana, Maine, Maryland, Massachusetts, New Hampshire, New Jersey, New York, North Carolina, Ohio, Pennsylvania, Rhode Island, Virginia, and West Virginia.

E-ZPass tags have a $25 value and are active upon purchase. The first $15 is immediately available for toll usage, and the remaining $10 becomes available once the tag is registered online or by phone. E-ZPass provides a five percent savings on Thruway tolls and offers toll discounts on many other roadways.

The Community Outreach Centers for the new bridge project were established last year as a gathering place and source of information for the community regarding the New NY Bridge. They are located at:

• 303 South Broadway in Tarrytown, and
• 142 Main Street in Nyack.

The centers are open Monday through Friday, 11 a.m. to 7 p.m.; Saturday and Sunday, 11 a.m. to 4 p.m.

Ongoing operations:

• Dredging operations will continue 24/7

• Test pile program

• Rockland Dock Extension under existing bridge

• Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.

• Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.

• Survey inspections on existing bridge

• Support for river-based work from the Rockland shoreline

Regulators release Hudson River restoration plan

Written by : Associated Press

ALBANY, N.Y. — A draft plan released by state regulators on Tuesday will guide efforts to restore and protect the Hudson River Estuary from the Troy dam to the Tappan Zee Bridge.

The Department of Environmental Conservation is taking public comment on the plan until the end of October and is holding public information sessions Wednesday afternoon at Margaret Norrie State Park in Staatsburg and Sept. 24 at Columbia Greene Community College in Hudson.

The plan identifies four priority habitats for restoration: tidal wetlands, shallows, shorelines and tributaries. It says those habitats are important to the overall health of the ecosystem but have been degraded or destroyed on a large scale by development.

About half the estuary’s shoreline remains in a natural state, but the rest has been engineered with walls and other structures to protect property or support transportation, recreation or industrial activities.

Besides harming wildlife, loss of shoreline wetlands and shallows has made riverside communities more vulnerable to flooding by removing natural barriers that protect against weather extremes and rapid sea level rise, authorities said.

“Restoration of healthy habitats will provide benefits for fish, birds, turtles, crabs, mammals and invertebrate animals and to the residents of the Hudson River Valley and the state of New York,” DEC Commissioner Joe Martens said in a prepared statement.

Habitats in the estuary, which is tidal up to the federal dam at Troy, have been damaged since the early 1800s by navigational dredging, filling of wetlands, construction of the railroad along sensitive shoreline habitats and construction of dams in tributaries.

The habitat restoration plan is intended to be used by community groups, governments, scientists and conservation organizations.

Restoration actions identified in the plan include dam removal and culvert improvement in tributaries to promote fish passage; invasive-species control programs; preservation of existing shore land habitat; and use of environmentally sound methods of shoreline stabilization where necessary to protect property.

ROCKLAND TEMPORARY TRESTLE CONSTRUCTION BEGINS

update

For immediate release: August 23, 2013

Work is scheduled to begin the week of August 26 on the Rockland trestle, which is the second temporary work platform to be constructed as part of the New NY Bridge Project.

The work will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to a maximum of 7 a.m. to 7 p.m. on weekdays and, occasionally, on Saturdays from 12 noon to 7 p.m. The trestle is a work platform that will eventually support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required near the Rockland shoreline

Impact pile driving will continue as part of the ongoing test pile program and will continue through October at various locations for future pile foundations. This work will be performed from 7 a.m. to 7 p.m. on weekdays and, occasionally, on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

Beginning Monday, August 26 through Wednesday, August 28, one northbound right hand lane and shoulder on I-87/I-287 between the existing Tappan Zee Bridge and Interchange 11 in Nyack will be closed from 9 a.m. to 3 p.m. for the installation of concrete traffic barriers to delineate traffic from the construction zone to ensure safety for traveling public and work crews.

Additional geotechnical borings to support design will be conducted on the river at various locations. Operations will run 24 hours a day, Monday through Friday.

