SOIL SAMPLING AND SUBSURFACE UTILITY INVESTIGATIONS BEGIN

The New NY Bridge; For Immediate Release: April 26, 2013

Contact: Dan Weiller: (518) 471-5300

Soil sampling and subsurface utility explorations operations will be conducted within the Thruway’s right of ways.  Soil sampling is a requirement of any project that includes excavation work, in order to verify the soil content for proper disposal or reuse. These operations will be conducted between 7 a.m. and 5 p.m.

Surveying work for the New NY Bridge Project will continue during the week of April 29 as engineering crews conduct more design surveys at various locations in Rockland and Westchester in the vicinity of the project, including the Westchester Haul Road location on New York State Thruway property in Tarrytown.

Installation of construction monitoring devices is planned at several locations this week. These devices, which monitor vibration, noise, and air quality, will be in place for the duration of the project to record construction activity impacts.

Preconstruction surveys of properties located near the construction will continue next week. These operations will be conducted by engineering teams and will involve photographing the exterior and interior of structures. Tappan Zee Constructors is coordinating with the property owners for access.

Preconstruction geotechnical investigations will continue as small barge-based drilling equipment will work at various locations throughout the project footprint in the Hudson River. The crews are conducting preconstruction geotechnical surveys to determine soil conditions where future piles will be installed for the new span. Noise levels from the equipment will be at a minimum. The river-based operations will run continuously 24 hours a day Monday through Friday and possibly Saturday.

Westchester:
Soil Sampling will begin on Thruway Authority right-of-ways. Limited test-boring operations will continue on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 a.m. and 5 p.m. Monday through Friday.

Rockland:
There are no land-based boring operations scheduled for the Rockland area for the week of April 29.

 

Environmental sensors to be installed near Tappan Zee construction

Lohud.com; By Khurram Saeed and Theresa Juva-Brown

April 30, 2013  TARRYTOWN — As the Tappan Zee Bridge project continues to ramp up, crews this week will begin installing environmental monitors that will allow residents to track noise, dust and vibration levels during the five years of construction.

The sophisticated shoebox-sizes devices with special sensors will be placed on top of poles at eight locations — four in Tarrytown and four in South Nyack. Losee Park in Tarrytown is set to get the first one by Wednesday.

Devices also will be installed at the Quay, an 89-unit condo complex in Tarrytown, south of the bridge in the neighborhood of Irving, and on New York State Thruway Authority property near South Broadway, state officials said.

Tappan Zee Constructors, the team engineering and constructing the $3.9 billion bridge, the Thruway Authority and community leaders are working to pin down specific locations for the devices in Rockland County, said Brian Conybeare, a special adviser on the project.

“The installation process is just getting under way, but once construction starts the public will be able to view the data from the monitoring stations 24 hours a day on our website, www.newnybridge.com,” he said.

Sensors devoted just to measuring construction vibrations have already been installed on the piers of the existing Tappan Zee Bridge, officials said.

Among the likely Rockland locations to receive a monitor is the 120-unit Salisbury Point Cooperative in South Nyack. TZC also wants to add a device at South Nyack Village Hall, but a village representative said officials had not been consulted about it.

Jerry Ilowite, head of South Nyack’s Tappan Zee Bridge task force, said TZC was supposed to present a monitoring and mitigation plan that would let the village weigh in on the best locations for the devices.

“I have no idea what they’re going to monitor or where or why they’re choosing the locations that they are,” Ilowite told The Journal News on Monday. “We have had no opportunity to contribute at all.”

After The Journal News inquired about the situation, a TZC representative called Ilowite on Monday afternoon to schedule a meeting.

The project team also plans to start taking photos and reports of property conditions before construction starts. This is done in case property owners later claim vibrations from the work damaged their homes.

Tori Weisel, president of the Irving Neighborhood Preservation Association, said about a dozen Irving residents plan to meet with TZC officials Wednesday to discuss which homes will be eligible for preconstruction surveys.

Meanwhile, the state has started to install new fencing along Van Wart Avenue to shield homes from traffic on the Thruway maintenance road. Weisel said more steps are needed.

“There is progress … but the true issue is not that fencing — it’s sound barriers and making sure our foundations are not rocked and cracked,” she said

State Cops To Relocate During T.Z. Rebuilding – Tarrytown Barracks Will Move To W. Nyack

LoHud.com April 27, 2013

Written by  Theresa Juva Brown

http://www.lohud.com/apps/pbcs.dll/article?AID=/201304262159/NEWS/304260115

Tappan Zee Constructors is finalizing a deal that would temporarily move state police and Thruway Authority facilities from Tarrytown to West Nyack during construction of the new Tappan Zee Bridge, state officials confirmed Friday.

