For immediate release: August 4, 2016 STAY CABLE INSTALLATION CONTINUES Tappan Zee Constructors, LLC (TZC) continues to install the new northbound bridges stay cable system. The stay cables are comprised of numerous metal strands, tightly packed in a protective sheath. After the initial installation process, TZC will install additional strands inside the sheath to provide further strength. TZC will install new structural steel sections and stay cables on alternating sides of the towers as work continues. Precast concrete deck panels will also be placed in the erected steel sections to provide a base driving surface. Maintenance Dock Construction Noise Barrier Construction TZC also will continue constructing foundation walls for the future highway and shared-use path along the northbound Thruway in South Nyack. The operation is scheduled to continue in the coming months. Additional work includes:
Boater Safety The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. The U.S. Coast Guard also has established a safety zone encompassing all navigable waters within a 200-yard radius of the largest machine on the project, the I Lift NY super crane, legally registered with the U.S. Coast Guard as the Left Coast Lifter. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. The Eastern RNA will be extremely active and vessels transitioning to and from the eastern shoreline at Tarrytown should approach and depart to the north. The Western RNA will be impassable at times and mariners should stay clear of the area. Boaters are strongly urged to use the center 600 feet of the main channel (when available) to navigate in a north-south direction with no wake at a maximum speed of five knots. Boaters should expect periodic partial closures of the main channel due to construction activities. Tune to Marine Radio Channel 22A for the latest U.S. Coast Guard advisories. Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Mariners are advised to stay clear of all overhead work and maintain a safe distance of 1,000 feet from all construction equipment and support vessels. In addition, all bridge piers and abutments are protected by a 25-yard security zone. Additional temporary navigational lights have been installed on the existing bridge to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard permit requirements, as are all moorings, barges and other equipment. All mariners should consult the latest USCG Local Notice to Mariners before transiting this area. More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site map can be found at NewNYBridge.com/Boater. The page includes an interactive GPS map showing vessel locations on the Hudson River, detailing which vessels are stopped and which are in motion to a new location, for recreational and commercial boaters to get current information on the very active construction zone. The vessel tracking map is for informational purposes and not intended for navigation. All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions. ###
|
Project Update: STAY CABLE INSTALLATION CONTINUES
PROJECT UPDATE – WESTCHESTER GIRDER INSTALLATION
For immediate release: Nov. 19, 2015
WESTCHESTER GIRDER INSTALLATION OVER METRO-NORTH RAILROAD TRACKS CONTINUES THIS FRIDAY EVENING
Overnight Closures of the I-87/I-287 Exit 10 On-Ramp Scheduled for Nov. 19 and Nov. 20
Next week, Tappan Zee Constructors, LLC (TZC) will continue installing structural steel girder assemblies from the new bridges Westchester landing in Tarrytown. The assemblies will connect the future westbound spans on-land abutment to the first offshore support pier in the Hudson River. TZC is installing the girders by literally pushing them west over the Metro-North Railroad Hudson Lines tracks toward the first pier in the river, as seen in this animation. As the operation progresses, additional girders are being connected to the assembly and pushed farther westward. TZC is closely coordinating the effort with Metro-North Railroad, ensuring that the operation maximizes safety for both workers and the public and minimizes impacts to rail service.
With the entire operation anticipated to conclude by the end of the year, the remaining work over the Metro-North tracks will occur during two Friday overnights, with the next scheduled for this Friday evening, Nov. 20. Metro-North has adjusted its schedule slightly to allow the work to be completed. TZC will suspend construction activities when commuter trains pass through the area, resuming when given the all clear instruction by Metro-North.
Across the river, TZC has completed steel girder installation near the Rockland shoreline, connecting the new bridges abutment to already-installed support structures in the Hudson River.
The I Lift NY super crane will continue placing larger girders across the river, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.
All-Electronic Toll Collection Gantry Work
Construction of the projects temporary all-electronic toll collection (AETC) system in Rockland will continue near the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to southbound New York State Thruway (I-87/I-287). The work will necessitate closing the on-ramp during the overnights of Thursday, Nov. 19 and Friday, Nov. 20. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the graphic below. No lane closures are planned for this work next week.
Ramp Closures Near the Tappan Zee Bridge
Tower Construction Deck Panel Installation Installation of Noise Barriers in South Nyack Additional work includes:
Boater Safety The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times. More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation. Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment. All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions. ### |
Project Update: Electronic Tolling System Requires Overnight Closures
For immediate release: Nov. 12, 2015
THRUWAY UNVEILS UPDATED PROJECT WEBSITE
All-Electronic Tolling System Work Requires Overnight Closure of Exit 10 On-Ramp on Friday, Nov. 20
The New York State Thruway Authority launched an updated NewNYBridge.com this week, featuring an easier-to-navigate interface, a comprehensive archive of project photos, videos and renderings, and a wealth of background information covering how the new crossing was studied and designed and is being built. Visit the new site and check back frequently for the latest updates on the fast-moving construction progress.
Steel Girder Installation
Tappan Zee Constructors, LLC (TZC) will continue installing steel girders near the Rockland shoreline, connecting the new bridges abutment to already-installed support structures in the Hudson River. Safely accomplishing the work will require reducing River Road/Piermont Avenue to one lane during weekdays between 6 a.m. to 5 p.m. Flag persons will keep traffic moving by alternating the directional flow between north and south. TZC also will hold traffic on River Road once daily between 9 a.m. and 3 p.m. for up to 20 minutes through Wednesday, Nov. 18 to enable the safe movement of girders and other materials.
Across the river, TZC will continue installing structural steel girder assemblies from the new bridges Westchester landing in Tarrytown. The assemblies will connect the future westbound spans on-land abutment to the first offshore support pier in the Hudson River. TZC is installing the girders by literally pushing them west over the Metro-North Railroad Hudson Lines tracks toward the first pier in the river, as seen in this animation. As the operation progresses, additional girders are being connected to the assembly and pushed farther westward. TZC is closely coordinating the effort with Metro-North, ensuring that the operation maximizes safety for both workers and the public and minimizes impacts to rail service.
With the entire operation anticipated to conclude by the end of the year, the remaining work over the Metro-North tracks will occur during two Friday overnights, one in November and one in December. The work will be announced in advance to enable Metro-North riders to plan ahead. Metro-North has adjusted its schedule slightly to allow the work to be completed. TZC will suspend construction activities when trains pass through the area, resuming when given the all clear instruction by Metro-North.
Additionally, the I Lift NY super crane will continue placing larger girders across the Hudson River, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge.
All-Electronic Toll Collection Gantry Work
Construction of the projects temporary all-electronic toll collection (AETC) system in Rockland will continue near the exit 10 (Nyack – South Nyack – US Route 9W) on-ramp to southbound New York State Thruway (I-87/I-287). The work will necessitate closing the on-ramp during the overnight of Friday, Nov. 20. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the graphic below. The work also requires double-lane closures during weekday overnights from Monday, Nov. 16 through Thursday, Nov. 19. This and other work require the specific lane and ramp closures detailed in the chart below.