Tappan Zee Constructors (TZC) will continue dredging operations in the Hudson River as part of the New NY Bridge Project. Dredging will occur through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.

Dredging crews will work 24/7 starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.

Ongoing operations:
– Test pile program

– Rockland bulkhead construction (including fence & gates) and Dock Extension at Rockland (under existing bridge)

– Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.

– Survey inspections on existing bridge

– Mobilization at the exit 10 staging area

– Support for river-based work from the Rockland shoreline
Rockland:
TZC will be installing temporary noise barriers along the right of way adjacent to I-87/I-287 near Ferris Lane. Fencing and sidewalk work will continue along River Road in South Nyack north of the existing bridge. This work is part of the bulkhead construction area and will be performed on weekdays between 7 a.m. and 3 p.m. At times, River Road will be limited to one lane with flag persons in place to ensure the safe flow of traffic.

ROCKLAND BULKHEAD CONSTRUCTION TO BEGIN–TEST PILE PROGRAM CONTINUES

update

FOR IMMEDIATE RELEASE; JULY 19, 2013

Construction of the Rockland Bulkhead will begin next week as crews enlarge the work platform in the New York State Thruway Authority’s Rockland maintenance area located on River Road in South Nyack.

The bulkhead will be part of the Thruway’s permanent dock and serve as the access point for Tappan Zee Constructors, LLC’s (TZC) Rockland trestle.  The trestle is the support platform that will allow TZC to build the foundations for the new bridge near the Rockland shoreline without dredging in that area.  TZC will utilize the bulkhead for support of construction throughout the entire project.

Orange and Rockland Utilities will install new utility poles near River Road in South Nyack to support utility relocations which are needed for the New NY Bridge project. These operations may require temporary lane closures and will be performed by the utility.

Test pile driving operations will be conducted over the next three months at proposed locations for pile foundations.  The test pile program will verify subsurface conditions in preparation for the construction of the bridge’s permanent foundation.

Multiple crews will conduct night time boring operations along I-87/I-287 in both directions in Westchester and Rockland Counties.  The night time operations are necessary due to lane closure restrictions during day time hours that are in place to keep traffic flowing over the current bridge. Boring operations began at exit 10 in Rockland County and continue to move west into Westchester County and then back to Rockland for one final boring location.

Ongoing operations:
– Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
– Survey inspections on existing bridge
– Rockland environmental monitor installations continue
– Geotechnical land borings
– Mobilization at the exit 10 staging area
– Support for river-based work from the Rockland shoreline
– Extension of Thruway’s Rockland maintenance dock

Westchester:
Night time boring operations to investigate subsurface soil conditions will be conducted in the southbound shoulder of I-87/I-287and will require a temporary right lane closure between the existing bridge and exit 9 on Tuesday, July 23, from 9 p.m. to 6 a.m.  Northbound lane closures will be required from exit 9 to the existing bridge on Wednesday, July 24, and from exit 9 to exit 11 in Rockland County on Thursday, July 25, and Friday, July 26. from 9 p.m. to 6 a.m.

Rockland:
Night time boring operations to investigate subsurface soil conditions will be conducted in the southbound shoulder of I-87/I-287 and will require a temporary right lane closure between exit 10 and the existing bridge on Monday, July 22, from 9 p.m. to 6 a.m.

VOTING SHOWS MAJORITY FAVOR NOISE BARRIERS FOR THE NEW NY BRIDGE

update

Project Update

For immediate release: July 19, 2013

Last month, the New York State Thruway Authority, the New York State Department of Transportation (NYSDOT), and the Federal Highway Administration (FHWA) invited local residents tovote on the placement of proposed noise barriers for the New NY Bridge Project.

