Archives for August 2013

Tappan Zee Bridge Labor Day Holiday Schedule 2013

update

For immediate release: August 30, 2013

NO IMPACT PILE DRIVING OR LANE CLOSURES SCHEDULED FOR LABOR DAY HOLIDAY WEEKEND, ROCKLAND BULKHEAD CONCRETE PLACEMENT TO COMMENCE

Tappan Zee Constructors, LLC (TZC) will not engage in any pre-construction activities that affect traffic through Monday, Sept. 2 in observance of Labor Day. No lane closures will be allowed until Tuesday Sept. 3 at 10am in order to avoid impacts on motorists during the busy Labor Day holiday travel weekend. In addition, no impact pile driving is scheduled until Tuesday September 3.

Dredging will continue 24/7 through Oct. 31. As outlined in the Final Environmental Impact Statement for the New NY Bridge project, the dredging window is designed to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.

Rockland bulkhead construction continues next week with concrete placement. Frequent concrete truck traffic is expected on certain designated roads in the villages of Nyack and South Nyack from 9 a.m. to 4 p.m. on Tuesday, Wednesday and possibly Thursday. TZC and the Thruway Authority have coordinated extensively with village leaders and local police to ensure safety and minimize impacts on traffic, the villages and their residents. Anyone with questions can call the New NY Bridge 24-hour Toll-Free Hotline: 1-855-TZ-BRIDGE.

Construction of the Rockland County trestle will continue and include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to a maximum of 7 a.m. to 7 p.m. on weekdays and, occasionally, on Saturdays from noon to 7 p.m. The trestle is a work platform that will support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required.

Impact pile driving will continue as part of the ongoing test pile program and will continue through October at various locations for future pile foundations during the same timeframe as above. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.

On Tuesday, Sept. 3, one northbound right hand lane and shoulder on I-87/I-287 near Exit 10 will be closed from 10 a.m. to 3 p.m. for shoulder work. The northbound right hand and shoulder lane will be closed at the same location from 10 a.m. to 12 noon on Wednesday, Sept. 4. On Friday, Sept. 6, one southbound right hand lane and shoulder on I-87/I-287 between the foot of the existing Tappan Zee Bridge and Exit 11 will be closed from 10 a.m. to 1 p.m. for shoulder work.

Ongoing operations:

Test pile program
Rockland bulkhead construction and Dock Extension at Rockland under existing bridge
Temporary Rockland trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
Survey inspections on existing bridge
Mobilization at the exit 10 staging area
Support for river-based work from the Rockland shoreline

ROCKLAND TEMPORARY TRESTLE CONSTRUCTION BEGINS

update

For immediate release: August 23, 2013

Work is scheduled to begin the week of August 26 on the Rockland trestle, which is the second temporary work platform to be constructed as part of the New NY Bridge Project.

The work will include daytime pile driving to install the temporary foundation piles needed to support the platform. Pile driving will be limited to a maximum of 7 a.m. to 7 p.m. on weekdays and, occasionally, on Saturdays from 12 noon to 7 p.m. The trestle is a work platform that will eventually support a crane for the construction of the westernmost section of the new bridge. The 1200-foot long platform helps reduce the amount of dredging required near the Rockland shoreline

Impact pile driving will continue as part of the ongoing test pile program and will continue through October at various locations for future pile foundations. This work will be performed from 7 a.m. to 7 p.m. on weekdays and, occasionally, on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

Beginning Monday, August 26 through Wednesday, August 28, one northbound right hand lane and shoulder on I-87/I-287 between the existing Tappan Zee Bridge and Interchange 11 in Nyack will be closed from 9 a.m. to 3 p.m. for the installation of concrete traffic barriers to delineate traffic from the construction zone to ensure safety for traveling public and work crews.

Additional geotechnical borings to support design will be conducted on the river at various locations. Operations will run 24 hours a day, Monday through Friday.

Tappan Zee Constructors (TZC) will continue dredging operations in the Hudson River as part of the New NY Bridge Project. Dredging will occur through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.

Dredging crews will work 24/7 starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.

Ongoing operations:
– Test pile program

– Rockland bulkhead construction (including fence & gates) and Dock Extension at Rockland (under existing bridge)

– Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.

– Survey inspections on existing bridge

– Mobilization at the exit 10 staging area

– Support for river-based work from the Rockland shoreline
Rockland:
TZC will be installing temporary noise barriers along the right of way adjacent to I-87/I-287 near Ferris Lane. Fencing and sidewalk work will continue along River Road in South Nyack north of the existing bridge. This work is part of the bulkhead construction area and will be performed on weekdays between 7 a.m. and 3 p.m. At times, River Road will be limited to one lane with flag persons in place to ensure the safe flow of traffic.

New NY Bridge Update August 16, 2013: LOAD TESTING FOR THE TEST PILE PROGRAM BEGINS; LANE CLOSURES ON BRIDGE

bridge

For immediate release: August 16, 2013

LOAD TESTING FOR THE TEST PILE PROGRAM BEGINS;
LANE CLOSURES ON BRIDGE

Tappan Zee Constructors, LLC (TZC) will begin testing both static and lateral loads this week as part of its test pile program.

These load tests are performed to ensure piles are capable of sustaining the design load of the new bridge. Testing will be conducted over a 40-hour period.

Impact pile driving will continue this week as part of the ongoing test pile program and will continue through October at various locations for future pile foundations. This work will be performed from 7 a.m. to 7 p.m. on weekdays and, at times, on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

Overnight lane closures will also be required in both directions on I-87/I-287 and the Tappan Zee Bridge due to various construction activities.