Lane and Ramp Closures Near the Tappan Zee Bridge
Tower Construction Deck Panel Installation Installation of Noise Barriers in South Nyack Additional work includes:
Boater Safety The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times. More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation. Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment. All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions. ### |
Project Update: ICONIC BRIDGE TOWERS CONTINUE RISING
For immediate release: Sept. 10, 2015
ICONIC BRIDGE TOWERS CONTINUE RISING Next week, the new bridge’s towers will continue rising toward their ultimate height of 419 feet, thanks to self-climbing jump forms. The state-of-the-art forms enable Tappan Zee Constructors, LLC (TZC) workers to build the towers in segments that progressively jump up from the foundations to their full height. Within the jump forms, workers assemble steel reinforcement cages that are then encased in concrete, one segment atop the previous one and so on. Eight towers will be constructed on the project’s football-field-long main span pile caps over the coming year, as seen in this animation. Structural Steel Installation The installation of girders over the river will continue next week and beyond. Smaller girder sections will be lifted into place by cranes from the Rockland trestle near the South Nyack shoreline. Ironworkers then bolt together the steel-blue girders and cross beams that support the new bridges concrete road deck. The I Lift NY super crane will continue placing larger girders, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge. All-Electronic Toll Collection Gantry Work Specific lane and ramp closure times are listed in the chart below.
|
Steel Girder Installation Continues
For immediate release: August 20, 2015
STEEL GIRDER INSTALLATION CONTINUES NEAR THE ROCKLAND LANDING Tappan Zee Constructors, LLC (TZC) will continue installing structural steel girders for the New NY Bridge project next week. Smaller girder sections will be lifted into place by cranes from the Rockland trestle near the South Nyack shoreline. Local ironworkers will then bolt together the steel blue girders and cross beams that will support the new bridges concrete road deck. In addition, the I Lift NY super crane will continue placing larger girder assemblies next week and beyond, averaging two placements a week. A total of 31 miles of steel girders cumulatively weighing more than 100,000 tons will be installed for the new twin-span bridge. Two northbound lanes of the New York State Thruway (I-87/I-287) will be closed during the overnights of Monday, August 24 and Tuesday, August 25 across the existing Tappan Zee Bridge to facilitate surveying efforts.
|
Holiday Traffic Update
For immediate release: July 1, 2015
NO LANE CLOSURES SCHEDULED ON NEW NY BRIDGE PROJECT OVER INDEPENDENCE DAY WEEKEND
Multiple Lane Closures During the Overnights of the Week of July 6
In observance of the Independence Day holiday, Tappan Zee Constructors, LLC (TZC) will suspend most construction activities over the Fourth of July weekend. Security and limited maintenance operations will continue throughout the project site. In accordance with New York States Drivers First initiative, no construction related lane closures are scheduled on or near the New NY Bridge project site from Thursday morning, July 2 to Monday night, July 6. Drivers First, launched in 2012, prioritizes the convenience of motorists to ensure that traffic disruptions are as minimal as possible for drivers at highway and bridge construction projects across the state.
Boater Safety With the 2015 boating season in full swing, the New NY Bridge project team urges all boaters to use caution on the Hudson River near the construction zone and to take advantage of the extensive safety-related information available on the project website including the 2015 New NY Bridge Boater Safety Guide.
Enhanced marine law enforcement patrols are in effect for the Independence Day holiday weekend. The U.S. Coast Guard, Westchester and Rockland County marine units will be patrolling the area urging all boaters to use caution and follow all safety regulations.
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.
More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.
Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.
Following the Holiday, Multiple-Lane Closures and Periodic Traffic Stops During the Overnights of Monday, July 6 through Friday, July 10 During the overnight of Monday, July 6, lane restriping operations will require triple-lane closures of the northbound New York State Thruway (I-87/I-287) from exit 9 (Tarrytown – Sleepy Hollow – US Route 9) to exit 11 (Nyack – South Nyack – US Route 9W). Specific lane closure times are listed in the chart below.
At least one lane will remain open at all times, except during periodic traffic stops lasting up to 10 minutes of all four lanes of the northbound Thruway near exit 11 (Nyack South Nyack US Route 9W). To ensure the publics safety, the New York State Police will stop and hold all traffic approaching the area immediately before the traffic stops go into effect. Motorists will be permitted to enter the Thruway from all ramps during the traffic stops.
Additionally the exit 10 (Nyack South Nyack US Route 9W) off-ramp from the northbound Thruway will also be closed during the overnight of Monday, July 6. Drivers will be directed to use exit 11 (Nyack South Nyack US Route 9W) as shown below:
During the overnight of Tuesday, July 7, construction operations will require overnight double-lane closures of the northbound Thruway from exit 9 (Tarrytown – Sleepy Hollow – US Route 9) to exit 11 (Nyack – South Nyack – US Route 9W). Specific lane closure times are listed in the chart below.
At least one lane will remain open at all times, except during periodic traffic stops lasting up to 10 minutes of all four lanes of the northbound Thruway near exit 11 (Nyack South Nyack US Route 9W.
During the overnights of Wednesday, July 8 through Friday, July 10, construction operations will require triple-lane closures of the southbound Thruway in the area of exit 10 (Nyack South Nyack US Route 9W). Specific lane closure times are listed in the chart below.
Additionally the exit 10 (Nyack South Nyack US Route 9W) on-ramp to the southbound Thruway will be closed from 8 p.m. to 5 a.m. during the overnights of Tuesday, July 7 and Wednesday, July 8. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the following graphic.
Lane closures throughout the coming week are scheduled as follows:
I-287/I-87 Lane and Ramp Closures near the Tappan Zee Bridge | |||
Date: | Closures Begin: | Closures End: | Location: |
Mon, 7/6 | 8 p.m. One left lane
9 p.m. Two left lanes 11 p.m. Three left lanes |
4:30 a.m., Tue, 7/7 | Northbound, from exit 9 to exit 11 |
Mon, 7/6 | 8 p.m. Ramp closure | 4:30 a.m., Tue, 7/7 | Northbound, exit 10 off-ramp |
Tues, 7/7 | 8 p.m. One left lane
9 p.m. Two left lanes |
4:30 a.m., Wed, 7/8 | Northbound, from exit 9 to exit 11 |
Tue, 7/7 | 8 p.m. Ramp closure | 4:30 a.m., Wed, 7/8 | Southbound,
exit 10 on-ramp |
Wed, 7/8 | 8 p.m. One left lane
9 p.m. Two left lanes 11 p.m. Three left lanes |
5 a.m., Thu, 7/9 | Southbound, from exit 10 to exit 11 |
Wed, 7/8 | 8 p.m. Ramp Closure | 4:30 a.m., Wed, 7/8 | Southbound,
exit 10 on-ramp |
Thu, 7/9 | 8 p.m. One left lane
9 p.m. Two left lanes 11 p.m. Three left lanes |
5 a.m., Fri 7/10 | Southbound, from exit 10 to exit 11 |
Fri, 7/10 | 9 p.m. One left lane
10 p.m. Two left lanes 11 p.m. Three left lanes |
6 a.m., Sat 7/11 | Southbound, from exit 10 to exit 11 |
All planned work is subject to postponement due to weather conditions.
Steel Girder Assemblies As piers are finalized in the coming weeks and months, steel girder assemblies for the approach span of the new bridge will continue being installed by the I Lift NY super crane.
Installation of Noise Barriers in South Nyack Next week will see continued installation of foundations for noise barriers along the southbound Thruway between the South Broadway bridge and River Road. The work will involve drilling holes into the soil to install the foundations. After the foundations are installed, concrete panels that form the noise barriers will be installed. The barriers will be treated with sound-absorbing material to further reduce traffic noise to the nearby community.
River Road in South Nyack River Road utility work will continue over the coming week. The work may require reducing River Road to one lane at times. TZC flag persons will direct traffic as needed and additional signage as well as other safety measures will be in place.
Foundation Work on the New Bridge Marine crews are continuing work on bridge foundations next week by placing reinforcing steel and concrete in the piles, main span pile caps and approach span pile caps. The high-strength concrete is made on site by the projects floating batch plants. Teams also will erect formwork for the cast-in-place pier columns, which eventually will support the new bridges road deck.
Crews also will continue working on the bridges landings at the Rockland and Westchester shorelines. The abutments, comprised of steel and concrete, will serve as strong bases where the new crossing meets the landside roadway.
Additionally, TZC will continue concrete placement for bridge foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and is delivered by truck to the Rockland trestle located off the Thruways southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.
