Pile Driving Set To Begin This Week

The New Tappan Zee Bridge

For immediate release: July 26, 2013

TEST PILE PROGRAM IMPACT PILE DRIVING SET TO BEGIN,
ROCKLAND THRUWAY DOCK CONSTRUCTION GETTING UNDERWAY

Tappan Zee Constructors, LLC (TZC) is scheduled to begin impact pile driving as part of the ongoing test pile operation this week. The test pile installation will continue over the next two to three months at the proposed locations of the foundations for the New NY Bridge. The test pile program will verify subsurface conditions in the river and the structural capacity of the pilings.

Under the Final Environmental Impact Statement, the hours of impact pile driving are restricted to 7 a.m. to 7 p.m., Monday through Friday and 12:00 noon to 7 p.m. on Saturday. There is no impact pile driving allowed at night or on Sundays. Noise monitors are in place along the Rockland and Westchester shorelines and the data is available at www.NewNYBridge.com.

Construction of the New York State Thruway’s temporary dock at the Rockland Maintenance facility on River Road in South Nyack will begin the week of July 29. TZC will reconstruct a maintenance dock that was damaged during Superstorm Sandy. This new dock will allow the Thruway to continue its normal maintenance work on the existing Tappan Zee as the construction activities for the New NY Bridge get underway.

Orange and Rockland Utilities will install new utility poles near River Road in South Nyack to support utility relocations which are needed for the New NY Bridge project. These operations may require temporary lane closures and will be performed by the utility.

Ongoing operations:
· Test pile program
· Rockland bulkhead construction
· Temporary Westchester trestle construction including pile driving on weekdays from
7 a.m. to 7 p.m.
· Survey inspections on existing bridge
· Rockland and Westchester environmental monitor installations
· Geotechnical land borings
· Mobilization at the exit 10 staging area
· Support for river-based work from the Rockland shoreline

Westchester:
Survey crews will be conducting surveys in the toll plaza area in Tarrytown on Wednesday, July 31 requiring temporary closures of toll lanes conducted one at a time.

Rockland:
Geotechnical boring operations to investigate subsurface soil conditions will be conducted in the northbound lanes of I-87/I-287 and will require a temporary lane closure between the existing bridge to Interchange 10 in South Nyack from 10 a.m. to 3 p.m. on Monday, July 29 through Wednesday, July 31. Southbound lane closures will be required from Interchange 10 to the existing bridge between 10 a.m. and 3 p.m. on Thursday, August 1 and from 10 a.m. to 2 p.m. Friday, August 2.

ROCKLAND BULKHEAD CONSTRUCTION TO BEGIN–TEST PILE PROGRAM CONTINUES

update

FOR IMMEDIATE RELEASE; JULY 19, 2013

Construction of the Rockland Bulkhead will begin next week as crews enlarge the work platform in the New York State Thruway Authority’s Rockland maintenance area located on River Road in South Nyack.

The bulkhead will be part of the Thruway’s permanent dock and serve as the access point for Tappan Zee Constructors, LLC’s (TZC) Rockland trestle.  The trestle is the support platform that will allow TZC to build the foundations for the new bridge near the Rockland shoreline without dredging in that area.  TZC will utilize the bulkhead for support of construction throughout the entire project.

Orange and Rockland Utilities will install new utility poles near River Road in South Nyack to support utility relocations which are needed for the New NY Bridge project. These operations may require temporary lane closures and will be performed by the utility.

Test pile driving operations will be conducted over the next three months at proposed locations for pile foundations.  The test pile program will verify subsurface conditions in preparation for the construction of the bridge’s permanent foundation.

Multiple crews will conduct night time boring operations along I-87/I-287 in both directions in Westchester and Rockland Counties.  The night time operations are necessary due to lane closure restrictions during day time hours that are in place to keep traffic flowing over the current bridge. Boring operations began at exit 10 in Rockland County and continue to move west into Westchester County and then back to Rockland for one final boring location.