TZC is about to sign a lease for a 42,000-square-foot warehouse at 160 N. Route 303. It is the former site of The Journal News Rockland printing operation and is now owned by Hauser Brothers, a construction contracting group.

This latest deal comes just weeks after Tappan Zee Constructors moved hundreds of project employees to new, leased office space on Old White Plains Road in Tarrytown.

“It’s exciting,” said Paul Adler, vice president at Rand Commercial Services, which is handling the West Nyack deal. “Folks, particularly in commercial real estate, have been suffering. … To finally see the light at the end of the tunnel — and it’s not a train coming at you — is critically important.”

As part of the bridge project contract, TZC will tear down the existing state police and Thruway buildings on South Broadway and use the land as a construction staging area.

After the $4 billion project is completed, TZC will rebuild those facilities. In the meantime, it has agreed to pay to relocate those agencies.

The asking price for the West Nyack warehouse was $6.25 per square foot, according to a listing on Rand’s website.

Adler said Rand has been preparing to assist with the space needs of the Tappan Zee project since last year, including setting up a Web page, www.tappanzeebridgeinfo.com, which advertises various types of available properties in Westchester and Rockland.

In addition to commercial properties, Adler expects a growing demand for housing as project workers arrive in the area. That will benefit everyone, he said.

“Everything from the dry cleaners to the pizza shop to restaurants and hotels, all of them get a shot in the arm,” he said. “Coming out of the long, dark, deep recession, this is just the kind of bump people need to restart the engine.”

In fact, Wedged-in Deli and Catering at 605 Old White Plains Rd., not far from the new TZC office, is already getting a bump as occupants of the newly filled office space turn to the family operated business for their food needs.

“They have been ordering some catering from us and coming in during lunchtime,” deli manager Harrison Yu said. “It’s helping us, but we are definitely expecting more as construction goes full on.”

Brian Conybeare, Gov. Andrew Cuomo’s special adviser on the project, called such signs “just the beginning of the positive economic impact” the project will have on the region.

 

 

 

Rand Commercial Services Weekly Real Estate Report- A Bridge To The Future

 

 

 

 

Are you a business looking to secure work related to the New NY Bridge project?

New City Patch; April 23, 201

By Krista Madsen

http://newcity.patch.com/articles/tappan-zee-bridge-business-to-business-forums-f6ab42a7?ncid=newsltuspatc00000001

The New York State Thruway Authority, Tappan Zee Constructors, New York State Department of Labor and the New NY Works Program will provide information for businesses wanting to learn about contract opportunities related to the new Tappan Zee Bridge project 10 a.m. Wednesday at the Crowne Plaza in Suffern.

Representatives of Tappan Zee Constructors, the NYS Dept. of Labor and Brian Coneybeare, special advisor to Gov. Andrew Cuomo on the project, will be among those making presentations.

To register for this event, visit:
http://www.labor.ny.gov/careerservices/new-ny-bridge.shtm

There will also be an event 2:30 p.m. today (April 23, 2013) at the Westchester Marriott in Tarrytown.

New NY Bridge Project Update April 19, 2013

The new NY bridge

April 19, 2013

New NY Bridge surveying crews to conduct multiple operations

Surveying work for the New NY Bridge Project will continue during the week of April 22 as engineering crews conduct more design surveys at various locations in Rockland and Westchester in the vicinity of the project, including the Westchester Haul Road location on New York State Thruway property in Tarrytown.

Installation of construction monitoring devices is planned at several locations this week. These devices, which monitor vibration, noise, and air quality, will be in place for the duration of the project to record construction activity impacts.

Preconstruction surveys of properties located near the construction will begin next week. These operations will be conducted by engineering teams and will involve photographing the exterior and interior of structures. Tappan Zee Constructors is coordinating with the property owners for access.

Preconstruction geotechnical investigations will continue as small barge-based drilling equipment will work at various locations throughout the project footprint in the Hudson River. The crews are conducting preconstruction geotechnical surveys to determine soil conditions where future piles will be installed for the new span. Noise levels from the equipment will be at a minimum. The river-based operations will run continuously 24 hours a day Monday through Friday and possibly Saturday.

Westchester:
Limited test-boring operations will continue on land under the existing bridge and just to the north at the proposed bridge locations. These operations are being conducted on Thruway property and will not affect traffic in any way. The work is scheduled to be conducted between the hours of 7 am and 5 pm Monday through Friday.

Rockland:
There are no land-based boring operations scheduled for the Rockland area for the week of April 22.