Additional work includes:
- Girder installation
- Pile cap foundation construction
- Main span foundation construction
- Landing abutment concrete work
- Support for river-based work from the Rockland trestle
- Survey inspections on the existing bridge
- Westchester Landings utility work
All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.
TZ Bridge Traffic Update
EXIT 10 ON-RAMP TO SOUTHBOUND NEW YORK STATE THRUWAY (I-87/I-287) CLOSED TONIGHT, FRIDAY, MAY 29
Triple-Lane Closures, Periodic Traffic Stops of Southbound Thruway in South Nyack During Overnights the Week of June 1
The exit 10 (Nyack South Nyack US Route 9W) on-ramp to the southbound New York State Thruway (I-87/I-287) will be closed from 9 p.m., Friday, May 29 to 5 a.m., Saturday, May 30. Drivers will be directed to use the on-ramp from Route 59 in Nyack, as shown in the following graphic. The closure will allow Tappan Zee Constructors, LLC (TZC) to safely move equipment needed to place concrete slabs for a new temporary all-electronic toll collection system that will be employed until a permanent system is constructed in the location of the current toll plaza in Tarrytown.
Additionally, weekday overnight triple-lane closures of the southbound Thruway will occur from Monday night, June 1 through Saturday morning, June 6. Closures will start at 7 p.m. with the closing of one lane near exit 11 (Nyack – South Nyack – US Route 9W) to the Tappan Zee Bridge, followed by a second lane at 9 p.m. and a third at 10:30 p.m. All lanes will reopen by 6 a.m. the following weekday or 8 a.m. the following Saturday.
Additionally, a double-lane closure is planned for the overnight of Saturday, May 30, with a single lane closing at 7 p.m., followed by a second lane at 11 p.m. The lanes will reopen by 10 a.m., Sunday, May 31.
The lane closures are necessary to allow TZC to modify the highway for the temporary all-electronic toll collection system.
During the weekday and weekend overnight closures, at least one lane will remain open at all times, except during periodic traffic stops lasting up to 10 minutes of all four lanes of the southbound Thruway near exit 11 (Nyack South Nyack US Route 9W), which will occur between 8 p.m. and 5 a.m. during the overnights of Thursday, June 4 and Friday, June 5. To ensure the publics safety, the New York State Police will stop and hold all traffic approaching the area immediately before the traffic stops go into effect. Motorists will be permitted to enter the Thruway from all ramps during the traffic stops. The complete traffic stops are necessary to move equipment from the right shoulder to the left shoulder.
All planned work is subject to postponement due to weather conditions.
River Road in South Nyack
River Road utility work will continue during the week of June 1. The work may require reducing River Road to one lane at times. TZC flag persons will direct traffic as needed and additional signage as well as other safety measures will be in place.
Foundation Work on the New Bridge
Marine crews will continue working on the foundations for the new bridge next week by placing reinforcing steel and concrete in the piles, main span pile caps and approach span pile caps. The high-strength concrete is made on site by the projects floating batch plants. Teams also will erect formwork for the cast-in-place pier columns, which eventually will support the new bridges road deck.
While the current phase of pile driving is anticipated to end soon, pile driving will continue next week. Pile driving is restricted to 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.
Crews also will continue working on the bridges landings at the Rockland and Westchester shorelines. The abutments, comprised of steel and concrete, will serve as strong bases where the new crossing meets the landside roadway.
Construction of pier 1 located near River Road in South Nyack will continue with the installation of sheet piles. The sheet piles support the surrounding soil while the foundation for the new bridge pier is constructed. TZC is implementing noise-reducing measures, including sound-absorptive temporary noise barriers, to protect nearby residents. The projects environmental compliance team will be on site to monitor noise levels during the operation.
Additionally, TZC will continue concrete placement for bridge foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and is delivered by truck to the Rockland trestle located off the Thruways southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.
Additional work includes:
- Pile cap foundation construction
- Main span foundation construction
- Landing abutment concrete work
- Support for river-based work from the Rockland trestle
- Survey inspections on the existing bridge
- Westchester Landings utility work
Boater Safety
During the summer months, Westchester and Rockland Marine Units will add extra overnight patrols to monitor the construction zone and encourage all boaters to obey the established U.S. Coast Guard safety protocols.
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots and to use extreme caution on the river at all times.
More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on the very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.
Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.
All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/ for real-time information regarding traffic conditions.
SUPER CRANE SUCCESSFULLY COMPLETES FIRST LIFT ON
NEW NY BRIDGE PROJECT
I LIFT NY hoists massive 600-ton foundation element into place today
One of the world’s largest floating cranes this morning successfully completed the first of many enormous lifts for the New NY Bridge project, following months of planning and preparation.
In a carefully coordinated three-and-a-half hour operation on the Hudson River between Westchester and Rockland counties, the I Lift NY super crane hoisted and set one of the project’s largest precast concrete pile caps weighing in at 600 tons.
Video and photos from today’s lift will be posted here.
“We brought in the I Lift NY super crane to reduce construction time and cost, and this first lift is another symbol that the New NY Bridge is officially on the way,” Thruway Acting Executive Director Robert L. Megna. “The crane is a key tool to building the bridge in a safer, more cost-effective, environmentally-friendly way. With savings of more than a billion dollars for tollpayers, this super crane will continue to do great work.”
Owned by Tappan Zee Constructors, LLC, the design-build contractor for the New York State Thruway Authority, the super crane’s extraordinary capabilities save time and money while enhancing quality and safety by allowing large sections of the bridge to be pre-fabricated off-site and shipped by barge to the construction zone.
I Lift NY will continue to lift and place sections of the new twin-span bridge some weighing from 900 to 1,100 tons and will assist with the dismantling of the existing 60-year-old Tappan Zee Bridge, reducing costs and shortening the deconstruction process.
The super crane’s boom is 328 feet tall, which is taller than a 30-story building, and can lift up to 1,900 tons, or the equivalent of 12 Statues of Liberty, at once. Despite its enormity, the barge-mounted crane sits high in the water, thereby reducing the need for dredging on the project by 50 percent.
The I Lift NY super crane made a 6,000-mile journey from the San Francisco Bay area in 2014, passing through the Panama Canal.
Since its arrival here in New York, the crane has gone through months of testing, modifications and upgrades including a new high-tech computer operating system and complete replacement of its rigging cables. The most experienced operating engineers in the area also spent months of specialized training to carefully handle this massive machine. Now that the ice has cleared on the Hudson River, the I Lift NY crane is getting to work on the pile caps and later this year will begin placing the even heavier structural steel beams that will carry the road deck across the new spans.
New NY Bridge Progress
Under Governor Cuomo’s leadership and with the support of President Barack Obama and the Federal government, the New NY Bridge project has progressed dramatically since construction began in October 2013 following many years of delay. Since October 2011, steps forward include: enactment of new design-build legislation; review and completion of concurrent environmental review and procurement processes; negotiation of a project labor agreement with construction unions; and recommendation from a panel of local leaders and transportation experts for a comprehensive plan for mass transit options for the region all with an unprecedented level of transparency and community involvement.
About the New NY Bridge
The New NY Bridge’s eight traffic lanes, four breakdown and emergency lanes, and state-of-the-art traffic monitoring systems will mean less congestion for motorists. Designed and constructed to be mass-transit-ready, the new crossing will be able to accommodate bus rapid transit, as well as light rail or commuter rail. The bridge will also include a bike and pedestrian shared-use path. Extensive measures are in place throughout the duration of the project to protect the environment and to monitor the impact of construction on surrounding communities.
