|
Archives for February 2015
Falcons Swoop In See Tappan Zee Peregrines Live Via Webcam
Coming to you live from high above the Hudson River are the fastest members of the animal kingdom! The Tappan Zee Bridge’s peregrine falcons have returned to their man-made nest box to prepare for the nesting season and can be viewed on the project’s “FalconCam.”
Installed in the steel super structure of the existing bridge, the nest box is equipped with a live, 24/7 FalconCam, accessible here.
The remote FalconCam, located outside the nest box, provides close-up views of the lives of these amazing migratory raptors, which recently came back to reproduce. Peregrine eggs typically are laid in February and March and chicks hatch approximately one month later. Viewers may be able to watch as the chicks peck their way out of their eggs and are then fed and cared for by their parents.
As construction on the New NY Bridge project continues, a 100-foot buffer area is in place to help protect the falcons during their nesting period.
Maintained and monitored by the New York State Thruway Authority, the nest box evetappan zeentually will be relocated to a new perch in the towers of the new bridge.
Learn more about the Tappan Zee falcons.
WINTER WEATHER WILL CONTINUE TO LIMIT WORK DURING THE WEEK OF FEBRUARY 16
Project Update:
WINTER WEATHER WILL CONTINUE TO LIMIT WORK DURING THE WEEK OF FEBRUARY 16
No construction work is scheduled for President’s Day, Monday, Feb. 16 on the New NY Bridge project.
Freezing temperatures and winter weather in the Hudson Valley will continue to limit operations at the project site during the week of Feb. 16. Tappan Zee Constructors, LLC (TZC) has included a two-month winter shutdown in its schedule to account for winter weather conditions.
TZC’s inclement weather preparation protocols include having tug boats on the water at all times, inspecting and adjusting all mooring lines, inspecting crane barges and securing all equipment, moving the large majority of cranes to shallow water moorings and taking all smaller crew boats out of the water. Additionally throughout every storm, TZC uses video and GPS to monitor the entire fleet of project vessels from its security operations center.
As weather permits, landside crews are working to assemble formwork that will shape the bridge’s landings on the Rockland and Westchester shorelines. The abutments, which will be made of steel and concrete, will serve as strong bases where the new crossing meets the landside roadways.
Pile Driving and Other Construction Activity
Construction will continue in the Hudson River as crews place the foundations of the new bridge. The work includes pile driving from 7 a.m. to 7 p.m., Tuesday through Friday and noon to 7 p.m., Saturday.
TZC also will continue limited concrete placement for foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and delivered by truck to the Rockland trestle located off the New York State Thruway (I-87/I-287) southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.
Westchester landing foundation operations continue as crews work to construct the land based piers and abutment for the new bridge.
Additional work includes:
• Pile cap foundation construction
• Main span foundation construction
• River Road utility work
• Support for river-based work from the Rockland trestle
• Survey inspections on the existing bridge
Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.
More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.
Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.
All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions
Project Update: Winter Weather Limits Operations
WINTER WEATHER CONTINUES TO LIMIT OPERATIONS AT NEW NY BRIDGE PROJECT SITE DURING THE WEEK OF FEBRUARY 9
Freezing temperatures and winter weather in the Hudson Valley continue to limit operations at the New NY Bridge project site. Tappan Zee Constructors, LLC (TZC) has included a two-month winter shutdown in its schedule to account for winter weather conditions.
During the week of February 9, TZC will continue limited operations.
TZC’s inclement weather preparation protocols include having tug boats on the water at all times, inspecting and adjusting all mooring lines, inspecting crane barges and securing all equipment, moving the large majority of cranes to shallow water moorings and taking all smaller crew boats out of the water. Additionally throughout every storm, TZC uses video and GPS to monitor the entire fleet of project vessels from its security operations center.
As weather permits, landside crews are working to assemble formwork that will shape the bridge’s landings on the Rockland and Westchester shorelines. The abutments, which will be made of steel, concrete, will serve as strong bases where the new crossing meets the landside roadways.
Pile Driving and Other Construction Activity
As much as allowed by weather conditions, construction will continue in the Hudson River, where crews are placing the foundations of the new bridge. The work includes pile driving from 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.
TZC also will continue limited concrete placement for foundations near the South Nyack shoreline. The concrete for this work is being acquired from local concrete suppliers and delivered by truck to the Rockland trestle located off the New York State Thruway (I-87/I-287) southbound access ramp. Trucks exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.
Westchester landing foundation operations continue as crews work to construct the land based piers and abutment for the new bridge.
Additional work includes:
- Pile cap foundation construction
- Main span foundation construction
- River Road utility work
- Support for river-based work from the Rockland trestle
- Survey inspections on the existing bridge
Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.
More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.
Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.
All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.