Ongoing operations:
– Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
– Survey inspections on existing bridge
– Rockland environmental monitor installations continue
– Geotechnical land borings
– Mobilization at the exit 10 staging area
– Support for river-based work from the Rockland shoreline
– Extension of Thruway’s Rockland maintenance dock

Westchester:
Night time boring operations to investigate subsurface soil conditions will be conducted in the southbound shoulder of I-87/I-287and will require a temporary right lane closure between the existing bridge and exit 9 on Tuesday, July 23, from 9 p.m. to 6 a.m.  Northbound lane closures will be required from exit 9 to the existing bridge on Wednesday, July 24, and from exit 9 to exit 11 in Rockland County on Thursday, July 25, and Friday, July 26. from 9 p.m. to 6 a.m.

Rockland:
Night time boring operations to investigate subsurface soil conditions will be conducted in the southbound shoulder of I-87/I-287 and will require a temporary right lane closure between exit 10 and the existing bridge on Monday, July 22, from 9 p.m. to 6 a.m.

VOTING SHOWS MAJORITY FAVOR NOISE BARRIERS FOR THE NEW NY BRIDGE

update

Project Update

For immediate release: July 19, 2013

Last month, the New York State Thruway Authority, the New York State Department of Transportation (NYSDOT), and the Federal Highway Administration (FHWA) invited local residents tovote on the placement of proposed noise barriers for the New NY Bridge Project.

“The public has spoken and they overwhelmingly support the construction of sound reducing traffic noise barriers as part of the New NY Bridge Project,” said Brian Conybeare, Governor Cuomo’s Special Adviser for the New NY Bridge Project. “This is another way we trying to make this the most inclusive and transparent infrastructure project in the history of the state. We will continue to include input from local residents and other stakeholders as the project moves forward.”

Noise barriers are recommended as a form of traffic noise abatement only if they are determined to be both feasible and reasonable. According to Thruway and NYSDOT noise policies, as well as FHWA noise regulations, once a noise barrier is deemed both feasible and reasonable, ‘benefited receptors’, defined as property owners and/or residents of properties that would receive at least a five decibel reduction in noise level as a result of the proposed noise barriers, have an opportunity to cast a vote either for or against its construction.

Public meetings were held in both Westchester and Rockland counties during the week of June 23. At the meetings, Tappan Zee Constructors, LLC explained the locations and heights of the proposed walls for the areas that met the noise mitigation requirements, along with any possible aesthetic preferences.

The voting results show the benefitted receptors overwhelmingly favor having noise barriers constructed as part of the New NY Bridge project. Overall, 306 ballots were sent to benefited receptors. The tabulated results from the vote appear below:

Barrier

Votes For

Votes Against

Results

Westchester East Sound Barrier

87

1

98% FOR BARRIER

Westchester West Sound Barrier

2

0

100% FOR BARRIER

Rockland North Sound Barrier

96

5

95% FOR BARRIER

Rockland South Sound Barrier

31

2

94% FOR BARRIER

NEW NY BRIDGE TEST PILE PROGRAM STARTS NEXT WEEK

The new NY bridge

 

For immediate release: July 12, 2013

NEW NY BRIDGE TEST PILE PROGRAM STARTS NEXT WEEK

Beginning the week of July 15, Tappan Zee Constructors, LLC will install the first test piles for the New NY Bridge.

The test pile operations will be conducted over the next three months at proposed locations for pile foundations. Work will start at the main span footings. Piles will be placed by utilizing both vibratory and impact installation techniques. The test pile program will verify subsurface conditions in preparation for the construction of the bridge’s permanent foundation.

Multiple crews will conduct night time boring operations along I-87/I-287 in both Westchester and Rockland Counties. The night time operations are necessary due to lane closure restrictions during day time hours that are in place to keep traffic flowing over the current bridge. Boring operations will begin at exit 10 in Rockland County and move west into Westchester County.