I LIFT NY SUPER CRANE SPECIFICATIONS
Type of vessel: Floating Sheerleg Crane
Propulsion: None
Hull material: Steel
Lifting capacity: 1,929 tons
Length: 384 feet
Breadth: 99.8 feet
Depth: 22 feet
Boom length: 328.08 feet
Boom width: 65.7 feet
Min. boom angle for transport: 4 degrees
Min. boom angle for lifting: 19 degrees
Max. boom angle for lifting: 67 degrees
For more information or for photos and video of the I Lift NY super crane’s first lift, go to www.NewNYBridge.com
New Year of Construction Looking Ahead to 2015
Traffic Update thru Jan 4th to Ease Holiday Travels
For immediate release: December 26, 2014
ALL LANES OF NEW YORK STATE THRUWAY (I-87/I-287) WILL REMAIN OPEN FROM FRIDAY DEC. 26, 2014 THROUGH SUNDAY, JAN. 4, 2015 TO EASE HOLIDAY TRAVEL All lanes of the New York State Thruway (I-87/I-287) will remain open from Friday, Dec. 26, 2014 through Sunday, Jan. 4, 2015 to help New Yorkers reach their winter holiday destinations. The 10-day lane-closure-free period follows Governor Andrew M. Cuomo’s “Drivers First” initiative, which gives priority to motorists by ensuring that disruptions associated with highway and bridge projects are kept as minimal as possible. While Tappan Zee Constructors, LLC (TZC) will continue working in several areas of the project during the week of Dec. 29, none of the planned activities will result in the closure of any traffic lanes. No construction work is scheduled for New Year’s Day, Thursday, Jan. 1, 2015, though safety and security teams will remain on site. Limited concrete placement will continue as TZC progresses the investigation of the recent incident on one of its floating concrete batch plants. The concrete for foundations near the S. Nyack shoreline will be acquired from local concrete suppliers that will be delivered to the site via trucks to the Rockland Trestle off of the New York State Thruway southbound access ramp. The trucks will exit the trestle to the Thruway via the northbound access ramp. This work could begin as soon as this week. Activities on the Westchester and Rockland landings will continue as originally scheduled as this work has always been planned to receive the needed concrete from trucks to the site. Continued Demolition of Westchester Landing of Existing Tappan Zee Bridge Pile Driving and Other Construction Activity A second shift of workers also will continue pile welding, pile cleanout and concrete placement operations associated with foundations. Work is continuing on the new bridge’s landings on both sides of the river. Additional work includes:
Boater Safety More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation. Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment. All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions |
Holiday Travel this week on the TZ Bridge
For immediate release: December 19, 2014
ALL LANES OF NEW YORK STATE THRUWAY (I-87/I-287) WILL REMAIN OPEN FROM WEDNESDAY, DEC. 24 THROUGH SUNDAY, DEC. 28 TO EASE HOLIDAY TRAVEL
All lanes of the New York State Thruway (I-87/I-287) will remain open from Wednesday, Dec. 24 through Sunday, Dec. 28 to help New Yorkers reach their winter holiday destinations. The five-day, lane-closure-free period follows Governor Andrew M. Cuomo’s “Drivers First” initiative, which gives priority to motorists by ensuring that disruptions associated with highway and bridge projects are kept as minimal as possible.
While Tappan Zee Constructors, LLC (TZC) will continue working in several areas of the project during the week of Dec. 22, none of the planned activities will result in the closure of any traffic lanes. No construction work is scheduled for Christmas Day, Thursday, Dec. 25, though safety and security teams will remain on site.
20-Minute closures of the north- and southbound Thruway and other lane closures scheduled for overnight Friday, Dec. 19
The removal of an overhead sign gantry near exit 10 in South Nyack will require the closure of three lanes of the southbound New York State Thruway (I-87/I-287) during the overnight of Friday, Dec. 19. Two lanes will be closed at 9 p.m., followed by a third lane at 12 midnight. One lane will remain open, other than during the periodic complete closures detailed below. The three closed lanes will reopen at 7 a.m., Saturday, Dec. 20.
The operation also will require a series of 20-minute closures of all four lanes on both the north- and southbound Thruway between the hours of 11:59 p.m., Friday, December 19 and 6 a.m., Saturday, December 20. To ensure the safety of the public, the New York State Police will stop and hold all traffic approaching the gantry removal operation immediately before the closures go into effect. Motorists will be permitted to enter the Thruway from all ramps during the closures.
Travelers are advised that delays are likely on both directions of the Thruway during the overnight operation.
Continued Demolition of Westchester Landing of Existing Tappan Zee Bridge
Following the removal of sections of deck of the existing Tappan Zee Bridge to make way for the new bridge, the associated supporting piers are being demolished. The majority of this work, which will clear the path for the northbound bridge’s landing and first foundation pier, will be completed during daytime hours.
Pile Driving and Other Construction Activity
Construction will continue in the Hudson River as crews place the foundations of the new bridge. Work will include pile driving from 7 a.m. to 7 p.m., Monday through Wednesday and noon to 7 p.m., Saturday. No pile driving will occur on Christmas Day, Thursday, Dec. 25 or Friday Dec. 26.
A second shift of workers also will continue pile welding, pile cleanout and concrete placement operations associated with foundations.
Work is continuing on the new bridge’s landings on both sides of the river.
Additional work includes:
- Pile cap foundation construction
- Main span foundation construction
- River Road utility work
- Support for river-based work from the Rockland trestle
- Survey inspections on existing bridge
Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.
More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.
Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.
All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.
2014 New NY Bridge Project Monthly Newsletter
Exhibits on Display this Month Dozens of art works interpreting the Tappan Zee Bridge and marking the construction of the New NY Bridge will be on display this fall at the new bridge project Community Outreach Centers in Rockland and Westchester. The art was created for the New York State Thruway Authority’s 2014 Bridge Art Show, a juried exhibition that invited local painters, sculptors and photographers to showcase their interpretations of the new bridge design or the existing Tappan Zee Bridge. |
The New NY Bridge team’s high standards of quality and precision are crucial to the day-to-day operations of the project. To ensure that the bridge’s foundation piles are welded with consistent accuracy, skilled operators are utilizing advanced mechanical welding machines. |
|
The Hudson Valley is a unique geological formation, created by receding glaciers tens of thousands of years ago. As the colossal sheets of ice melted and formed the Great Lakes, the melt-water rushed down the Palisades and filled the Hudson Valley with enough sediment to bury the Statue of Liberty. This torrential force of nature created the striking Hudson Valley landscape and more recently, a number of geotechnical hurdles for the New NY Bridge project. |
|
The New York State Thruway Authority, Tappan Zee Constructors, LLC (TZC) and the U.S. Coast Guard have worked together to establish a safe channel for recreational boaters looking to access Piermont’s popular waterfront. The newly-marked channel is part of the New NY Bridge project team’s ongoing efforts to enhance boater safety in and around the construction area. |
|
|
UPDATED: VIEWING PLATFORMS TAKE SHAPE AS CONSTRUCTION CONTINUES ON THE NEW NY BRIDGE PROJECT
For immediate release: September 5, 2014
UPDATED: VIEWING PLATFORMS TAKE SHAPE AS CONSTRUCTION CONTINUES ON THE NEW NY BRIDGE PROJECT
Construction on the New NY Bridge viewing platform in Nyack took another step forward this past week as Nyack officials broke ground on a new fishing pier in Memorial Park. The pier will be the site of the Rockland viewing platform. The plan for the site is the result of months of collaboration between village officials and the New NY Bridge project team
Viewing platforms in Nyack and at Scenic Hudson RiverWalk Park in Tarrytown will provide residents and visitors with an unobstructed and easily accessible view of the historic project’s progress and will include spotter’s guides, informational signs and high tech binoculars.
The installation of the new bridge’s pile caps will continue the week of Sept. 8. The caps, which cover the foundation piles installed in the river, are large hollow tubs that are fabricated offsite. The forms weigh several hundred tons and are barged to the project site for installation. Once in place, they are filled with reinforcing steel and concrete.