“The public has spoken and they overwhelmingly support the construction of sound reducing traffic noise barriers as part of the New NY Bridge Project,” said Brian Conybeare, Governor Cuomo’s Special Adviser for the New NY Bridge Project. “This is another way we trying to make this the most inclusive and transparent infrastructure project in the history of the state. We will continue to include input from local residents and other stakeholders as the project moves forward.”

Noise barriers are recommended as a form of traffic noise abatement only if they are determined to be both feasible and reasonable. According to Thruway and NYSDOT noise policies, as well as FHWA noise regulations, once a noise barrier is deemed both feasible and reasonable, ‘benefited receptors’, defined as property owners and/or residents of properties that would receive at least a five decibel reduction in noise level as a result of the proposed noise barriers, have an opportunity to cast a vote either for or against its construction.

Public meetings were held in both Westchester and Rockland counties during the week of June 23. At the meetings, Tappan Zee Constructors, LLC explained the locations and heights of the proposed walls for the areas that met the noise mitigation requirements, along with any possible aesthetic preferences.

The voting results show the benefitted receptors overwhelmingly favor having noise barriers constructed as part of the New NY Bridge project. Overall, 306 ballots were sent to benefited receptors. The tabulated results from the vote appear below:

Barrier

Votes For

Votes Against

Results

Westchester East Sound Barrier

87

1

98% FOR BARRIER

Westchester West Sound Barrier

2

0

100% FOR BARRIER

Rockland North Sound Barrier

96

5

95% FOR BARRIER

Rockland South Sound Barrier

31

2

94% FOR BARRIER

Tappan Zee Bridge Update: Two more monitors planned in Rockland

LoHud Jun 8, 2013 Written By Khurram Saeed

http://www.lohud.com/article/20130607/NEWS03/306070051/Tappan-Zee-Bridge–2-more-monitors-planned-in-Rockland?source=nletter-news

The New Tappan Zee Bridge

A South Nyack apartment complex and a residential street in Grand View may soon be home to devices to monitor noise, dust and vibrations during construction of the new Tappan Zee Bridge.

Tappan Zee Constructors is working on finalizing details to install environmental monitors at Bradford Mews Apartments on Piermont Avenue and Ferris Lane, a project official told The Journal News on Friday afternoon.

South Nyack Mayor Bonnie Christian on said Friday morning that the monitors would be installed this weekend, but that’s not the case, the official said.

However, a monitor was recently installed at Interchange 10 of the Thruway in South Nyack, and another is set to go up next week on River Road, just south of Grand View Village Hall near Orangetown’s sewage pumping station.

That would bring to four the total number of monitors in Rockland, with two more on the horizon.

Devices were installed a few weeks ago at South Nyack’s Salisbury Point Cooperative, across from Bradford Mews, and near the Thruway’s Interchange 12 in West Nyack.

South Nyack has been working with the bridge’s design-builder to find suitable locations since TZC proposed putting up the shoebox-sized devices in front of Village Hall and Elizabeth Place Park, both in the village.

“We had them go around again and give a look,” Christian said. “They came up with these two alternatives (Bradford Mews and Ferris Lane). There may be other sites to come.”

Christian said discussions will continue with TZC about other appropriate locations so residents can keep an eye on potential quality of life disturbances during the five-year construction of the twin-span crossing.

Four environmental monitors in Tarrytown are already in place.

Data from all of the devices can be viewed at http://newnybridgegall- ery.com/noise/.

A New Week of Tappan Zee Bridge Repair Work Coming

Nyack-Piermont Patch  Posted by William Demarest (Editor), 

http://nyack.patch.com/groups/politics-and-elections/p/a-new-week-of-tappan-zee-bridge-repair-work-coming?ncid=newsltuspatc00000001&evar4=picks-2-post

Contruction delays on Tappan Zee Bridge

Work on the Tappan Zee Bridge will continue May 20 through May 24, according to the New York State Thruway Authority.

In case of inclement weather, the work may be postponed.

Monday, May 20 through Friday, May 24

During the daytime hours, the contractor will be working within designated maintenance lane closures and/or underneath the bridge.

