ROCKLAND TEMPORARY TRESTLE CONSTRUCTION BEGINS

Print Friendly

update

For immediate release: August 23, 2013

Work is scheduled to begin the week of August 26 on the Rockland trestle, which is the second temporary work platform to be constructed as part of the New NY Bridge Project.

The work will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to a maximum of 7 a.m. to 7 p.m. on weekdays and, occasionally, on Saturdays from 12 noon to 7 p.m. The trestle is a work platform that will eventually support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required near the Rockland shoreline

Impact pile driving will continue as part of the ongoing test pile program and will continue through October at various locations for future pile foundations. This work will be performed from 7 a.m. to 7 p.m. on weekdays and, occasionally, on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

Beginning Monday, August 26 through Wednesday, August 28, one northbound right hand lane and shoulder on I-87/I-287 between the existing Tappan Zee Bridge and Interchange 11 in Nyack will be closed from 9 a.m. to 3 p.m. for the installation of concrete traffic barriers to delineate traffic from the construction zone to ensure safety for traveling public and work crews.

Additional geotechnical borings to support design will be conducted on the river at various locations. Operations will run 24 hours a day, Monday through Friday.

Tappan Zee Constructors (TZC) will continue dredging operations in the Hudson River as part of the New NY Bridge Project. Dredging will occur through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.

Dredging crews will work 24/7 starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.

Ongoing operations:
– Test pile program

– Rockland bulkhead construction (including fence & gates) and Dock Extension at Rockland (under existing bridge)

– Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.

– Survey inspections on existing bridge

– Mobilization at the exit 10 staging area

– Support for river-based work from the Rockland shoreline
Rockland:
TZC will be installing temporary noise barriers along the right of way adjacent to I-87/I-287 near Ferris Lane. Fencing and sidewalk work will continue along River Road in South Nyack north of the existing bridge. This work is part of the bulkhead construction area and will be performed on weekdays between 7 a.m. and 3 p.m. At times, River Road will be limited to one lane with flag persons in place to ensure the safe flow of traffic.