Construction will continue in the Hudson River as crews place the foundation for the New NY Bridge. Work will include pile driving between 7 a.m. and 7 p.m., Monday through Friday and 12 noon to 7 p.m. on Saturday.
A second shift of workers will also continue pile welding, pile cleanout and concrete placement operations associated with permanent foundations.
TZC will also continue construction on the new bridge’s Westchester landing, drilling holes into the bedrock for the foundation. This drilling process will produce less noise than the impact pile driving alternative, and TZC has installed sound mitigation to further reduce noise levels for the eight-week operation. The work will continue to the new westbound abutment in Westchester over the next few weeks.
Sheet pile installation at the Rockland landing is complete at this time. The sheet piles will allow TZC to excavate soil in that location and construct the westbound landing for the new bridge.
Work will continue on the Rockland work trestle near the shoreline, including pile driving and cofferdam installation. The trestle will support equipment used for the construction of the westernmost section of the new bridge.
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of five knots, and to use extreme caution on the river at all times.
More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.
Mariners should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.
Lane Closures for New York State Thruway (I-87/I-287):
Monday | Sept 08 | Northbound, Left Lane near Exit 9 | 9 a.m. to 3 p.m. |
Tuesday | Sept 09 | Northbound, Left Lane near Exit 9 | 9 a.m. to 3 p.m. |
Wednesday | Sept 10 | Southbound, Right Lane near Exit 9 | 10 a.m. to 3 p.m. |
Ongoing Operations:
- Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays
- Pile Cap foundation construction
- Main Span foundation construction
- Rockland Landing construction
- Westchester landing construction
- River Road utility work
- Rockland trestle construction, including pile driving
- Survey inspections on existing bridge
- Support for river-based work from the Rockland trestle
T.Z. Bridge: State cops move to Rockland from Tarrytown
LoHud august 8, 2014 Theresa Juva-Brown, tjuva@lohud.com
If you’re looking for the state police station in Tarrytown, be prepared to drive across the Tappan Zee Bridge to Rockland.
Troopers have moved to 160 N. Route 303 in West Nyack, where they will share a 42,000-square-foot building with 28 Thruway Authority employees for the next four years. It also is housing the headquarters of Zone 1, which includes three state police barracks in the region.
The Thruway and state police leave behind an 18,000-square-foot building on Route 9 that will be torn down in the next year to make way for Tappan Zee Bridge construction activities.
“We were over there for 50-plus years in that barracks,” said state police Capt. Richard Mazzone, commander of Zone 1. “The move — when you’ve been in the building that long — is certainly a little difficult, but we certainly planned it well, and we’ve made the move rather seamless.”
Though the Tarrytown station is now in Rockland, it has retained its Westchester identity.
“We are referring to it as the Tarrytown barracks,” Mazzone said. “This is a temporary facility.”
In 2018 after the new Tappan Zee Bridge is completed, state police and the Thruway Authority will move back to Tarrytown to separate locations that have yet to be built.
For the past month, troopers have been settling into the transformed warehouse, the former Journal News printing plant. The new building has its perks — a lot more space — but also drawbacks — a lack of windows and natural light.
Mazzone said he doesn’t know of any problems with people finding the new location, which is a couple miles from the Tappan Zee, unlike the old barracks.
“As far as the 100 miles of roadway in Zone 1, the bridge is one of the most critical pieces of roadway,” he said. “It’s definitely going to be nicer when we get back in the new facility, where I can look out the window and actually see the bridge.”
That will be especially important because the new 3-mile crossing will have a path for cyclists and pedestrians.
“We’re certainly anticipating some additional responsibilities with the shared-use path,” Mazzone said.
PROJECT UPDATE FOR BOATERS
NEW NY BRIDGE PROJECT ESTABLISHES SAFE CHANNEL FOR PIERMONT BOATERS
Following collaboration with the U.S. Coast Guard, the New NY Bridge project team has installed channel markers near Piermont to help guide recreational boaters to and from the Hudson River Main Channel.
Soil borings will begin in South Nyack near the intersection of S. Broadway and Cornelison Ave. during the week of August 11 to inform preliminary design options. The samples of material will be taken in different areas to help designers understand subsurface conditions that may be experienced during construction. Some survey activities are also being performed to support these design investigations. These operations require temporary lane closures and traffic control measures including flaggers to maintain safety and movement of local traffic.
Construction will continue in the Hudson River as crews place the foundation for the New NY Bridge. Work will include pile driving between 7 a.m. and 7 p.m., Monday through Friday and 12 noon to 7 p.m. on Saturday.
A second shift of workers will also continue pile welding, pile cleanout and concrete placement operations associated with permanent foundations.
Sheet pile driving at locations on land and near the Rockland landing is temporarily on hold due to high noise levels from the operation. Tappan Zee Constructors, LLC (TZC) continues to implement additional noise-reducing measures at sheet pile driving operations at the Rockland Landing and in the river at one of the closest piers to the shoreline. Sheet pile driving operations will continue as soon as noise is at an allowable level.
Work will continue on the Rockland work trestle near the shoreline, including pile driving. The trestle will support equipment used for the construction of the western-most section of the new bridge.
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of five knots, and to use extreme caution on the river at all times.
More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners, and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.
Mariners should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.
Lane Closures for New York State Thruway (I-87/I-287):
Monday | Aug 11 | Northbound, Left Lane near Exit 9 | 10 a.m. to 3 p.m. |
Monday | Aug 11 | Northbound, Right Lane approaching the Tappan Zee Bridge | 9 p.m. to 5 a.m. |
Tuesday | Aug 12 | Southbound, Left Lane approaching the Toll Plaza and Left hand EZ-Pass Lanes. | 10 a.m. to 3 p.m. |
Tuesday | Aug 12 | Northbound, Right Lane approaching the Tappan Zee Bridge | 9 p.m. to 5 a.m. |
Wednesday | Aug 13 | Northbound, Left Lane near Exit 9 | 10 a.m. to 3 p.m. |
Wednesday | Aug 13 | Northbound, Right Lane approaching the Tappan Zee Bridge | 9 p.m. to 5 a.m. |
Thursday | Aug 14 | Southbound, Right Lane near Exit 9 | 10 a.m. to 3 p.m. |
Thursday | Aug 14 | Northbound, Right Lane approaching the Tappan Zee Bridge | 9 p.m. to 5 a.m. |
Friday | Aug 15 | Southbound, Right Lane near exit 9 | 10 a.m. to 1 p.m. |
Friday | Aug 15 | Northbound, Right Lane approaching the Tappan Zee Bridge | 9 p.m. to 5 a.m. |
Ongoing Operations:
- Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays
- Pile Cap foundation construction
- Main Span foundation construction
- Rockland Landing construction
- Westchester Landing construction
- River Road utility work
- Rockland trestle construction, including pile driving
- Survey inspections on existing bridge
Support for river-based work from the Rockland trestle
Tappan Zee Bridge path critic teams with South Nyack
South Nyack beefs up its TZ Task Force as it tackles surrounding the new crossing’s bike and walking path.
Following a public outcry, the three members of South Nyack’s bridge task force quickly decided to hit the reset button, asking the Tappan Zee project team to work with them to take another look at where the path would end in the village, where people would park and other local impacts.
The task force also made another move: it added Toolan to its team, along with Nancy Willen, who recently retired from the Clarkstown Highway Department.
Toolan, a land surveyor currently working on the Second Avenue subway project in Manhattan, has remained active since that contentious meeting with village and project officials at Nyack College. In many ways, he represents the other village residents who spoke that night, those skeptical of the state’s intentions and worried about the dangers that drivers in search of parking in neighborhoods would pose to residents.