Nighttime lane closures scheduled for Monday, May 20 through Friday, May 24

Monday, May 20 and Tuesday, May 21

Work will begin at 8 p.m. resulting in the closure of one left southbound lane and an additional left southbound lane at 10:30 p.m. until 6 a.m. on the Tappan ZeeBridge. In addition, this will result in the closure of two left northbound lanes at 9 p.m. and an additional left northbound lane at 10:30 p.m. until 6 a.m., also on theTappan Zee Bridge.  At least one lane southbound and one lane northbound will be opened to traffic from 8 p.m. to 6 a.m.

During Monday and Tuesday night operations, due to the southbound lane closures, the southbound entrance to the Thruway at Exit 10 (South Nyack) will be closed from 8 p.m. to 6 a.m. and southbound detour signs will be posted through Nyack for the entrance at Route 59 near Exit 11 (Nyack).

During Monday and Tuesday night operations, due to the northbound lane closures, the entrance ramp to the Thruway from Broadway in Tarrytown will also be closed from 9 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Wednesday, May 22

Work will begin at 8 p.m. resulting in the closure of two left southbound lanes and an additional left southbound lane at 10:30 p.m. until 6 a.m. on the Tappan ZeeBridge. In addition, this will result in the closure of one left northbound lane at 9 p.m. and an additional left northbound lane at 11 p.m. until 6 a.m., also on theTappan Zee Bridge.  At least one lane southbound and one lane northbound will be opened to traffic from 8 p.m. to 6 a.m.

During Wednesday night operations, due to the southbound lane closures, the southbound entrance to the Thruway at Exit 10 (South Nyack) will be closed from 8 p.m. to 6 a.m. and southbound detour signs will be posted through Nyack for the entrance at Route 59 near Exit 11 (Nyack).

During Wednesday night operations, due to the northbound lane closures, the entrance ramp to the Thruway from Broadway in Tarrytown will also be closed from 9 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Thursday, May 23

Work will begin at 9 p.m. resulting in the closure of two left southbound lanes and an additional left southbound lane at 11 p.m. until 6 a.m. on the Tappan ZeeBridge. In addition, this will result in the closure of one left northbound lane at 10 p.m. and an additional left northbound lane at 11:30 p.m. until 6 a.m., also on theTappan Zee Bridge.  At least one lane southbound and one lane northbound will be opened to traffic from 8 p.m. to 6 a.m.

During Thursday night operations, due to the southbound lane closures, the southbound entrance to the Thruway at Exit 10 (South Nyack) will be closed from 9 p.m. to 6 a.m. and southbound detour signs will be posted through Nyack for the entrance at Route 59 near Exit 11 (Nyack).

During Thursday night operations, due to the northbound lane closures, the entrance ramp to the Thruway from Broadway in Tarrytown will also be closed from 10 p.m. until 6 a.m. All traffic will be detoured to the entrance ramp from Route 119.

Friday, May 24

No nighttime work scheduled.

Saturday, May 25 and Sunday, May 26

No work scheduled.

The nighttime lane closures on Monday through Friday are required in order for the contractor to continue with miscellaneous work on the Tappan Zee Bridge.

For the safety of the public and construction workers, motorists are urged to proceed with caution and obey posted work-zone speed limits.

Traffic updates will be broadcast to motorists via Variable Message Signs along the highway and by Highway Advisory Radio 530 AM in the Tappan Zee Bridgecorridor, as well as 1610 AM in the Newburgh area. To see real-time webcam views of the bridge and approaches, go to http://www.thruway.ny.gov/travelers/map/index.html?layer=cameras.

ROCKLAND ENVIRONMENTAL MONITORS TO BE INSTALLED

update

For immediate release: May 17, 2013 


Installation of the Rockland environmental monitors is scheduled to begin the week of May 20. These construction monitoring devices, which monitor vibration, noise, and air quality, will be in place for the duration of the New NY Bridge project.

