Archives for January 2015

NYS Thruway Lane Closures for Jan 28-29,2015

For immediate release: January 23, 2015 

TWO LANES OF SOUTHBOUND NEW YORK STATE THRUWAY (I-87/I-287) CLOSED OVERNIGHT WEDNESDAY JAN. 28 AND THURSDAY JAN. 29

Two lanes of the southbound New York State Thruway (I-87/I-287) will be closed between The Tappan Zee Bridge Toll Plaza in Tarrytown and exit 8A (Elmsford – NY Route 119 – Saw Mill River Parkway North) during the overnights of Tuesday, January 27 and Wednesday, January 28. The two overnight closures will occur between 7 p.m. and 5 a.m. and are necessary to accommodate work on an electronic message sign facility.

Bridge Abutment Work Continues

Tappan Zee Constructors, LLC (TZC) will continue assembling formwork that will shape the bridge’s landing on the Rockland and Westchester shorelines. The abutments, which will be made of steel, concrete and earth, will serve as strong bases for where the new crossing meets the landside roadway.

Pile Driving and Other Construction Activity
Construction will continue in the Hudson River as crews place the foundations of the new bridge. Work will include pile driving from 7 a.m. to 7 p.m., Monday through Friday and noon to 7 p.m., Saturday.

TZC will continue limited concrete placement for foundations near the South Nyack shoreline. In the absence of the project’s floating batch plants, which were temporarily taken out of service last month after a silo failed, the concrete for this work will be acquired from local concrete suppliers and will be delivered by truck to the Rockland trestle located off of the New York State Thruway (I-87/I-287) southbound access ramp. Trucks will exit the trestle to the Thruway via the northbound access ramp. The access ramps are used only by construction vehicles, providing a safe route directly to the work site and reducing traffic impacts on local roads.

Westchester landing foundation operations continue as crews work to construct the land based piers and abutment for the new bridge.

  • Additional work includes:
  • Pile cap foundation construction
  • Main span foundation construction
  • River Road utility work
  • Support for river-based work from the Rockland trestle
  • Survey inspections on existing bridge

Boater Safety
The U.S. Coast Guard has established a Safety Zone surrounding 16 construction barge mooring locations at the project site. No unauthorized vessels are allowed in the Safety Zone. In addition, marine law enforcement will be enforcing the rules of the expanded Regulated Navigation Areas (RNAs) east and west of the Safety Zone. The RNAs stretch 500 yards north and 500 yards south of the existing bridge. Boaters are urged to transit the main channel with no wake at a maximum speed of 5 knots, and to use extreme caution on the river at all times.

More New NY Bridge boater safety information, including the U.S. Coast Guard Notice to Mariners and construction site maps, can be found here at NewNYBridge.com. An interactive map showing vessel locations on the Hudson River is also available here for recreational and commercial boaters to get updated information on this very active construction zone. The GPS tracking map is for informational purposes and not intended for navigation.

Mariners also should be aware that TZC will continue work in the vicinity of the side channels under the existing bridge. Additional temporary navigational lights have been installed to further define the 600-foot navigation channel under the main span. Permanent elements of the new bridge are lit per U.S. Coast Guard requirements, as are all moorings, barges and other equipment.

All lane closures are subject to change due to traffic, weather or emergency situations. Please visit http://www.thruway.ny.gov/travelers/map/index.html?layer=incidents for real-time information regarding traffic conditions.

NEW NY BRIDGE BIKE/PEDESTRIAN PATH

More Community Input Wanted on Parking Facility Concepts  for Rockland and Westchester

bike path

Residents and other interested stakeholders are invited to provide comments on the new bridge’s shared-use bike/pedestrian path parking concepts.

Once complete, the New NY Bridge to replace the Tappan Zee will offer Hudson Valley residents a safer and easier commute, as well as a brand new 3.1-mile-long shared-use path for pedestrians and bicycles with stunning Hudson Valley views. The path will be perfect for a leisurely stroll, a challenging run or an exhilarating ride.

 

The project team has been working closely with residents, elected officials and experts for more than a year to develop the best design for visitor parking and other amenities. We completed a comprehensive study to determine the amount of parking needed, and an environmental assessment of the options is underway. Public meetings will be held to present the findings of the environmental assessment and take more comments from the public before any plans are finalized.

 

Now, we want your input on the parking options.

 

Please click here to view parking concepts. Comments will be accepted through Friday, February 13, 2015, and can be made via mail, email or fac (see instructions below). 

 

At the Westchester landing, the parking facility is planned on Thruway Authority property off South Broadway in Tarrytown. This site offers ample space for both parking and amenities.

 

For the Rockland landing, a variety of community-generated concepts are being studied to provide sufficient parking and amenities – including one on Thruway property at exit 10. At the Village of South Nyack’s request, the bike/pedestrian path’s entrance was moved from Smith Avenue to Cornelison Avenue at South Broadway. A $250,000 grant was awarded to the village through the New NY Bridge project’s Community Benefits Program to study the feasibility of redeveloping exit 10.

 

The parking facility concepts can be viewed at NewNYBridge.com/SUP and public comments can be submitted as follows:

 

Mail: Brian Conybeare
Special Advisor to the Governor for the New NY Bridge Project
303 South Broadway, Suite 413
Tarrytown, New York 10591

 

Email: Info@NewNYBridge.com  

 

Fax: 914.524.5455

 

Thank you in advance for your comments!

 

Construction Milestone on the TZ Bridge

Another major construction milestone  on the Tappan Zee Bridge project.

“To get to this point is very big,” Tappan Zee Constructors construction services manager Ro DiNardo told The Journal News.

Over the coming weeks and months, there will be a whirlwind of activity on the $3.9 billion project in Rockland alone.

Watch them build this hulking structure known as an abutment, which is where the new crossing meets land.

http://lohud.us/1BJb9Iy

Lohud  Khurram Saeed, ksaeed@lohud.com, January 9,2015

New Year of Construction Looking Ahead to 2015

New Year of Construction
Looking Ahead to 2015

December 31, 2014 |

With a fleet of approximately 130 floating cranes, barges, tugboats and other vessels working on the New NY Bridge, construction continues to move forward. The coming year will see the completion of the new crossing’s foundations and an increasing number of bridge piers across the Hudson River.

Early in 2015, the I Lift NY super crane will make the first of what will be hundreds of heavy lifts by installing a 600-ton approach span pile cap, a task that no other crane on the job can handle. Next year will also bring the completion of phase one of pile driving (phase two is scheduled for 2017, after the landings of existing bridge are removed); the installation of numerous precast approach-span pile capsby the project’s floating cranes; and the completion of the main-span pile caps, which will support the soaring 419-foot main span towers. The bridge also will begin to take its finished form, as segments of the road deck are mounted on the steel girders that connect the approach span piers. With the placement of thousands of tons of concrete and steel in the coming year, the project is steadily progressing towards completion in 2018.

Individuals keen on observing progress of the New NY Bridge project firsthand are invited to visit the recently opened Westchester viewing platform in Tarrytown’s Scenic Hudson RiverWalk Park. The platform is equipped with telescopes and a spotter’s guide, which describes the wide array of equipment on the river. The Rockland viewing platform, which will be situated in Nyack’s Memorial Park, is under development and is slated to open in early 2015. The project’s day-by-day progress also can be tracked from the comfort of home, thanks to construction cameras situated at various vantage points on and around the project site and accessible from the project website.

Here’s to another year of progress on this historic project in 2015!