A resident since 2007, Toolan, his wife and three children live on Cornelison Avenue, not far from the proposed site for the path’s terminus at the corner of his street and South Broadway. That terminus would be directly across from a southbound entrance to the Thruway.
“I’m pretty directly affected by what’s happening with that” path, Toolan said, describing its location “an afterthought” on the state’s part.
Rather than just complain, Toolan has been trying to come up with solutions, as he’s well-versed in blueprints and design technicalities.
Even before joining the task force, he met with project engineers to pitch a plan. It’s a bit complicated but basically allows Interchange 10 to remain a construction staging area for the duration of building, but eliminates the need to circle entirely around the interchange. Instead, he envisions a roundabout near South Franklin Street. He calls for reconnecting Route 9W back to Hillside Avenue to handle two-way traffic and closing off the Thruway entrance on South Broadway, so the ramp can be used for parking.
Though he has no hard cost figures, he admits it would carry “quite a price tag.”
“It’s kind of grandiose, but it all makes sense,” Toolan said. He also belongs to the Tappan Zee Gateway Alliance, a recently formed group concerned about the location of the shared path.
A rendering of Toolan’s proposal will be included in a meeting to update the community of the different ideas. It may take place this month.
Toolan remains a pragmatist though. He said ending the path at Cornelison as originally planned remains “a huge possibility.”
But it won’t be for a lack of effort from him and others in the community.
“I know there’s a lot of animosity you can get wrapped up in, but I would rather get a good solution than focus on what was done in the past,” Toolan said.
Willen, a 10-year resident of South Nyack, acknowledged that while she had to catch up with the rest of the volunteer task force, her experience working as confidential secretary to the highway superintendent for 16 years made her familiar with some of the issues and players involved.
Connie Coker, a member of the village task force, was excited to see what the two newest members would bring to the conversation.
“I think they’re both really going to add a lot,” Coker said.
Twitter: @ksaeed1
Pile work for Tappan Zee Bridge starting in South Nyack
Khurram Saeed, ksaeed@lohud.com
Sheet piles will be installed just off River Road to create a temporary support wall for the Rockland landing of the new bridge.
Work is starting later this week to install 60-foot-long flat sheet piles along the northbound Thruway near River Road. The work will last about three weeks and take place only during the day, said Carla Julian, spokeswoman for bridge builder Tappan Zee Constructors. The sheet piles, which are different from the round pipe piles being used in the Hudson, will create a temporary continuous wall that will support the Thruway during the excavation and construction for the Rockland landing of the new bridge, Julian said in an email.
About 45 to 50 sheets are needed to cover approximately 100 feet, and crews typically average three piles per day, Julian saidThe site formerly housed a state Thruway Authority maintenance building; it was demolished a few weeks ago. A 165-foot tall crane positioned just off River Road will install the piles into the ground using a vibratory hammer, an alternative to louder pile driving.
The interlocking sheets are installed in sequence. Julian said crews first install a 25-foot-high template, lift and swing a sheet into the template, position it and drive enough of the pile to stand in the template, drive additional sheets, move the template and drive the piles the remaining depth.”The actual pile driving is the fastest part of the process and is not done in one shot,” she said.Tappan Zee Constructors crews are expected to be on the site Wednesday to mobilize and plan to begin work on Thursday or Friday.The pile work will require the closure of the right lane on the northbound Thruway for some of the operation, Julian said.
The lane will be closed this week from 10 a.m. to 3 p.m. Wednesday and Thursday, and from 10 a.m. to 1 p.m. on Friday. The project team has a video on YouTube providing an animated look at the construction of the new bridge’s main span foundation and towers.
FOUNDATION WORK CONTINUES ON THE NEW NY BRIDGE
Bridge Project Update
For immediate release: May 30, 2014
FOUNDATION WORK CONTINUES ON THE NEW NY BRIDGE
Construction of the New NY Bridge continues the week of June 2 with pile driving between 7 a.m. and 7 p.m., Tuesday through Friday. A second shift of workers will also continue pile welding operations associated with permanent foundations.
Marine crews are working from the shorelines of Rockland and Westchester counties, moving outward to place permanent foundation piles. Work on the foundations for the main span will continue as well. To learn more about the main span foundation and tower construction see the new “Bridge Rising” animation on NewNYBridge.com
Work will also continue on the Rockland work trestles near the county shorelines, including pile driving to install the temporary foundations needed to support the platforms. The trestle will support cranes for the construction of the western-most sections of the new bridge.
Lane Closures for New York State Thruway (I-87/I-287):
Monday | June 2 | Southbound, Right Lane near Exit 10 | 10 a.m. to 3 p.m. |
Tuesday | June 3 | Southbound, Right Lane near Exit 10 | 10 a.m. to 3 p.m. |
Wednesday | June 4 | Northbound, Right Lane near Exit 10 | 10 a.m. to 3 p.m. |
Thursday | June 5 | Northbound, Right Lane near Exit 10 | 10 a.m. to 3 p.m. |
Friday | June 6 | Northbound, Right Lane near Exit 10 | 10 a.m. to 1 p.m. |
Mariners should be aware that TZC will continue installing permanent piles in the vicinity of the side channels under the existing bridge, weather permitting. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Both temporary and permanent piles are illuminated at night. An interactive map showing vessel locations on the Hudson River is now available on the project website, NewNYBridge.com, for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation. More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here.
Ongoing Operations:
- Permanent pile installation, including pile driving between 7 a.m. and 7 p.m. on weekdays, and between noon and 7 p.m. on Saturdays
- Rockland Landing construction
- Westchester Landing construction
- River Road utility work
- Rockland trestle construction, including pile driving
- Survey inspections on existing bridge
- Support for river-based work from the Rockland shoreline
- Armoring of Dredge channel
- Construction of Temporary Joint Facility at exit 12
In Progress: Tappan Zee crews work around the clock to install piles
A short reprieve from bad weather in the last week has finally allowed Tappan Zee Bridge construction crews to resume work on the Hudson River.
LoHud By Theresa Juva-Brown11:26 p.m. EST March 3, 2014
A short reprieve from bad weather in the last week has finally allowed Tappan Zee Bridge construction crews to resume work on the Hudson River.
Not only are they back to work, but crews are toiling away around the clock to install giant steel piles that will help support the new crossing. The pile
s are being installed in two segments and then welded together.
The pile welders, members of the local dockbuilders union, are working six days a week in two 12-hour shifts. As the work progresses, a third shift will be added, with each team of welders working eight-hour shifts six days a week, project leaders say.
Over the next year, leaders have said they hope to have 1,000 piles installed in the river. Crews are currently working on a batch of 90 piles.
In other Tappan Zee Bridge project news this week:
• The project’s 31-member mass transit task force delivered its final report on Friday, after more than a year of meetings. The Thruway Authority formed the panel in 2012 to study and make recommendations for mass transit improvements on Interstate 287.
• The panel has proposed expanding the existing Tappan ZEExpress bus service and a creating a “bus rapid transit” system with seven routes in Westchester and Rockland. The ambitious plan calls for a series of new stations, modern vehicles, and dedicated bus lanes in some places.
• The report did not include cost estimates or specific ways to pay for such a system. Still, top state transportation leaders said they are committed to having the system in place by the time the new Tappan Zee is completed in 2018.
THIRD NEW CONSTRUCTION CAMERA GOES LIVE
Project Update
For immediate release: November 15, 2013
Residents and motorists now have a Rockland County-view of work at the site of the New NY Bridge with the addition of a third construction camera. The construction camera went live this afternoon at NewNYBridge.com, and joins two others that provide views from Tarrytown and the Tappan Zee Bridge, respectively.
Located on a hill overlooking the Hudson River in Upper Grandview, the newest construction camera offers a view of the existing span, as well as barges, equipment and the permanent piles that are currently being constructed.