Beginning Monday, August 19 through the morning of Wednesday, August 21, one southbound right hand lane and shoulder between exit 11 and the Tappan Zee Bridge will be closed from 9 p.m. to 6 a.m. for the installation of concrete traffic barriers to facilitate the reconstruction of the Thruway maintenance ramp. Additionally, one southbound right hand lane on the Tappan Zee Bridge will be closed during this period for the installation of structural monitors.

Beginning Wednesday, August 21 through the morning of Saturday, August 24, one northbound right hand lane and shoulder between exit 9 and the Tappan Zee Bridge, as well as one northbound right hand lane on the Tappan Zee Bridge will be closed from 9 p.m. to 6 a.m. for the installation of structural monitors.

Additional geotechnical borings will be conducted on the river at various locations. Operations will run 24 hours a day, Monday through Friday.

TZC will continue dredging operations in the Hudson River as part of the New NY Bridge Project. Dredging will occur through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.

Dredging crews will work 24 hours a day, seven days a week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.

Ongoing operations:
· Test pile program
· Rockland bulkhead construction (including fence & gates) and Dock Extension at Rockland (under existing bridge)
· Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline

Rockland:
TZC will continue fencing and sidewalk work along River Road in South Nyack north of the existing bridge. This work is part of the bulkhead construction area and will be performed on weekdays between 7 a.m. and 3 p.m. At times, River Road will be limited to one lane with flag persons in place to ensure the safe flow of traffic.

DREDGING OPERATIONS AND TEST PILE PROGRAM IMPACT PILE DRIVING CONTINUE

For immediate release: August 9, 2013

update

Tappan Zee Constructors, LLC (TZC) will continue 24-hour-a day dredging operations in the Hudson River as part of the New NY Bridge Project.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use the main channel, reduce wake and use extreme caution while transiting the area in the vicinity of the Tappan Zee Bridge.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com under the boating safety icon.

Dredging will occur over a three-month period from August 1 through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.

Dredging crews will work 24-hours-a-day, seven-days-a-week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being properly disposed of at offsite locations.

Impact pile driving will continue this week as part of the ongoing test pile program and will continue through October 31 at various locations for future pile foundations. This work will be performed from 7 a.m. to 7 p.m. on weekdays and, at times, on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions and test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

Ongoing operations:
· Test pile program
· Geotechnical land borings
· Rockland bulkhead construction (including fence & gates) and Dock Extension at Rockland (under existing bridge)
· Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Rockland and Westchester environmental monitor installations
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline

Westchester:
Ongoing geotechnical boring activities will continue to support the developing design for the New NY Bridge Project.

Rockland:
TZC will continue fencing and sidewalk work along River Road in South Nyack north of the existing bridge. This work is part of the bulkhead construction area and will be performed between 7 a.m. and 3 p.m. Monday through Friday. River Road will be limited at times to one lane with flag persons in place to control traffic safely.

DREDGING OPERATIONS BEGIN, TEST PILE PROGRAM IMPACT PILE DRIVING ONGOING

new

Project Update

For immediate release: August 2, 2013

Tappan Zee Constructors, LLC (TZC) began 24 hour a day dredging operations today in the Hudson River as part of the New NY Bridge Project.

The U.S. Coast Guard has issued a revised Notice to Mariners with updated safety information, including a request that boaters use extreme caution within 1,000 feet of all construction barges as a safety precaution.

The Coast Guard boating safety information can be found the project website, www.NewNYBridge.com.

Dredging will occur over a three-month period from August 1 through October 31 to avoid negatively impacting migration and spawning patterns of local sturgeon populations and other fish species.

Dredging crews will work 24 hours a day, seven days a week starting from the main navigation channel end of the dredging footprint towards the shoreline on both the Rockland and Westchester County sides of the bridge. The operations will deepen the river’s shallow water level in the work zone by removing sediment from the river bottom. The dredged materials are being processed and properly disposed at offsite locations.

Impact Pile driving began this week as part of the ongoing test pile program and will continue over the next three months at various locations for future pile foundations. This work will be performed 7 a.m. to 7 p.m. on weekdays and at times on Saturdays from 12 noon to 7 p.m. The test pile program will verify subsurface conditions test structural load capacities in preparation for construction of the new bridge’s permanent foundation.

Ongoing operations:
· Test pile program
· Rockland bulkhead construction (including fence & gates)
· Dock Extension at Rockland (under existing bridge)
· Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Rockland and Westchester environmental monitor installations
· Geotechnical land borings
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline

Westchester:
Limited test-boring operations will continue on Thruway property near the Irving Neighborhood in Tarrytown. The work is scheduled to be conducted between the hours of 7 a.m. and 5 p.m. Monday, August 5 through Wednesday, August 6.

Rockland:
TZC, LLC will reconstruct the sidewalk along River Road in S. Nyack north of the existing bridge. This is part of the Bulkhead construction area and will be performed between 7 a.m. and 3 p.m. Monday, August 5 and Tuesday, August 6. River Road will be limited to one lane with flag persons in place to control traffic safely.

Survey activity will occur in the southbound lanes of I-87/I-287 and will require a temporary lane closure between exit 10 and the existing bridge from 10 a.m. to 3 p.m. Monday, August 5 and Tuesday, August 6.

Some property information provided by CoStar, Loopnet, HGAR, Yelp, Rand Commercial Services and other public sources.