LARGE CRANES START TO ARRIVE ON THE HUDSON RIVER THIS WEEK

Print Friendly

update

Two large barge-mounted cranes that will be used to place permanent piles for the substructure of the New NY Bridge Project will arrive throughout the next two weeks. Upon arrival, crews will start to assemble each crane and moor them until the test pile operations begin in mid-July. The cranes will be moored on the north side of the bridge closer to the Rockland County side of the Hudson River.


Neither of these cranes are the Left Coast Lifter, which is set to arrive late this year.

Work will also begin next week on the New York State Thruway Authority’s Rockland bulkhead area located on River Road in South Nyack. Work includes clearing of the site and construction of a larger bulkhead that will be used for staging of equipment.

Ongoing operations:
– Construction of the temporary Westchester work trestle which includes pile driving operations occurring weekdays between 7 a.m. and 7 p.m.
– Survey inspections on existing bridge
– Environmental monitoring activities
– Geotechnical land borings
– Mobilization at the Exit 10 staging area
– Support for river-based work from the Rockland shoreline

Westchester:

Limited geotechnical analysis boring operations continue this week on Thruway property and will not require lane closures. Work activities will be conducted between 7 a.m. and 3:30 p.m. Monday through Friday.

Rockland:

Limited geotechnical analysis boring operations continue this week on Thruway property and will not require lane closures due to work being performed behind barriers. Crews will also inspect and clean the 72-foot storm sewer line that services the existing Thruway property. Work is scheduled between the hours of 7 a.m. and 3:30 p.m. Monday through Friday. 

Some property information provided by CoStar, Loopnet, HGAR, Yelp, Rand Commercial Services and other public sources.