The installation of permanent piles will continue at the site next week, as will “armoring” of the dredge channel. Armoring is a process that helps protect the water quality for marine life. Currently, TZC crews are layering sand and stone within the dredge channel to armor the river bottom in an effort to ensure sediment is not kicked up by construction vessels.
The creation of the first of four new permanent noise barriers is also underway in Rockland County and sections of the existing noise wall along northbound I-87/I-287 in the area south of exit 10 will continue to be removed next week. From Monday, Nov. 18 to Wednesday, Nov. 20, one northbound right-hand lane and shoulder on I-87/I-287 in the area south of exit 10 in Nyack will be closed from 10 a.m. to 3 p.m. for sound wall removal. A temporary noise barrier and noise monitors have been installed nearby and additional temporary noise barriers will be installed along a local access ramp and the New York State Thruway, after improvements are made to the ramp.
Mariners should be aware that TZC will be installing permanent piles in the vicinity of the side channels under the existing bridge. Pile driving will take place between 7 a.m. and 7 p.m. on weekdays, and occasionally between noon and 7 p.m. on Saturdays. New temporary navigational lights have been installed to further define the 600’ navigation channel under the main span. Both temporary and permanent piles are illuminated at night.
The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including the establishment of a Regulated Navigation Area (RNA) 300 yards north and 200 yards south of the existing Tappan Zee Bridge. All boaters are advised to use the main channel, reduce wake and use extreme caution while transiting the area. If necessary, the Coast Guard in the future may temporarily prohibit all vessel traffic in the RNA for safety purposes. The Coast Guard boating safety information can be found on the project website under the “Boating Safety” icon.
Ongoing operations:
- Rockland access ramp modifications
- Armoring of dredge channel
- River Road utility work
- Test pile program
- Rockland Dock Extension – finishing work under existing bridge
- Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
- Survey inspections on existing bridge
- Support for river-based work from the Rockland shoreline
- Reinforcement steel pre-assembly at bridge yard
The first permanent piles for the New Tappan Zee Bridge are going in this week.
Tarrytown-Sleepy Hollow Patch; Posted by Krista Madsen (Editor) ,
The big news on today’s media boat tour of the work surrounding the Tappan Zee Bridge was that construction is now officially underway for the new bridge.
All the action we’ve been seeing for months in the river has been preconstruction work – test piling, geotechnical investigations, dredging. Just this week, permanent piles are being vibrated, and then pounded, in place to begin forming the bridge’s foundation.
“This week, we are putting shovels in the ground and starting formal construction on a new bridge to replace the Tappan Zee, the largest infrastructure project New York State has undertaken in decades,” Governor Andrew Cuomo said in a press release following the tour, which was cut a little short due to the threat of rain.
“After more than a decade of delay, New York State has moved this project forward at a dramatic pace while working with the community, involving the public and protecting the local environment,” Cuomo said. “Once completed, drivers in Rockland, Westchester and surrounding areas will finally have a safer, less congested bridge that will include a walkway for pedestrians and bikers and accommodates future mass transit.”
The project, said Thruway Authority Chairman Howard Milstein, is on track with a projected build timeline in place of just under five years.
Bridge cam anyone? You can watch the progress up close as it happens on a new ‘Construction Camera’ section of the New NY bridge website.
The specifics of the five-year timeline to date:
· Dredging to prepare for bridge construction is ongoing until November 1, and will also take place during August, September and October, 2014.
· October 2013: Main span permanent pile installation begins
· November 2013: Permanent pile installation begins for approaches
· March 2014: Work begins on approach substructure
· June 2014: Work begins on main span substructure
· September 2014: Work begins for erection of superstructure
· Late 2014 / early 2015: Work begins on cable stay installation
· Late 2016: Complete north span
· December 2016: Relocate westbound traffic to new north span
· February 2017: Relocate existing eastbound traffic to new north span
· February 2017: Start demolition of existing bridge
· Late 2017: Both spans complete
· November 2017: Relocate eastbound traffic from new north span to new south span
· April 2018: Physical completion of project
· July 2018: Final acceptance of project
There are reports that one of the world’s largest floating cranes, the Left Coast Lifter, is in Virginia now, ever so slowly making its way upriver for the biggest show we’ll see yet.
Read complete article here:
New NY Bridge Update August 16, 2013: LOAD TESTING FOR THE TEST PILE PROGRAM BEGINS; LANE CLOSURES ON BRIDGE
For immediate release: August 16, 2013
LOAD TESTING FOR THE TEST PILE PROGRAM BEGINS;
LANE CLOSURES ON BRIDGE
Tappan Zee Constructors, LLC (TZC) will begin testing both static and lateral loads this week as part of its test pile program.
These load tests are performed to ensure piles are capable of sustaining the design load of the new bridge. Testing will be conducted over a 40-hour period.
Impact pile driving will continue this week as part of the ongoing test pile program and will continue through October at various locations for future pile foundations. This work will be performed from 7 a.m. to 7 p.m. on weekdays and, at times, on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.
Overnight lane closures will also be required in both directions on I-87/I-287 and the Tappan Zee Bridge due to various construction activities.
Beginning Monday, August 19 through the morning of Wednesday, August 21, one southbound right hand lane and shoulder between exit 11 and the Tappan Zee Bridge will be closed from 9 p.m. to 6 a.m. for the installation of concrete traffic barriers to facilitate the reconstruction of the Thruway maintenance ramp. Additionally, one southbound right hand lane on the Tappan Zee Bridge will be closed during this period for the installation of structural monitors.
Beginning Wednesday, August 21 through the morning of Saturday, August 24, one northbound right hand lane and shoulder between exit 9 and the Tappan Zee Bridge, as well as one northbound right hand lane on the Tappan Zee Bridge will be closed from 9 p.m. to 6 a.m. for the installation of structural monitors.
Additional geotechnical borings will be conducted on the river at various locations. Operations will run 24 hours a day, Monday through Friday.
TZC will continue dredging operations in the Hudson River as part of the New NY Bridge Project. Dredging will occur through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.
Dredging crews will work 24 hours a day, seven days a week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.
The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.
The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.
Ongoing operations:
· Test pile program
· Rockland bulkhead construction (including fence & gates) and Dock Extension at Rockland (under existing bridge)
· Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline
Rockland:
TZC will continue fencing and sidewalk work along River Road in South Nyack north of the existing bridge. This work is part of the bulkhead construction area and will be performed on weekdays between 7 a.m. and 3 p.m. At times, River Road will be limited to one lane with flag persons in place to ensure the safe flow of traffic.
DREDGING OPERATIONS AND TEST PILE PROGRAM IMPACT PILE DRIVING CONTINUE
For immediate release: August 9, 2013
Tappan Zee Constructors, LLC (TZC) will continue 24-hour-a day dredging operations in the Hudson River as part of the New NY Bridge Project.
The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.
The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.
Dredging will occur over a three-month period from August 1 through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.
Dredging crews will work 24-hours-a-day, seven-days-a-week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.
Impact pile driving will continue this week as part of the ongoing test pile program and will continue through October 31 at various locations for future pile foundations. This work will be performed from 7 a.m. to 7 p.m. on weekdays and, at times, on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.
Ongoing operations:
· Test pile program
· Geotechnical land borings
· Rockland bulkhead construction (including fence & gates) and Dock Extension at Rockland (under existing bridge)
· Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Rockland and Westchester environmental monitor installations
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline
Westchester:
Ongoing geotechnical boring activities will continue to support the developing design for the New NY Bridge Project.
Rockland:
TZC will continue fencing and sidewalk work along River Road in South Nyack north of the existing bridge. This work is part of the bulkhead construction area and will be performed between 7 a.m. and 3 p.m. Monday through Friday. River Road will be limited at times to one lane with flag persons in place to control traffic safely.