Work on the Westchester trestle continues this week and will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to the hours between 7 am and 7 pm Monday through Friday. The trestle is a work platform that will support a crane for the construction of the easternmost 1,000 feet of the new bridge. The 1,000-foot long platform helps reduce the amount of dredging required and allows the crews to work from the water and not from the Westchester shoreline. Environmental monitoring is in place and can be viewed at www.newnybridge.com.

Surveying work and soil sampling for the New NY Bridge Project will continue during the week of May 20 as engineering crews conduct more design surveys at various locations in Rockland and Westchester in the vicinity of the project, including the Westchester access road location on New York State Thruway property in Tarrytown.

Preconstruction geotechnical investigations will continue as small barge-based drilling equipment will work at various locations throughout the project footprint in the Hudson River. The crews are conducting preconstruction geotechnical surveys to determine soil conditions where future piles will be installed for the new span. Noise levels from the equipment will be at a minimum. The river-based operations will run continuously 24 hours a day Monday through Friday and possibly Saturday.

Westchester:
Surveying work and soil sampling for the New NY Bridge Project will continue during the week of May 20.

Rockland:
Limited test-boring operations will continue on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on New York State Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 am and 5 pm Monday through Friday.

Soil sampling will be conducted in the area of New York State Thruway during daytime hours; this operation will not cause lane closures and should not affect traffic.

Tappan Zee Constructors, LLC. has no lane closures scheduled on River Road in South Nyack.

STATE-OF-THE-ART ENVIRONMENTAL MONITORING SYSTEM ONLINE FOR TZ BRIDGE

For immediate release: May 10, 2013
Contact: Dan Weiller (518) 471-5300

Residents kept informed by noise, vibration and air quality monitors
as first pile driving begins on a temporary work platform

As work begins on a temporary Westchester work platform for the New NY Bridge, residents will be kept informed by a first-of-its kind environmental monitoring system with results publicly posted on the internet.

“We are empowering people with information and keeping them up to date on what’s happening with this vital project,” said Thruway Authority Executive Director Thomas Madison. “We are taking unprecedented measures to mitigate noise, vibration and air quality issues and the monitoring system that is now on our website is a major part of that effort.”

As soon as Friday, May 10, Tappan Zee Constructors, LLC (TZC) will begin daytime pile driving work to install the temporary foundation needed to support a trestle in the Hudson River on Thruway Authority property just north of the current bridge in Tarrytown.   The trestle is a work platform that will support a crane for the construction of the easternmost 1000 feet of the new bridge.  The 1000-foot long platform, which will be dismantled when the bridge is complete, helps reduce the amount of dredging required in the Hudson and allows the crews to work from the water and not from the Westchester shoreline.

TZC has installed highly sophisticated monitoring devices at locations near the project site in Westchester. These devices will record the level of sound, vibration and air quality and the data will be available to the public online at www.newnybridge.com as part of the New York State Thruway Authority’s commitment to openness and transparency.

Environmental requirements limit pile driving and other loud construction activities to a maximum of 7 a.m. to 7 p.m. Monday through Friday. There will be no pile driving done on the weekends.

Because the soil under the river is so soft, the pilings will be installed using the vibration technique for the most part.  Vibratory pile driving is much quieter than impact pile driving and will be less intrusive for nearby residents.  Short duration impact pile driving will be used to set the piles into bedrock.  TZC will also use sound mitigating shrouds and other techniques to reduce the noise levels involved.

The EPCs are intended to monitor, minimize and mitigate potential adverse effects related to construction noise, vibration and air quality associated with the project.  In addition to the monitoring systems and specialized pile driving techniques, the Thruway Authority is requiring many other mitigation measures including state-of-the-art controls to limit dust and emissions and receiving deliveries of equipment and supplies mostly by barge, rather than truck.