Ongoing operations

– Temporary Westchester trestle construction including pile driving on weekdays from 7 a.m. to 7 p.m.
– Survey inspections on existing bridge
– Rockland environmental monitor installations continue
– Geotechnical land borings
– Mobilization at the exit 10 staging area
– Support for river-based work from the Rockland shoreline

Westchester:
Night time boring operations to investigate subsurface soil conditions will be conducted in the southbound shoulder of I-87/I-287 and will require a temporary right lane closure between the existing bridge and exit 9 on Friday, July 19 from 9 p.m. to 6 a.m.

Rockland:
Night time boring operations to investigate subsurface soil conditions will be conducted in the southbound shoulder of I-87/I-287 and will require a temporary right lane closure between exit 10 and the existing bridge from 9 p.m. to 6 a.m. beginning Monday, July 15 through Thursday, July 18.

Tappan Zee Bridge: Former power plant site may be used as staging area – Builder could lease 30 acres in Tomkins Cove

Lohud July 9, 2013

Written by: Khurrum Saeed

TOMKINS COVE — The former Lovett power plant will likely serve as a staging area to build parts of the new Tappan Zee Bridge.

Tappan Zee Constructors, the team designing and building the $4 billion replacement crossing, is in final discussions with NRG Energy to lease the long-vacant 30-acre parcel in Tomkins Cove, team spokeswoman Carla Julian said Monday.

Also, Stony Point Supervisor Geoff Finn will meet at noon Friday with Tappan Zee Constructors officials to discuss plans for the riverfront property. The meeting is purely informational since NRG owns the land and is negotiating the deal.

“I’m excited because there’ll be some activity there,” Finn said of the site, which is off of Elm Avenue. “It would certainly be good for our tax base.”

Last week, Tappan Zee Constructors withdrew a proposal to lease a 10-acre property in the Village of Haverstraw, said real-estate agent Jim Damiani, who has been working with the consortium for six months regarding use of the former site of the Empire State Chair Factory. He said the builders provided a staging area plan to the village early last month.

“I got a message from them that they were withdrawing from any further discussion,” said Damiani, who works for Rand Commercial Services in New City. “I guess they’re not interested.”

The coal-fueled Lovett plant was torn down in 2008, when the previous owner opted not to upgrade to meet state environmental regulations.

The property has an assessed value of $875,000 with a $5.5 million market value, Stony Point Assessor Bill Beckmann said. NRG pays about $315,000 in annual property taxes to the town and the North Rockland Central School District.

How much more the town stands to receive by Tappan Zee Constructors’ presence remains to be seen, and it depends on what structures are installed.

“If they add value to the real property, they’ll be taxed accordingly,” said Beckmann, who will join Finn at Friday’s meeting.

Ninety percent of the materials that will be used to build the span will arrive by barge.

Some of that will be accomplished by building some of the larger components at an off-site staging area and floating them by barge to the work site.

Dredging is scheduled for next month and work on the main span is expected to begin in October.

A spokesman for NRG did not respond to phone messages Monday seeking comment.

ONGOING PRECONSTRUCTION ACTIVITIES CONTINUE ON THE NEW NY BRIDGE PROJECT

The new NY bridge

For immediate release: July 5, 2013

ONGOING PRECONSTRUCTION ACTIVITIES CONTINUE ON THE NEW NY BRIDGE PROJECT

Tappan Zee Constructors, LLC (TZC, LLC) will continue preconstruction activities the week of July 8 in Westchester and Rockland Counties.

Ongoing operations:

– Cleaning and preparation for future construction of the Thruway’s Rockland Bulkhead
– Construction of the temporary Westchester work trestle which includes pile driving operations that will occur between 7 a.m. and 7 p.m.
– Survey inspections on existing bridge
– Rockland environmental monitor installations continue
– Geotechnical land borings
– Mobilization at the Exit 10 staging area
– Support for river-based work from the Rockland shoreline

Lane closures will be in place on the right lane of northbound I-87/I-287 on Monday, Tuesday and Friday from 10 a.m. to 3 p.m. for installation of instrumentation to monitor the existing bridge during construction. Lane closures will also be in place on the southbound right lane of I-87/I-287 Wednesday and Thursday from 10 a.m. to 3 p.m. for the same activity.