DREDGING OPERATIONS BEGIN, TEST PILE PROGRAM IMPACT PILE DRIVING ONGOING
Project Update
For immediate release: August 2, 2013
Tappan Zee Constructors, LLC (TZC) began 24 hour a day dredging operations today in the Hudson River as part of the New NY Bridge Project.
The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use extreme caution within 1,000 feet of all construction barges as a safety precaution.
The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com.
Dredging will occur over a three-month period from August 1 through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.
Dredging crews will work 24 hours a day, seven days a week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being processed and properly disposed at offsite locations.
Impact Pile driving began this week as part of the ongoing test pile program and will continue over the next three months at various locations for future pile foundations. This work will be performed 7 a.m. to 7 p.m. on weekdays and at times on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions test structural load capacities in preparation for construction of the new bridge’s permanent foundation.
Ongoing operations:
· Test pile program
· Rockland bulkhead construction (including fence & gates)
· Dock Extension at Rockland (under existing bridge)
· Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Rockland and Westchester environmental monitor installations
· Geotechnical land borings
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline
Westchester:
Limited test-boring operations will continue on Thruway property near the Irving Neighborhood in Tarrytown. The work is scheduled to be conducted between the hours of 7 a.m. and 5 p.m. Monday, August 5 through Wednesday, August 6.
Rockland:
TZC, LLC will reconstruct the sidewalk along River Road in S. Nyack north of the existing bridge. This is part of the Bulkhead construction area and will be performed between 7 a.m. and 3 p.m. Monday, August 5 and Tuesday, August 6. River Road will be limited to one lane with flag persons in place to control traffic safely.
Survey activity will occur in the southbound lanes of I-87/I-287 and will require a temporary lane closure between exit 10 and the existing bridge from 10 a.m. to 3 p.m. Monday, August 5 and Tuesday, August 6.
Pile Driving Set To Begin This Week
For immediate release: July 26, 2013
TEST PILE PROGRAM IMPACT PILE DRIVING SET TO BEGIN,
ROCKLAND THRUWAY DOCK CONSTRUCTION GETTING UNDERWAY
Tappan Zee Constructors, LLC (TZC) is scheduled to begin impact pile driving as part of the ongoing test pile operation this week. The test pile installation will continue over the next two to three months at the proposed locations of the foundations for the New NY Bridge. The test pile program will verify subsurface conditions in the river and the structural capacity of the pilings.
Under the Final Environmental Impact Statement, the hours of impact pile driving are restricted to 7 a.m. to 7 p.m., Monday through Friday and 12:00 noon to 7 p.m. on Saturday. There is no impact pile driving allowed at night or on Sundays. Noise monitors are in place along the Rockland and Westchester shorelines and the data is available at www.NewNYBridge.com.
Construction of the New York State Thruway’s temporary dock at the Rockland Maintenance facility on River Road in South Nyack will begin the week of July 29. TZC will reconstruct a maintenance dock that was damaged during Superstorm Sandy. This new dock will allow the Thruway to continue its normal maintenance work on the existing Tappan Zee as the construction activities for the New NY Bridge get underway.
Orange and Rockland Utilities will install new utility poles near River Road in South Nyack to support utility relocations which are needed for the New NY Bridge project. These operations may require temporary lane closures and will be performed by the utility.
Ongoing operations:
· Test pile program
· Rockland bulkhead construction
· Temporary Westchester trestle construction including pile driving on weekdays from
7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Rockland and Westchester environmental monitor installations
· Geotechnical land borings
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline
Westchester:
Survey crews will be conducting surveys in the toll plaza area in Tarrytown on Wednesday, July 31 requiring temporary closures of toll lanes conducted one at a time.
Rockland:
Geotechnical boring operations to investigate subsurface soil conditions will be conducted in the northbound lanes of I-87/I-287 and will require a temporary lane closure between the existing bridge to Interchange 10 in South Nyack from 10 a.m. to 3 p.m. on Monday, July 29 through Wednesday, July 31. Southbound lane closures will be required from Interchange 10 to the existing bridge between 10 a.m. and 3 p.m. on Thursday, August 1 and from 10 a.m. to 2 p.m. Friday, August 2.
ROCKLAND BULKHEAD CONSTRUCTION TO BEGIN–TEST PILE PROGRAM CONTINUES
FOR IMMEDIATE RELEASE; JULY 19, 2013
Construction of the Rockland Bulkhead will begin next week as crews enlarge the work platform in the New York State Thruway Authority’s Rockland maintenance area located on River Road in South Nyack.
The bulkhead will be part of the Thruway’s permanent dock and serve as the access point for Tappan Zee Constructors, LLC’s (TZC) Rockland trestle. The trestle is the support platform that will allow TZC to build the foundations for the new bridge near the Rockland shoreline without dredging in that area. TZC will utilize the bulkhead for support of construction throughout the entire project.
Orange and Rockland Utilities will install new utility poles near River Road in South Nyack to support utility relocations which are needed for the New NY Bridge project. These operations may require temporary lane closures and will be performed by the utility.
Test pile driving operations will be conducted over the next three months at proposed locations for pile foundations. The test pile program will verify subsurface conditions in preparation for the construction of the bridge’s permanent foundation.
Multiple crews will conduct night time boring operations along I-87/I-287 in both directions in Westchester and Rockland Counties. The night time operations are necessary due to lane closure restrictions during day time hours that are in place to keep traffic flowing over the current bridge. Boring operations began at exit 10 in Rockland County and continue to move west into Westchester County and then back to Rockland for one final boring location.
Ongoing operations:
– Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
– Survey inspections on existing bridge
– Rockland environmental monitor installations continue
– Geotechnical land borings
– Mobilization at the exit 10 staging area
– Support for river-based work from the Rockland shoreline
– Extension of Thruway’s Rockland maintenance dock
Westchester:
Night time boring operations to investigate subsurface soil conditions will be conducted in the southbound shoulder of I-87/I-287and will require a temporary right lane closure between the existing bridge and exit 9 on Tuesday, July 23, from 9 p.m. to 6 a.m. Northbound lane closures will be required from exit 9 to the existing bridge on Wednesday, July 24, and from exit 9 to exit 11 in Rockland County on Thursday, July 25, and Friday, July 26. from 9 p.m. to 6 a.m.
Rockland:
Night time boring operations to investigate subsurface soil conditions will be conducted in the southbound shoulder of I-87/I-287 and will require a temporary right lane closure between exit 10 and the existing bridge on Monday, July 22, from 9 p.m. to 6 a.m.
Holiday Construction Schedule for TZ Bridge
For immediate release: June 28, 2013
NO WORK SCHEDULED JULY 4–NEW NY BRIDGE CELEBRATES INDEPENDENCE DAY
Tappan Zee Constructors, LLC (TZC) will not work on July 4 in observance of Independence Day.
Preconstruction activities will continue throughout the week; however, TZC will have no lane closures in order to keep traffic moving on the Thruway.
Ongoing operations:
– Cleaning and preparation for future construction of the Thruway’s Rockland Bulkhead
– Construction of the temporary Westchester work trestle which includes pile driving operations that will occur weekdays from 7 a.m. to 7 p.m. (except for July 4)
– Survey inspections on existing bridge
– Rockland environmental monitor installations continue
– Geotechnical land borings
– Mobilization at the Exit 10 staging area
– Support for river-based work from the Rockland shoreline
Westchester:
Limited geotechnical analysis boring operations continue this week on Thruway property and will not require lane closures as work will be performed behind barriers. Work may be scheduled between the hours of 7 a.m. and 3:30 p.m.
Rockland:
Limited geotechnical analysis boring operations continue this week on Thruway property and will not require lane closures as work will be performed behind barriers. Work may be scheduled between the hours of 7 a.m. and 3:30 p.m.