Construction of the temporary Westchester trestle is expected to last several months.  Construction of a similar work platform on Thruway property near the Rockland County shoreline is expected to begin in July.

For a direct link to the data from the monitors go to: http://newnybridgegallery.com/noise/

###

Excitement grows among Tappan Zee Bridge workers

Lohud.com  May 5, 2013

Written by Theresa Juva-Brown and Khurram Saeed
http://www.lohud.com/article/20130505/NEWS/305050051/Excitement-grows-among-Tappan-Zee-Bridge-workers?source=nletter-news&nclick_check=1

Bobby Stackhouse feels the growing excitement for the new Tappan Zee Bridge as he fuels the boats of the first work crews on the river.

It’s just Stackhouse and about two dozen other union workers currently on site, but they will gradually get more company as thousands of laborers join the monumental effort to build the Tappan Zee replacement in the next five years.

“This is just the beginning,” said Stackhouse, who grew up in North Tarrytown and is lead steward on the project for Teamsters and Chauffeurs Local 456. “All the trades have been starving for the last five or six years — it’s been so bad. This job is like adrenaline being tapped into you. Once it gets going, it’s going to put many people back to work.”

The $3.9 billion project to replace the Tappan Zee is expected to employ roughly 2,600 full-time construction workers each year for the next five years, according to state economic models based on the cost of the project. Some of those union members may work during certain portions of the project, while others may be employed for the duration of the project.

So far, the small team that includes Stackhouse is making early preparations such as setting up staging areas on piers and testing the river soil. As the work intensifies in the coming months, Stackhouse, 59, will manage groups of truck drivers, transport equipment for repairs and keep track of supplies.

“People who are coming to this job know it’s steady work for a while, and they’ll be OK with their bills,” he said. “Everyone is very happy out here.”

From carpenters to crane operators, workers from dozens of construction specialties will all work under the same labor agreement to complete the 3-mile, twin spans by April 2018.

The deal encompasses some 50 locals and was negotiated last year between local and state union leaders and the New York State Thruway Authority. The several-hundred-page document establishes consistent policies regarding work hours, overtime rates and holidays. The common rules will save the state some $450 million, while also providing highly skilled workers for the complex job, officials say.

Longer work weeks

Many of the unions typically work 35 hours a week, with any work beyond that paid as overtime. But under the bridge’s labor agreement, the standard work week on the project will be 40 hours, either in four 10-hour days or five eight-hour days.

The wages, compensation packages and annual raises union workers receive will vary based on trade and experience. They are standard rates for their work that were negotiated between the unions and their trade councils, and are not specific to the bridge project. Workers will also receive annual raises based on trade and experience.

For example, a fully-trained ironworker specializing in the bridge’s steel structure will receive $110 an hour in total compensation. That includes $46 in wages and $64 for health and other benefits.

Workers will receive an extra $25 every day they show up an hour before the start of their shift, to give them more than enough time to catch a bus or boat to their job site. The bonus is designed to save TZC both time and money by making sure shifts start on time, officials said.

A cap on the overtime rate is another way the state expects to save money. While some unions are paid a double-time rate for overtime, all union workers on this job will be paid at time-and-a-half.

The agreement also standardizes paid holidays for workers. Some unions receive a dozen holidays on other jobs, but will get eight on this one. The deal details how to settle disputes and handle injuries and guarantees that there will be no strikes, slowdowns or picketing by labor or lockouts by management.

Even with the compromises, the deal was worth it because it will give a pool of some 40,000 union members a chance for steady work, union leaders said. That’s important for some trades that have suffered with unemployment rates as high as 40 percent in recent years.

“What’s guaranteed is that the men on the job are from (local) building trades,” said Pete Creegan, business agent for Iron Workers Ornamental Local 580, which has about 1,000 members in Westchester and Putnam counties. “It keeps the people living in the area paying their school taxes, putting their kids through school, and keeping those communities alive. Everyone benefits.”

Safety and security

While standardized rules in project labor agreements are typical, the one for the Tappan Zee project includes stiff, and in some cases unprecedented, requirements to minimize the risk of accidents, ensure top performance and keep the site secure.

“This job … requires every worker on the job, including management, including people designing the bridge in an office miles way, to be substance tested” for drug and alcohol use, Ross Pepe, president of the Construction Industry Council of Westchester and Hudson Valley, said.

“It’s the only public works project in the state, that I know of, that has a requirement for substance testing,” Pepe said.

The drug and alcohol tests will be administered before employment, on a random basis, following accidents and for reasonable suspicion. Tarrytown-based Clarity Testing will carry out the program and perform daily urine tests on site.

Because project workers will know details about the bridge’s design and structure, workers have to undergo background checks to see whether they have criminal histories, immigration issues or financial problems that could make them vulnerable to bribes, officials said.

Those entering the work zone, whether they are top managers, daily workers or visitors, will have to go through homeland security clearance ahead of time.

These safety and security measures also lower costs for liability insurance and worker’s compensation and reduce the project’s overall price tag, they said.

A diverse workforce

Women and minority workers will get special consideration as part of the labor agreement. It requires that nearly 30 percent of the total construction hours — 22.6 percent for minorities and 6.9 percent for women — go to those groups.

Though there aren’t specific requirements for this project, union leaders said they are currently working with Helmets to Hard Hats to get military veterans on the job.

Union workers will carry out the majority of the actual construction, but the labor agreement allows up to 12 percent of the workforce to include nonunion workers.

Because public money is involved, even non-union construction workers have to be paid the prevailing wage, which is set by state law.

Most of the nonunion work on the project will be related to activities outside of construction, such as public relations and information technology.

Creegan, the ironworker union leader, said the Tappan Zee project is a special opportunity for workers to accomplish a great feat.

“They accept that challenge,” he said. “What’s a better feeling than making it happen at the end of the day?”

 

 

www.NewNYBridge.com

For immediate release: May 3, 2013

The new NY bridge

WESTCHESTER TEMPORARY TRESTLE CONSTRUCTION SCHEDULED TO BEGIN

Work is expected to begin during the week of May 6 on the Westchester trestle, which is the first of the temporary work trestles to be constructed as part of the New NY Bridge project.

The work will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to a maximum of 7:00am to 7:00pm Monday through Friday and is expected begin on Friday May 10. The trestle is a work platform that will support a crane for the construction of the easternmost 1000 feet of the new bridge. The 1000-foot long platform helps reduce the amount of dredging required and allows the crews to work from the water and not from the Westchester shoreline.

In addition, two mooring buoys will be installed in the Hudson River on the Rockland side of the channel. These will be utilized to secure work barges and will be on site for the duration of the project.

Surveying work and soil sampling for the New NY Bridge Project will continue during the week of May 6 as engineering crews conduct more design surveys at various locations in Rockland and Westchester in the vicinity of the project, including the Westchester haul road location on New York State Thruway property in Tarrytown.

Preconstruction geotechnical investigations will continue as small barge-based drilling equipment will work at various locations throughout the project footprint in the Hudson River. The crews are conducting preconstruction geotechnical surveys to determine soil conditions where future piles will be installed for the new span. Noise levels from the equipment will be at a minimum. The river-based operations will run continuously 24 hours a day Monday through Friday and possibly Saturday.

Westchester:
Limited test-boring operations will continue on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 am and 5 pm Monday through Friday.

Rockland:
At times traffic on River Road near the South Nyack-Grand View border will be restricted to one lane during weekday daytime hours for utility investigations. Signs and flag persons will be in place to help keep traffic flowing safely.

Limited test-boring operations may start on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 am and 5 pm Monday through Friday.

 

 

https://tappanzeebridge.randcommercial.com/922/

Some property information provided by CoStar, Loopnet, HGAR, Yelp, Rand Commercial Services and other public sources.